MRT Line 7
Hyundai Rotem trains in September 2021
Overview
StatusUnder construction
OwnerDepartment of Transportation
Line number7
LocaleMetro Manila and Bulacan
Termini
Stations14[1]
Service
TypeRapid transit
SystemManila Metro Rail Transit System
Services1
Operator(s)SMC-Mass Rail Transit 7 Incorporated[1]
Rolling stockClass 000 EMUs
Daily ridership300,000 (initial)
850,000 (design capacity)
History
Planned opening2025 (full)[2]
Technical
Line length22.8 km (14.2 mi)
Number of tracksDouble-track
CharacterGrade separated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail[3]
Average inter-station distance1.62 km (1.01 mi)
Route map

San Jose del Monte
Tala
Sacred Heart
Depot
Quirino
Mindanao Avenue
Regalado
Doña Carmen
Manggahan
Batasan
Don Antonio
Tandang Sora
University Avenue
Quezon Memorial
North Avenue
 MMS 
3

The Metro Rail Transit Line 7, also known as MRT Line 7 or MRT-7, is a rapid transit line under construction in the Philippines. When completed, the line will be 22.8 kilometers (14.2 miles) long, with 14 stations, and the first line to have a third rail electrification.[3] The line runs in a northeast–southwest direction, beginning at San Jose del Monte, Bulacan up to the North Triangle Common Station in North Avenue, Quezon City.

First planned in 2001 and approved in 2004,[4][5] the 25-year concession agreement was signed in 2008 between the Philippine government and the project's original proponent, Universal LRT Corporation.[6] However, construction has been repeatedly delayed due to right-of-way issues. The project was re-approved in 2013,[6] while funding for the project was obtained in 2016.[7] Construction on the line began the following year and is slated to open by 2025.[8][2] The project will cost an estimated 62.7 billion (US$1.54 billion),[9] with additional plans are laid for capacity expansion in order to accommodate the possible increase in passenger ridership in the future.

It is integrated with the public transit system in Metro Manila, and passengers also take various forms of road-based public transport, such as buses, to and from a station to reach their intended destination.

Route

The line will start at San Jose del Monte located in Bulacan and will end at the North Triangle Common Station in Quezon City. The line is mostly elevated and erected either over or along the roads covered, with underground sections between Quezon Memorial and University Avenue, and at San Jose del Monte. The rail line serves the cities that Quirino Highway, Regalado Highway, Commonwealth Avenue, and North Avenue passes through: San Jose del Monte in Bulacan, Caloocan and Quezon City in Metro Manila.

Stations

Upon completion, the line will have 14 stations along its route. Only one station, North EDSA, will initially serve as an interchange with the other metro lines, although two more will be interchanges when Line 8 opens.

List of stations
No.[10] Station Distance (km)[11] Structure type Connections Location
Between
stations
Total
 S01  North EDSA[10] 2.195 22.664 Elevated
Interchange with Metro interchange Manila LRT
Interchange with Metro interchange Manila MRT
  •  1  North Avenue
  •  18   33   64  SM North EDSA
  •  4  Road 1  8  Trinoma
Quezon City
 S02  Quezon Memorial Circle[10] 0.835 20.469 Depressed
Proposed interchange with Metro interchange Manila MRT
  •  6   7   17   34   49  Visayas Avenue
     6   7   17   34   49  Quezon City Hall
 S03  University Avenue 1.663 19.634 Depressed
Proposed interchange with Metro interchange Manila MRT
  •  6   7   17   34   49  Technohub
 S04  Tandang Sora 2.256 17.971 Elevated
  •  6   7   17   34   36   39   41   49  Tandang Sora
     18   50   51  Luzon Avenue
 S05  Don Antonio 0.973 15.715 Elevated
  •  6   7   17   34   36   39   41   49  Ever Gotesco
  •  2  St. Peter Parish
 S06  Batasan 1.391 14.742 Elevated
  •  6   7   17   34   36   39   41   49  Batasan
  •  2  Maclang General Hospital
 S07  Manggahan 1.470 13.351 At-grade
  •  6   7   17   36   39   41   49  Manggahan
 S08  Doña Carmen 1.145 11.881 Elevated
  •  6   7   17   36   39   41   49  Puregold North Commonwealth
 S09  Regalado Avenue[10] 3.429 10.736 Elevated
  •  6   7   17   36   39   41   49  Fairview Center Mall
 S10  Mindanao Avenue 0.786 7.307 Elevated
  •  6   7   17   20   33   36   37   38   39   40   41   49  SM Fairview (Nova Stop)
 S11  Quirino Avenue 1.954 6.521 Elevated
  •  6   20   33   49  Lagro
 S12  Sacred Heart 2.024 4.567 Elevated
  •  6   20   33   49  Amparo
Caloocan
 S13  Tala 2.543 2.543 Elevated
  •  6   20   33   49  Pangarap
 S14  San Jose del Monte 0.000 Depressed
  • Bus interchange San Jose del Monte Intermodal
San Jose del Monte, Bulacan
Stations, lines, and/or other transport connections in italics are either under construction, proposed, unopened, or have been closed.

