Line 1
 1 
Overview
StatusOperational
OwnerShijiazhuang
LocaleShijiazhuang, Hebei, China
TerminiXiwang - Fuze (current)
Huai'anlu - Dongyang (future)
Stations26 (current)
30 (future)
Service
TypeRapid transit
SystemShijiazhuang Metro
Services1
Operator(s)Shijiazhuang Metro Corporation
History
Opened26 June 2017 (2017-06-26)
Technical
Line length34.3 km (21.3 mi) (current)
Number of tracks2
CharacterUnderground
Track gauge1,435 mm (4 ft 8+12 in)
Route map

Zhangying Depot
Xiwang
Shiguangjie
Changchengqiao
Hepingyiyuan
Minxin River
Lieshilingyuan
Xinbaiguangchang  3 
Jiefangguangchang
Ping'andajie
Beiguoshangcheng  2 
Bowuyuan
Tiyuchang
Beisong
Tangu
Zhaohuiqiao
Baifo
Liucun
Huojuguangchang
Shijiazhuangdongzhan
Nancun
Xiaohedadao
Xizhaotong Depot
Xizhuang
Dongzhuang
Huizhanzhongxin
Shangwuzhongxin
Yuanboyuan
Fuze
Phase II North section
Dongshangze
Dongyang

Line 1 of the Shijiazhuang Metro (Chinese: 石家庄地铁一号线; pinyin: Shíjiāzhuāng Dìtiě Yī Hào Xiàn) is a rapid transit line in Shijiazhuang, Hebei province, China. Currently it is 34.3 km (21.3 mi) long with 26 stations. The line opened on 26 June 2017.

History

Phase 1

Phase 1 of the line began construction on 1 July 2013 and began service on 26 June 2017, completed at a cost of ¥18.892 billion.[1]

Phase 2 initial section

The Phase II of Line 1 is 13.495 km (8.4 mi)[2] with 8 stations.[3] Only 6 stations from Xiaohedadao to Fuze (10.4 km[4]) opened on 26 June 2019.

Phase 2 North section

Two more stations, Dongshangze and Dongyang will open later. The section is 3.1 km in length with 2 stations.[5] The section will open in 2024.

Phase 3 (Southwest extension)

The Phase 3 will add two more stations (Huai'anlu and Shangzhuang) in Southwest of the line. The extension is under planning.

Opening timeline

SegmentCommencementLengthStation(s)Name
Xiwang — Xiaohedadao 26 June 2017 23.9 km (14.9 mi)[6] 20 Phase 1
Xiaohedadao — Fuze 26 June 2019 10.4 km (6.5 mi)[4] 6 Phase 2 (initial section)

Stations

Phase Station name Connections Distance
km
Location
English Chinese
Phase 3 Huai'anlu 槐安路
Shangzhuang 上庄
Phase 1 Xiwang 西王 Qiaoxi
Shiguangjie 时光街
Changchengqiao 长城桥
Hepingyiyuan 和平医院
Lieshilingyuan 烈士陵园
Xinbaiguangchang 新百广场  3 
Jiefangguangchang 解放广场 Qiaoxi/Xinhua
Ping'andajie 平安大街 Qiaoxi/Chang'an
Beiguoshangcheng 北国商城  2 
Bowuyuan 博物院 Chang'an
Tiyuchang 体育场
Beisong 北宋
Tangu 谈固
Zhaohuiqiao 朝晖桥
Baifo 白佛
Liucun 留村 Yuhua
Huojuguangchang 火炬广场
Shijiazhuangdongzhan 石家庄东站 Shijiazhuang East railway station SXP
Nancun 南村 Chang'an
Xiaohedadao 洨河大道
Phase 2 Xizhuang 西庄
Dongzhuang 东庄
Huizhanzhongxin 会展中心 Zhengding
Shangwuzhongxin 商务中心
Yuanboyuan 园博园
Fuze 福泽
Dongshangze 东上泽
Dongyang 东洋

Rolling stock

Services are provided by CRRC Tangshan Type A rolling stock, which are operated in six-car sets that hold up to 2520 passengers each.[6]

References

  1. 石家庄地铁1号线建成通车 "高颜值"地铁首次驶进石家庄. China.com (in Chinese). 26 June 2017. Archived from the original on 28 December 2017. Retrieved 28 December 2017.
  2. 石家庄地铁1号线二期工程顺利通过单位工程竣工验收(组图). 中工城建 (in Chinese). 2019-05-22. Archived from the original on 2019-05-26. Retrieved 2019-05-26.
  3. 石家庄地铁1号3号线二期最新规划 2019年通车. 搜狐 (in Chinese). 30 August 2017. Archived from the original on 28 December 2017. Retrieved 28 December 2017.
  4. 1 2 石家庄地铁1号线二期先开通这6座车站,票价确定. 河北新闻网 (in Chinese). 2019-06-09. Archived from the original on 2019-06-30. Retrieved 2021-11-28.
  5. "开工!石家庄地铁1号线二期北段工程启动". 本次开工的1号线二期北段工程,即东上泽站至东洋站以及南牛停车场建设,线路长度3.1公里,预计工期三年
  6. 1 2 石家庄地铁开通 河北正式迈入"地铁时代". CNR (in Chinese). 2017-06-27. Archived from the original on 2017-08-02. Retrieved 2019-05-26.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.