Kaleshwaram Lift Irrigation Project
Kaleshwaram Lift Irrigation Project is located in India
Kaleshwaram Lift Irrigation Project
Location of Kaleshwaram Lift Irrigation Project in India
Kaleshwaram Lift Irrigation Project is located in Telangana
Kaleshwaram Lift Irrigation Project
Kaleshwaram Lift Irrigation Project (Telangana)
LocationKaleshwaram, Bhupalpally, Telangana, India
Coordinates17°44′27″N 78°41′26″E / 17.74083°N 78.69056°E / 17.74083; 78.69056
PurposeIrrigation, power, and transport
StatusCompleted/Inaugurated
Construction began2016
Opening date21 June 2019
Construction cost₹ 80000 crores[1]
Operator(s)Telangana Irrigation Department
Dam and spillways
ImpoundsGodavari River
Heightup to top of earth dam above the lowest river bed.
Spillway typeChute spillway
Website
https://www.kaleshwaramproject.com/

The Kaleshwaram Lift Irrigation Project (KLIP) is a multi-purpose irrigation project on the Godavari River in Kaleshwaram, Bhupalpally, Telangana, India.[2] Currently the world's largest multi-stage lift irrigation project,[3] its farthest upstream influence is at the confluence of the Pranahita and Godavari rivers. The Pranahita River is itself a confluence of various smaller tributaries including the Wardha, Painganga, and Wainganga rivers which combine to form the seventh-largest drainage basin on the subcontinent, with an estimated annual discharge of more than 6,427,900 acre-feet (7,930 cubic hectometres) or 280 TMC. It remains untapped as its course is principally through dense forests and other ecologically sensitive zones such as wildlife sanctuaries.

The Kaleshwaram Lift Irrigation Project[4][5] is divided into 7 links and 28 packages spanning a distance of approximately 500 km (310 mi) through 13 districts and utilizing a canal network of more than 1,800 km (1,100 mi).[6] The project aims to produce a total of 240 TMC (195 from Medigadda Barrage, 20 from Sripada Yellampalli project and 25 from groundwater), of which 169 has been allocated for irrigation, 30 for Hyderabad municipal water, 16 for miscellaneous industrial uses and 10 for drinking water in nearby villages, with the remainder being estimated evaporation loss. The project aims at increasing total culturable command area (the sustainable area which can be irrigated after accounting for both upstream and downstream factors) by 1,825,000 acre⋅ft (2,251 hm3) across all 13 districts in addition to stabilizing the existing CCA.

On 21 June 2019, the project was opened by Telangana Governor E. S. L. Narasimhan and Chief minister K. Chandrashekar Rao. National Green Tribunal declared the Scheme is constructed without following the statuary provisions with regard to environmental aspects.[7]

Four major pumping facilities manage the project's outflow, the largest at Ramadugu (Medaram, Annaram and Sundilla being the others) is also likely to be the largest in Asia once consistent measurements are available,[8] requiring seven 140 MWh (500 GJ) pumps designed and manufactured specifically for the project by the BHEL.[9] The Engineering giant Megha Engineering and Infrastructures Limited built 15 of 22 Pump houses and undertook major part of the project.

Project details

In addition to constructing new reservoirs, Kaleshwaram also rejuvenates existing ones.[10]

Existing reservoirs

Reservoir Location Capacity

(in Tmcft)

Sripada Yellampalli project Yellampalli village 20.175
Mid Manair Dam 25.875
Upper Manair Dam 2.20
Kaddam Project 7.60
Masani Tank 0.13
Total 55.98

New reservoirs

Reservoir Location Capacity

(in Tmcft)

FRL(in m)
Medigadda Barrage 16.17 100.0
Annaram Barrage Annaram 10.87 120.0
Sundilla Barrage 8.83 130.0
Medaram Online storage Medaram 0.78
Ananthagiri Online storage Ananthagiri 3.50
Sri Ranganayaka Sagar Imambad (chandlapur) 3.50
Sri Komaravelli Mallanna Sagar Tadkapally 50.00
Malkapet Online storage 3.0
Konda Pochamma Online storage Pamulaparthy 15.00
Amarlabanda Online storage 5.00
Katchapur 2.50
Thimmakka Palli 3.00
Issaipet 2.50
Bhoompally Online storage 9.0
Gujjal Online storage 1.50
Katewadi Online storage 5.00
Mothe Online storage 2.90
Kondem Cheruvu 3.50
Gandamalla Online storage 9.87
Baswapuram Online storage 11.39
TOTAL 147.710
  • Link-I: From Medigadda Barrage on Godavari River to Sripada Yellampalli Project (30,000 acres)
  • Link-II: From Sripada Yellampalli Project to Mid Manair Dam
  • Link-III: From Mid Manair Dam to Upper Manair Reservoir (86,150 acres)
  • Link-IV: From upper Manair Dam to Konda Pochamma Reservoir (595,754 acres)
  • Link-V: From Anicut to Chityala (243,500 acres)
  • Link-VI: From Sri Komaravelli Mallanna Sagar to Singur Dam (280,296 acres)
  • Link-VII: From SRSP Foreshore to Nizam Sagar Canals and to Dilawarpur and Hangarga village for Nirmal and Mudhole Constituency (590,000 acres)