History

Early planning and delays

A part of the right-of-way of the present MRT-7 project can be traced to the original MRT Line 4 proposal as part of the Metro Manila Urban Transportation Integration Study published by the Japan International Cooperation Agency in 1999. It called for the construction of a 22.8 km (14.2 mi) elevated railway between Recto Avenue in Manila to Novaliches in Quezon City. A branch line, which would either be an automated guideway transit or busway, would have shuttle commuters to and from San Mateo, Rizal. This proposal would be later split into MRT-7 and the MRT Line 8 proposal. The section of this route between the Quezon Memorial Circle and Novaliches became Line 7 while the rest of the proposed line became Line 8.[12]

On August 27, 2001, an early proposal of the MRT-7 project was submitted to the Department of Transportation and Communications (now the Department of Transportation).[4] The Investment Coordination Committee (ICC) of the National Economic and Development Authority (NEDA) first approved a version of the MRT Line 7 project in March 2004; this initial approval was provisional and contingent on the project's impact on the government's deficit reduction program. It had been submitted as an unsolicited proposal under the build–operate–transfer scheme by the Universal LRT Corporation, a consortium consisting of Alstom, EEI Corporation, Tyco Electronics, and others.[5] NEDA subsequently authorized the $1.2 billion project's construction the following August, citing the proponents' willingness to comply with the ICC's requirements, with construction slated to begin in 2005 and a targeted opening date in 2007.[13][14] In October 2004, Universal LRT Corporation signed an agreement with the Manila Banking Corporation to purchase 193 hectares (480 acres) of property in Bulacan for ₱1 billion, stating it would develop this property to complement the rail line.[15]

Universal LRT Corporation, later renamed to now SMC-Mass Rail Transit 7 Incorporated, a subsidiary of San Miguel Corporation (SMC) was selected by the Department of Transportation and Communications to build the line in 2008. The concession agreement of the project was signed on June 18, 2008.[6][16] Construction of the line should have commenced in January 2010, but was postponed several times.[17]

In May 2012, the joint venture of Marubeni Corporation and DMCI was awarded a construction contract.[18] However, after years of delays, SMC planned to conduct a second round of bidding in 2015, due to revised construction cost assumptions.[19]

The current project was approved on November 21, 2013, by the NEDA board, chaired by President Benigno Aquino III, and the project was developed through a public-private partnership (PPP). It has an indicative cost of ₱62.7 billion.[20]

The Department of Finance issued the terms of financial guarantee for the line in 2014, and financial closure for the project was achieved in February 2016.[7] On January 22, 2016, Hyundai Rotem won the US$440.2 million contract with SMC-Mass Rail Transit 7 Incorporated to supply 108 train cars, signalling, communication and power supply systems.[21][22]

Construction

Construction progress of Batasan Station along Commonwealth Avenue, Quezon City as of August 2018.
Construction along Commonwealth Avenue, March 2021.

