The 2006 Argentine nuclear reactivation plan is a project to renew and reactivate the development of nuclear power in Argentina. The main points of the plan were announced by the Argentine government through Planning Minister Julio de Vido during a press conference on 23 August 2006.[1][2] They include:

  • Finishing the incomplete Atucha II Nuclear Power Plant, which was started on July 14, 1981. Construction was halted in 1994, and resumed in late 2006. Atucha II was scheduled to start up in 2012.[3] The plant began to produce energy on June 27, 2014.[4] It reached its first criticality on June 3, 2014; the first grid connection was on June 25, 2014; the first commercial operation began on May 26, 2016.
  • Researching the feasibility of the construction of a fourth nuclear plant in Argentina.
  • Extending the operational life of the Embalse power plant, originally projected to end in 2011.
  • Resuming the domestic production of enriched uranium. The reactor has a net capacity of 693 MWe and a gross capacity of 745 MWe.
  • Working on a prototype CAREM, a low-power nuclear reactor[5] which could also be installed in one of the TR-1700 class submarines currently under construction.

In 2010, an agreement was signed with Atomic Energy of Canada Limited (AECL) for the construction of Atucha III Nuclear Power Plant and the upgrade of Embalse [6] A C$440m contract was signed in August 2011 for the refurbishment of Embalse from November 2013, which will add 25–30 years to its life.

References

  1. de Vido, Julio (23 August 2006). "Reactivación de la Actividad Nuclear en la Republica Argentina" (in Spanish). Comision Nacional de Energia Atomica (CNEA). Archived from the original on 2011-09-25. Retrieved 23 September 2011.
  2. La Nación. 24 August 2006. Lanzó el Gobierno un plan de impulso a la energía nuclear.
  3. Valente, Marcela (8 September 2011). "Against the Current in Nuclear Energy". IPS. Archived from the original on 13 October 2011. Retrieved 23 September 2011.
  4. La Central Nuclear Néstor Kirchner -Atucha II- comenzó a generar energía Archived July 15, 2014, at the Wayback Machine
  5. INVAP, CAREM Project Archived 2009-02-05 at the Wayback Machine.
  6. Ylarri, Pedro (13 March 2010). "Avanza Atucha III, un negocio de más de US$ 3 mil millones" (in Spanish). Archived from the original on 3 March 2016. Retrieved 14 April 2010.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.