Total: 1,65,700 acres (New ayacut) Apart from: 1,875,00+ acres (Stabilisation of existing ayacut)

Gravity Canals & Tunnels for distribution

1. Gravity Canal - 1,531 km

2. Gravity Tunnel - 203 km

3. Pressure Mains / Delivery Mains - 98 km

Link-I: From Medigadda Barrage on Godavari River to Sripada Yellampalli Project

Water will be reverse pumped from the confluence point of Godavari and Pranahita Rivers to Sripada Yellampalli Project with the help of 3 barrages (Medigadda, Annaram and Sundilla) and 3 lifts.

As of June 2019, lifts are being commissioned with provision to lift 2 TMC (56,63,36,93,184 liters) of water per day from Medigadda. The water is lifted to backwaters of Annaram barrage. Again from Annaram barrage to Sundilla barrage. Finally from Sundilla to Sripada Yellampalli Project. Civil works are being executed to lift 3 TMC per day but pumps are being installed to lift only 2 TMC. If need be, only pumps would need to be installed to increase capacity by one more TMC.

Link-II: From Sripada Yellampalli Project to Mid Manair Dam

A new balancing reservoir is also being proposed in the outskirts of Hyderabad of 20–30 TMC to store water. The water will be supplied to this balancing reservoir in the same link.

Link-V: From Anicut to Chityala

From Anicut, a series of gravity canals and a small tunnel of 1.2 km are planned to transfer water to Gandamalla Reservoir and Baswapuram Reservoir. Thereafter, gravity canals are planned towards Chityal Mandal and its villages.

Link-VI: From Sri Komaravelli Mallanna Sagar to Singur Dam

From Sri Komaravelli Mallanna Sagar, another sequence of gravity canals, tunnels and lifts are used to transfer water to Singur Dam. Apart from that, if need be, water can be transferred to Nizam Sagar Project and from there, to SRSP.

Link-VII: From SRSP Foreshore to Nizam Sagar Canals and to Dilwarpur and Hangarga village for Nirmal and Mudhole Constituency

From the foreshore waters of SRSP, water will be transferred to reservoirs at Hangarga and Dilwapur villages. Apart from this, existing reservoirs like Masani Tank and kondem Cheruvu will also be linked. Canals under Nizam Sagar will also be irrigated.

Water lifting

The chief minister has said that every year about 400 TMC of water will be lifted. On the contrary, over the past 5 years, only about 150 TMC of water has been lifted and out of this 100 TMC was released back in to Godavari. Therefore on an average only about 10 TMC of water is lifted per year. Every year water lifting is usually started in late June and July, and few TMC is lifted to the several barrages. However, in July projects get sufficient rain water, that necessitates releasing the lifted water back in to Godavari. Over the past 5 years, lifting and releasing back is a recurrent phenomenon that calls for an intelligent water lifting plan. On the other hand, 10 TMC of water lifting per year is quite flow and does not justify the huge amount of money spent. For example, with 10 TMC of water, 1 lakh acres could be irrigated. The annual expenditure for the project is estimated to be beyond Rs. 20,0000 crore per year. This implies that per acre annual expenditure is 20 lakh, which is astronomically high. Such very poor cost benefit ratios make the project a financial disaster for the state.

Project Economics

The project requires about 5,900 MW of electricity to run its several large water pumps. Assuming, on average, the pumps require constant running for two months during the monsoon period, 24 hours a day, the total electricity consumption would be 849 crore units. Taking a unit electricity charge of Rs. 8.0 per kWh, the annual electricity cost is going to be Rs. 7000 crores per year. Assuming the project irrigates about 15 lakh acres, the electricity cost for irrigation is about Rs. 46,666 per acre per year. The chief minister has said that the project requires about Rs. 5000 crore annually for electricity charges.[11] On the other hand, the state irrigation department had allocated Rs.7000 crores for electricity charges in its 2020 budget.[12]

The project was mainly funded with the money obtained through loans. Assuming an existing loan of Rs. 80,000 crore, at an interest rate of 6% that needs to paid up over a period of 30 years, the annual loan repayment charge is about Rs. 5760 crores per year. This implies an additional charge of Rs. 38,400 per acre per year towards the loan repayment. Therefore, the total cost of irrigation per acre is approximately Rs. 85,000 per acre per year. On the other hand, the net profit from the cultivation of the main crop i.e., paddy, could be expected to be around Rs.40,000 per acre per year,[12] assuming two crops in a year. These numbers raise questions about the financial viability of the project.