Soil testing and surveying, including pre-construction related activities, were conducted in February 2016. SMC tapped the consortium of Hyundai Rotem and EEI Corporation as the engineering, procurement and construction contractor in the same year.[23] A groundbreaking event was held on April 20, 2016, 15 years after initial development began, and was attended by President Benigno Aquino III.[24] The line was expected to be finished by 2019,[25] but was repeatedly pushed back because of right-of-way issues regarding the acquisition of a 33-hectare (82-acre) land for the San Jose del Monte station, depot, and the intermodal transport terminal (ITT).[26]

More than a year after the groundbreaking ceremony was held, construction on the 22.8-kilometer (14.2-mile) line officially started on August 15, 2017, and has resulted in lane closures and heavy traffic along Commonwealth Avenue and Quirino Highway, both in Quezon City.[8][27][25] The project also includes construction of a 22-kilometer (13.7-mile) highway from the NLEX Bocaue Interchange, up to the proposed intermodal transport terminal (ITT) located near San Jose del Monte station.[1]

Groundbreaking for Batasan station was held on October 7, 2017,[28] while the excavation for the underground guideway at Quezon Memorial Circle is ongoing as of November 2017.[25] Construction of the station and rail track along North Avenue began on January 22, 2018.[29]

Nearly two years since the start of the construction of Line 7, works at the depot commenced on November 26, 2019, according to a statement by the DOTr.[30][31] After two years of court hearings and appeals to obtain a site, the original location of the depot in San Jose del Monte, Bulacan was moved to Quirino Highway in Barangay Greater Lagro, Quezon City. The relocation was found optimal for right-of-way, operational reliability, and maintenance.[30] The depot site was approved by Tugade on June 29, 2019, and the DOTr offered to buy the property from lot owners Century Properties Group, Inc. at the current market value, which was appraised by a Bangko Sentral ng Pilipinas-accredited independent property appraiser.[32] Construction works at the depot started on May 31, 2022, after the land area was cleared.[33]

Originally, the site in Bulacan was subject to a legal case after the property owner questioned the expropriation at the Malolos Regional Trial Court Branch 11. If it was pushed through, the cost of the project would have multiplied ninefold from ₱67.105 million to ₱598.905 million. Transport Assistant Secretary Goddes Hope Oliveros-Libiran stated that it would take forever to resolve the case and it will no longer be pursued. The case in Bulacan has prompted San Miguel to conduct a scheduled partial operation of the line from North Avenue to a station in Fairview in 2021.[34]

In 2021, the project was realigned. Due to right-of-way issues, the original site of the Tala and San Jose del Monte station was relocated, and the guideway leading to the station itself was realigned, now passing through the Quirino Highway alignment instead of passing through Pangarap Village, which has been disputed for years.[35]

As of January 31, 2023, the project is 66.07% complete.[36] The line was planned to undergo "demonstration runs" by 2023 and full operations by 2024–2025; but was later deemed no longer feasible, targeting full operations by the second quarter of 2025 instead,[2] with DoTr Project Management Service (PMS) Director Eduardo D. Mangalili citing the completion of the depot as the main factor.[2]

Station design and layout

The stations will have a standard layout, with a concourse level and a platform level. The concourse is usually above or below the platform, with stairs, escalators and elevators leading down to the platform level. Station concourses will contain ticket booths, which is separated from the platform level by fare gates. Most stations will be designed to be barrier-free inside and outside the station, and trains will have spaces for passengers using wheelchairs.

Stations will either have island platforms and side platforms.

Rolling stock

Installation of coaches.
President Rodrigo Duterte during the unveiling of Hyundai Rotem EMU train sets for the MRT-7 along Commonwealth Avenue in Diliman, Quezon City on December 16, 2021

