Jalna-Nanded Samruddhi Mahamarg | |
---|---|
Route information | |
Maintained by Maharashtra State Road Development Corporation (MSRDC) | |
Length | 179 km (111 mi) |
Existed | Dec 2024 (expected)–present |
Major junctions | |
Northwest end | Jalna district |
Southeast end | Nanded district |
Location | |
Country | India |
States | Maharashtra |
Major cities | Jalna, Parbhani, Nanded |
Highway system | |
The Jalna-Nanded Expressway is a link road greenfield project that connects the largest cities of Marathwada (Jalna, Parbhani, Hingoli, and Nanded) to Mumbai-Nagpur Expressway, which is also officially known as Hindu Hrudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg.[1] Proposed as 6-lane wide, this segment will reduce the road distance between Jalna and Nanded from 226 kilometres to 179 kilometres and bring down travel time between Nanded and Mumbai from 12 hours to around 6 hours.[2]
Route Alignment
The Jalna-Nanded Expressway will travel through Jalna, Parbhani, and Nanded districts directly. The 179-kilometre Jalna-Nanded segment passes through 87 villages. Around 93.52 kilometres of this segment passes through four tehsils in Parbhani, while 66.46 kilometres passes through three tehsils of Jalna and 19.82 kilometres passes through one tehsil in Nanded.[3]
Cities & Towns
Below are the lists of cities/towns through which the Jalna-Nanded Expressway will connect:
Construction
MSRDC invited RFQ applications for the expressway’s civil construction in April 2023. Here’s a list of civil packages included within the RFQ document:
Sr. No. | Package | Length in km | Contractor |
---|---|---|---|
1. | JNE-1 (36.09 km): 0.000 to 36.09 | 36.09 | Tender Notice Pending |
2. | JNE-2 (30.46 km): 36.09 to 66.55 | 30.46 | Tender Notice Pending |
3. | JNE-3 (32.44 km): 66.55 to 98.99 | 32.44 | Tender Notice Pending |
4. | JNE-4 (28.85 km): 98.99 to 127.84 | 28.85 | Tender Notice Pending |
5. | JNE-5 (32.19 km): 127.84 to 160.03 | 32.19 | Tender Notice Pending |
6. | JNE-6 (19.82+4.48 km): 160.03 to 179.85 (package includes from Hingole Gate to Chatrapai Chowk) | 24.3 | Tender Notice Pending |
Status updates
- March 2021: Project Announcement at Maharashtra State Annual Budget 2021–22.[4]
- November 2021: Maharashtra State Rajpatra (Work Order) Release.[5]
- December 2021: Land Acquisition Process Start.[6]
- February 2022: 77% Land Acquisition Survey Completed.[7]
- November 2022: Land Acquisition Notification Release.[8]
- November 2022: 22000 Crore Rupees Fund Raising For Land Acquisition & Construction Work. [9]
- April 2023: Invited Request for Qualifications (RFQ) to select eligible contractors for the construction.
See also
References
- ↑ "'Jalna to Nanded new Expressway'". 7 July 2021.
- ↑ "'Jalna to Nanded Expressway'". 12 February 2021.
- ↑ "'Jalna to Nanded Expressway route'". 12 February 2022.
- ↑ "Project Announcement". 9 April 2021.
- ↑ "Rajpatra Release". 14 November 2021.
- ↑ "Land Acquisition Start". 14 November 2021.
- ↑ "Land Acquisition Survey". The Times of India. 14 February 2022.
- ↑ "Land Acquisition". 11 November 2022.
- ↑ "Fund Raising". 11 November 2022.