A recent report by the comptroller and auditor general of India (CAG) has pointed out that the cost to benefit ratio of the project is 1:0.75 in contrast to the state govt.'s claim of 1:1.5.[13] In addition, by taking in to account the escalated costs for lifting the third TMC, the ratio comes down to 1:0.52. According to the report, the annual operational costs for irrigating an acre of land is Rs. 46,364 cr. The annual electricity costs are estimated to be Rs. 10,374 cr. Despite the negative report by CAG on the financial viability, the state govt. has made no effort refute the report.

Project Execution

Indian Public sector Enterprise BHEL is executing this project and has already commissioned 16 pumping units.[14][15]

Environmental law violations

In October 2020, the National Green Tribunal, India's court for environmental issues, directed the Telangana government to halt work on the KLIP except the drinking water supply component. A petition had been filed by a farmer from Siddipet district, whose land was affected by the KLIP. The National Green Tribunal found, on hearing his petition, that the environmental clearances for the KLIP had not been obtained before the project, as is required by law, but had been granted by the Union Government of India after work on the project had already begun by the Telangana government. The National Green Tribunal has directed the Indian government's Ministry of Environment, Forests and Climate Change to constitute a committee to investigate the illegally granted clearances, and to file a report with them within six months.[16][17][18]

See also

References

  1. "KALESHWARAM PROJECT" (PDF). www.irrigation.telangana.gov.in/icad/projectsMajUp#.
  2. "Why is Telangana's Kaleshwaram Lift Irrigation Project important?". The Hindu. 1 July 2017. ISSN 0971-751X. Retrieved 20 April 2018.
  3. "Kaleshwaram project: World's largest multi-stage lift irrigation project inaugurated in Telangana". Retrieved 22 June 2019.
  4. "EXECUTIVE SUMMARY FOR THE PROPOSED KALESHWARAM PROJECT" (PDF). tspcb.cgg.gov.in. Retrieved 3 April 2021.
  5. "Kaleshwaram Project Summary" (PDF). Telangana State PCB.
  6. "Kaleshwaram Project" (PDF). Telangana Government Irrigation.
  7. "Order of the NGT regarding Kaleshwaram Lift Irrigation Scheme dated 20/10/2020". Retrieved 20 October 2020.
  8. Kumar, V. Rishi (20 June 2009). "Kaleshwaram — the making of an engineering marvel". The Hindu Business Line. Retrieved 9 August 2019.
  9. "BHEL commissions 1 more unit of Kaleshwaram irrigation project in Telangana". Moneycontrol. 5 August 2019. Retrieved 13 August 2019.
  10. "Kaleshwaram Project [ Full Details ] Telangana - 2019". kaleshwaramproject.com/. Retrieved 9 September 2019.
  11. "CM KCR Serious Warning over Kaleshwaram Project Electricity Bill | NTV". YouTube.
  12. 1 2 "Telangana: Irrigation dept to spend 50% of its budget on power bill | Hyderabad News - Times of India". The Times of India. 7 July 2020.
  13. "CAG Report on Kaleshwaram". hmtvlive.com. Retrieved 18 December 2023.
  14. "BHEL Commissions two more units of Kaleshwaram Lift Irrigation Scheme Package-6 (7x116 MW) in Telangana" (PDF). bhel.com. Retrieved 18 December 2023.
  15. "BHEL commissions 14 Pumping Units of Kaleshwaram Lift Irrigation Scheme in Telangana in a record period of six months" (PDF). bhel.com. Retrieved 18 December 2023.
  16. "NGT red-flags Kaleshwaram project: Green clearance was in violation of law, halt work". The Indian Express. 21 October 2020. Retrieved 21 October 2020.
  17. Pulipaka, Balu (21 October 2020). "NGT says environmental clearance for Kaleshwaram violates law". Deccan Chronicle. Retrieved 21 October 2020.
  18. "Kaleshwaram irrigation project got environmental clearance 'ex post facto' in violation of law: NGT". The Economic Times. Retrieved 21 October 2020.

(Telangana India)

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.