The line will be operated with 108 rail cars in a three-car configuration. Hyundai Rotem was awarded a $440.2 million contract to supply 108 metro cars, which will be configured into 36 train sets (3 cars per train set, with plans of expanding up to 6 cars per train set). The contractual scope also includes signalling, communications, and power supplies for the metro line. All ordered trainsets have undergone the necessary testing and trials. After being stored in South Korea since 2018 due to a lack of a depot,[26] the 108 railcars are already in the process of being shipped to the Philippines.[37] The first batch of two three-car trainsets arrived in the country on September 6, 2021.[38] The trains were then brought from the Port of Manila to Commonwealth Avenue and were laid on the tracks near the Tandang Sora station from September 11 and 12.[39] On the other hand, the trains are seen to begin test runs by April 2022.[40] As of December 2021, six trainsets were delivered and laid on the tracks near Tandang Sora station, with the latest deliveries of two trains that were laid in November 2021.[41][42] The trains were unveiled on December 16, 2021.[43]

Rolling stock specifications
Rolling stock First-generation
Image
Year 2018–2019
Manufacturer Hyundai Rotem
Model Class 000
Number built 108 cars (36 sets)[21][22]
Length MC: 21.95 m (72 ft 0 in)
MT: 21.56 m (70 ft 9 in)
Width 3.15 m (10 ft 4 in)
Height 3.75 m (12 ft 4 in)
Body material Stainless steel
Weight 115 t (254,000 lb)
Configuration 3-car: MC-MT-MC
6-car: MC-MT-MC-MC-MT-MC (planned)
Capacity 1,166 passengers (3-car)
Doors Sliding pocket; 4-doors/side
Drive unit Gear coupling (WN) Drive
Traction power 750 V DC third rail
Traction control IGBTVVVF
Traction motor 200 kW (270 hp) 3-phase AC induction motor
Top speed 90 km/h (55 mph)
Braking system Electro-pneumatic
Safety system(s) ATP
Acceleration 1 m/s2 (3.3 ft/s2)
Deceleration 1 m/s2 (3.3 ft/s2) (Normal) / 1.3 m/s2 (4.3 ft/s2) (Emergency)
Gauge 1,435 mm (4 ft 8+12 in)
Coupling Shibata close-contact
Status 6 trainsets (18 cars) delivered as of December 2021[41]

Depot

MRT Line 7 Depot in Barangays 183 Tala (Quirino Highway)

The line will maintain an at-grade depot in Barangay Greater Lagro, Quezon City, close to the proximity of La Mesa Watershed.[30] The depot occupies 20 hectares (49 acres) of space and will be the center of the operations and maintenance of the line.[31] It will be capable of handling 150 trains for future expansion of the line.[44]

Expansion

SMC plans for MRT-7 to evolve into a 200-kilometer (120-mile) network. Its main feature is a circumferential mainline comprising the present line, the Airport Access segment to the New Manila International Airport, the West Rail Link, and the Phase 2A between the Manila North Harbor and the North Avenue Common Station. Additional branches will also be built in northeastern Metro Manila and Rizal.

Phase 2A

The first proposed extension by phase number is Phase 2A, an unnamed westward extension of the line to Tutuban station via West Avenue, Quezon Avenue and Earnshaw Street before running parallel to the LRT Line 2 after Legarda station.[45] This is similar to an earlier proposal under review, MRT Line 8, under the Philippine National Railways, that has proposed technical specifications identical to the MRT-7. Depending on the deliberations and pending approvals, the two lines may coexist or may be merged.

Phase 2A stations

Name Line transfers Barangay City/Municipality Nearest Landmarks
Del Monte none Phil-Am Quezon City None
Delta West Triangle Capitol Medical Center, St. Mary's College
A. Roces Paligsahan Fisher Mall, Amoranto Sports Complex
Santo Domingo Santo Domingo Santo Domingo Church, UST Angelicum College
D. Tuazon Santa Mesa Heights Welcome Rotonda, National Labor Relations Commission
España Boulevard  NSCR  España Sampaloc Manila Trabajo Market
G. Araneta none University of Santo Tomas
Legarda Legarda San Sebastian Church, University Belt (Mendiola Street section)
Recto Recto Santa Cruz Isetann Recto, Manila City Jail
Tutuban Tutuban
Tutuban
Tondo Tutuban Center (Old Tutuban Station), Divisoria
North Port Pier 4
North Port Passenger Terminal
Port of Manila

Phase 2B (West Rail Link)

Phase 2B is dubbed the West Rail Link project. It will be an airport rail link to the New Manila International Airport and traversing the northwest coast of Metro Manila, in similar fashion to the Clark–Buendia Airport Limited Express of the North–South Commuter Railway. It will host express train services and aims to connect the NMIA and Metro Manila within 20 minutes.[46] Thus, it will only have three stations: C2 in Manila, C4 in Navotas, and NMIA. The length of the segment is yet to be determined.[45]

Phase 3 (Airport Access)

With the depot underway, San Miguel Corp. has plans to extend the line further to Bocaue, Bulacan, replacing the planned six-lane highway, which aims to be connected to the North Luzon Expressway.[47] The extension will improve access to Ciudad de Victoria complex, where the Philippine Arena will be within its vicinity.[48] The line will also connect Metro Manila with the New Manila International Airport, adding 30.3 kilometers (18.8 miles) to the present line to 53.1 kilometers (33.0 miles).[49] Plans were also laid out connect the airport to the cities of Navotas, Malabon, and Manila, consisting of 19 additional stations, and will travel through the alignment of the LRT 2 Western Extension and the planned MRT 8, before traversing to West Avenue, and finally connecting the planned extension line to the North Triangle Common Station.[50]

This segment shall be operated together with the Philippine National Railways.[49]

Phase 3 stations

Name Line transfers Barangay City/Municipality Nearest Landmarks
Tungkong Mangga 7 San Jose del Monte Tungkong Mangga San Jose del Monte Skyline Hospital and Medical Center, Iglesia ni Cristo - Maharlika, College of St. Anthony
Francisco Homes none Mulawin Grace Medical Center, The Church of Jesus Christ of Latter Day Saints
Dulong Bayan Dulong Bayan City of San Jose del Monte Government Center, River Park Esplanade
Santa Maria San Vicente Santa Maria Bella Vista
Philippine Arena Tabing Bakod Philippine Arena, Philippine Sports Stadium
Marilao (Phase 3)  NSCR  Marilao Ibayo Marilao SM City Marilao
NMIA 7 NMIA Taliptip Bulakan New Manila International Airport

Phase 4A (Southeast Alignment)

Phase 4A involves the construction of an extension from D. Tuazon station of Phase 2A to Taytay, Rizal. Excluding D. Tuazon, it will have 10 stations running on a northwest–southeast alignment.[45] This project is also similar to the MRT Line 4, except it will run on the same Line 7 network, providing wider access of stations. It will also traverse areas north of Gilmore station towards Quezon Avenue. Line 4 was originally intended to be a monorail system, until it was upgraded to a heavy rail system.

Phase 4A stations

Name Line transfers Barangay City/Municipality Nearest Landmarks
Araneta Avenue none New Manila Quezon City De Los Santos Medical Center, St. Luke's Medical Center – Quezon City, Trinity University of Asia
E. Rodriguez Kristong Hari Christ the King Seminary, Barangay Mariana Park, Quezon City Sports Club
Gilmore Gilmore New Manila Gilmore Commercial Plaza, St. Paul University Quezon City
Greenhills none Greenhills San Juan Cardinal Santos Medical Center, Greenhills Shopping Center
POEA–Ortigas Wack Wack–Greenhills Mandaluyong EDSA Shrine, La Salle Green Hills, Philippine Overseas Employment Administration, Robinsons Galleria, Wack Wack Golf and Country Club
Meralco Avenue 7 (Southeast Alignment Spur) Ugong Pasig Meralco Main Office, The Medical City
Pasig None Rosario Sto. Rosario de Pasig Church
Bonifacio Avenue 7 (Katipunan branch) Santo Domingo Cainta, Rizal Robinsons Cainta
L. Wood None San Isidro Taytay, Rizal Taytay Rotonda Monument
Taytay Dolores Taytay Public Market, Taytay Municipal Hall

Phase 4B

Phase 4B involves the construction of a spur line between Ortigas Center and V. Mapa station of LRT Line 2. Excluding Meralco Avenue station and V. Mapa, it will have 6 stations traversing a U-shaped right of way.[45]

Phase 5 (Katipunan spur)

Plans were also laid out for a 13.9 kilometers (8.6 miles) additional spur line, known as the MRT 7 Katipunan Spur Line, that aims to connect the line from Tandang Sora station to the LRT Line 2 at Katipunan and Marikina stations; the U.P. Town Center, the Ateneo de Manila University, the Riverbanks Center, and the MRT 4 Cainta Station. The project also consists of 8 additional stations, and will connect areas within Quezon City, Marikina, the eastern parts of Pasig, and Cainta, Rizal. The proposed spur line will traverse through the University of the Philippines Diliman complex, Katipunan Avenue, Aurora Boulevard, Andres Bonifacio Avenue, Sumulong Highway, Mayor Gil Fernando Avenue, and Felix Avenue.[51][52]

Phase 5 stations

Name Line transfers Location Nearest landmarks
Tandang Sora 7 Tandang Sora Matandang Balara, Quezon City New Era University, Commonwealth Avenue
Balara none University of the Philippines Diliman, MWSS, Balara Filters Park
U.P. Town Center Diliman, Quezon City U.P. Town Center, C.P. Garcia Avenue (UP), Brgy. Pansol
Ateneo Loyola Heights, Quezon City Miriam College, Ateneo de Manila University
Katipunan Katipunan Xavierville Avenue, Aurora Boulevard, Project 2 & 3
Riverbanks none Marikina Riverbanks Center, Barangka, Provident Village
Sumulong Marikina City Hall, Amang Rodriguez Memorial Medical Center, Sumulong Highway
Emerald-Marikina Marikina Marikina–Infanta Highway, Sta. Lucia East, Robinsons Metro East
Bonifacio Avenue 4 Cainta Cainta, Rizal Ortigas Avenue Extension, Cainta Public Market, Robinsons Cainta

Notes

    References

    1. 1 2 3 "MRT Line 7". www.ppp.gov.ph. Public-Private Partnership Center. Archived from the original on April 14, 2021. Retrieved May 5, 2021.
    2. 1 2 3 4 Balinbin, Arjay L. (January 25, 2023). "Full MRT-7 operations seen by 2nd quarter 2025". BusinessWorld. Philippines: The Philippine STAR. Archived from the original on January 25, 2023. Retrieved January 25, 2023.
    3. 1 2 Gines, Ben Jr. (December 17, 2021). "MRT-7 gets new train sets". The Manila Times. Archived from the original on March 11, 2022. Retrieved March 11, 2022.
    4. 1 2 Devio, Lea (July 23, 2021). "MRT-7 60.93% complete". The Manila Times. Archived from the original on July 23, 2021. Retrieved July 23, 2021.
    5. 1 2 Ferriols, Des (March 29, 2004). "NEDA body approves MRT Line 7". The Philippine Star. Archived from the original on July 6, 2020. Retrieved December 1, 2021.
    6. 1 2 3 "MRT 7 PROJECT" (PDF). Public-Private Partnership Center. August 2019. Archived (PDF) from the original on January 9, 2022. Retrieved January 9, 2022.
    7. 1 2 Camus, Miguel R. (February 17, 2016). "With funds secured, Line 7 to run by '19". Philippine Daily Inquirer. Archived from the original on February 17, 2016. Retrieved November 12, 2017.
    8. 1 2 "Brace for heavy traffic on Commonwealth Avenue as MRT-7 construction starts". GMA News Online. August 13, 2017. Archived from the original on August 14, 2017. Retrieved August 14, 2017.
    9. Marasigan, Lorenz S. (April 28, 2014). "SMC vows to finish MRT 7 project by August 2019". Business Mirror. Archived from the original on October 4, 2015. Retrieved October 2, 2015 via Public–Private Partnership Center.
    10. 1 2 3 4 한국철도TV. "필리핀 기차, 한국철도 기술을 담다 🚄 | KORAIL PHILIPPINE BRANCH". YouTube. Archived from the original on December 21, 2022. Retrieved December 21, 2022.
    11. "THE MRT 7 PROJECT" (PDF). Public-Private Partnership Center. August 2019. Archived (PDF) from the original on August 11, 2022. Retrieved March 10, 2022.
    12. Iwata, Shizuo (March 5, 1999). Final Report Summary (PDF). Metro Manila Urban Transportation Integration Study (Report). Japan International Cooperation Agency. Archived (PDF) from the original on October 2, 2021. Retrieved October 2, 2021.
    13. Reyes, Mary Ann Ll. (August 14, 2004). "Gov't gives green light for $1.2-B MRT-7 intermodal transport system". The Philippine Star.
    14. Cabacungan Jr., Gil C. (September 14, 2004). "Massive Luzon railway projects to cost at least $5B". Philippine Daily Inquirer.
    15. Batino, Clarissa S. (October 27, 2004). "MRT-7 group buys P1-B land in Bulacan". Philippine Daily Inquirer.
    16. Dela Paz, Chrisee (April 14, 2016). "San Miguel Corp forms new company for MRT7". Rappler. Archived from the original on July 22, 2021. Retrieved July 22, 2021.
    17. Camus, Miguel R. (November 29, 2013). "Construction of Line 7 seen to start in 2014". Philippine Daily Inquirer. Archived from the original on December 1, 2013.
    18. "Marubeni-DMCI group bags $1B contract to build MRT-7". Agence France-Presse. May 15, 2012. Archived from the original on January 24, 2020. Retrieved December 1, 2021 via ABS-CBN News.
    19. Camus, Miguel R. (February 5, 2016). "SMC given 2 weeks to close funding deal for MRT-7". Motioncars. Archived from the original on February 6, 2016. Retrieved December 1, 2021.
    20. Tan, Kimberly Jane (November 21, 2013). "NEDA approves MRT 7, LRT-1 extension projects". GMA News and Public Affairs. Archived from the original on August 30, 2018. Retrieved August 31, 2021.
    21. 1 2 Barrow, Keith (January 25, 2016). "Hyundai Rotem trains for Manila Line 7". International Railway Journal. Archived from the original on July 1, 2016. Retrieved July 17, 2016.
    22. 1 2 "Hyundai Rotem wins $440mn turn-key project in Philippines". Pulse News. January 22, 2016. Archived from the original on September 18, 2016. Retrieved July 17, 2016.
    23. Daxim L. Lucas (February 15, 2016). "SMC seals financing for P63B MRT-7 commuter project". Inquirer. Archived from the original on February 16, 2016. Retrieved March 15, 2016.
    24. "Construction Begins for Line 7, Connecting QC to Bulacan". PropertyAsiaPH. April 20, 2016. Archived from the original on April 23, 2016. Retrieved June 6, 2016.
    25. 1 2 3 "DoTr: Expect traffic slowdown on Quirino Highway due to Line 7 construction". GMA News Online. November 5, 2017. Archived from the original on November 5, 2017. Retrieved November 5, 2017.
    26. 1 2 "Right-of-way issue hounds MRT 7". BusinessWorld Online. August 7, 2018. Archived from the original on August 7, 2018. Retrieved December 5, 2018.
    27. "Motorists told to avoid Quirino Highway due to MRT7 construction". Rappler. November 5, 2017. Archived from the original on November 5, 2017. Retrieved November 8, 2017.
    28. Cordero, Ted (October 7, 2017). "Concrete pouring at MRT-7 Batasan Station in QC begins". GMA News Online. Archived from the original on October 7, 2017. Retrieved October 28, 2017.
    29. Galvez, James Konstantin (January 20, 2018). "Heavy traffic expected with MRT-7 construction". The Manila Times. Archived from the original on January 23, 2018. Retrieved January 23, 2018.
    30. 1 2 3 Cordero, Ted (November 27, 2019). "MRT7 depot works commence as QC court grants DOTr, SMMRT7 writ of possession". GMA News Online. Archived from the original on October 6, 2021. Retrieved November 29, 2019.
    31. 1 2 Galvez, Daphne (November 27, 2019). "MRT-7 depot construction starts as courts grant DOTr, SMC right of way". newsinfo.inquirer.net. Archived from the original on November 28, 2019. Retrieved November 29, 2019.
    32. Subingsubing, Krixia (November 28, 2019). "MRT 7 on track for partial opening in 2021". business.inquirer.net. Archived from the original on November 28, 2019. Retrieved November 29, 2019.
    33. Cordero, Ted (May 31, 2022). "San Miguel starts construction of MRT7 depot in Bulacan". GMA News. Archived from the original on May 31, 2022. Retrieved May 31, 2022.
    34. Balinbin, A.L. (November 28, 2019). "MRT-7 clears key hurdle". BusinessWorld. Archived from the original on April 12, 2020. Retrieved November 29, 2019.
    35. Dangla, Demie (June 18, 2015). "Pangarap Village residents decry harassment over land dispute". Manila Today. Archived from the original on February 4, 2018. Retrieved July 22, 2021.
    36. "House Tackles Dotr's Railway Projects Status, Urges Agency To Fix Project Delays". House of Representatives of the Philippines. Press and Public Affairs Bureau. February 16, 2023. Archived from the original on February 20, 2023. Retrieved February 21, 2023.
    37. "Trains for MRT-7 project set to arrive next week: SMC". Philippine News Agency. September 1, 2021. Archived from the original on September 1, 2021. Retrieved September 1, 2021.
    38. Sarao, Zacarian (September 7, 2021). "Two train sets for MRT 7 arrive in Manila". Philippine Daily Inquirer. Archived from the original on September 7, 2021. Retrieved September 8, 2021.
    39. "SMC starts installation of first MRT7 train sets from Korea". GMA News. September 13, 2021. Archived from the original on September 13, 2021. Retrieved September 13, 2021.
    40. Cabuenas, Jon Viktor D. (September 20, 2021). "MRT7 trains to be seen running by April 2022". GMA News. Archived from the original on September 21, 2021. Retrieved September 21, 2021.
    41. 1 2 "Six newly installed train sets for the Metro Rail Transit Line 7 (MRT-7) project were spotted along Commonwealth Avenue, Quezon City on Wednesday". Facebook. December 1, 2021. Retrieved December 1, 2021.
    42. "Two new train sets of MRT-7 have arrived as of today morning along Commonwealth Avenue". Facebook. November 13, 2021.
    43. "New train sets for MRT-7 unveiled". CNN Philippines. December 16, 2021. Archived from the original on December 16, 2021. Retrieved December 16, 2021.
    44. Ombay, Giselle (December 15, 2021). "DOTr says MRT-7 now 62% complete". GMA News. Archived from the original on December 15, 2021. Retrieved December 15, 2021.
    45. 1 2 3 4 NMIA Multimodal Transportation Network. SMC Infrastructure. Archived from the original on August 30, 2021. Retrieved August 30, 2021.
    46. Gonzales, Iris (August 31, 2018). "SMC plans MRT Loop to link Bulacan airport". Philippine Star. Archived from the original on August 31, 2018. Retrieved August 30, 2021.
    47. Amojelar, Darwin G. (December 8, 2019). "SMC wants to extend MRT Line 7 to Bocaue". Manila Standard. Archived from the original on December 2, 2021. Retrieved December 10, 2019.
    48. Camus, Miguel R. (December 9, 2019). "MRT 7 extension to Bocaue eyed". business.inquirer.net. Archived from the original on August 30, 2021. Retrieved December 10, 2019.
    49. 1 2 "MRT 7 Airport Express". www.ppp.gov.ph. Public-Private Partnership Center. Archived from the original on June 11, 2020. Retrieved November 1, 2020.
    50. "Bulacan Airport MRT Seven Masterplan". www.puregroupofcompanies.com. Archived from the original on June 29, 2021. Retrieved June 29, 2021.
    51. http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2021/I4.pdf&ved=2ahUKEwihkJ7SlLLuAhUqwYsBHV0zChwQFjABegQIAhAF&usg=AOvVaw3qFFXQTmQDfpiyBj9bQ0qy&cshid=1611409381609
    52. "MRT 7 Katipunan Spur Line Project". PPP Center. Archived from the original on June 9, 2020.
    This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.