Morecambe South gas field
CountryUnited Kingdom
RegionIrish Sea
Location/blocksUK Block 110/2a and extends into Blocks 110/3a, 110/8a, 110/7a
Offshore/onshoreoffshore
Coordinates53°50’48”N 03°34’51”W
OperatorsHydrocarbons GB Limited, British Gas E & P Ltd, Centrica plc, Spirit Energy
OwnerHydrocarbons GB Limited, British Gas E & P Ltd, Centrica plc, Spirit Energy
Service contractorssee text
Field history
DiscoverySeptember 1974
Start of productionJanuary 1985
Production
Estimated gas in place150×10^9 m3 (5.3×10^12 cu ft)
Producing formationsTriassic sandstone

The Morecambe gas fields are two major natural gas producing fields in Morecambe Bay in the Irish Sea, 27 km west of Blackpool.

The fields

The Morecambe South field is in UK Block 110/2a and extends into Blocks 110/3a, 110/8a, 110/7a; Morecambe North is in Block 110/2a. The fields were discovered in September 1974 and February 1976 respectively.[1] [2] The fields are named after a light-ship station, they are sometimes erroneously called Morecambe Bay.[2]

The gas reservoir is a Triassic sandstone and has the following characteristics.[3] [4]

Morecambe reservoir properties
Reservoir depth, feet 2,200 to 3,750
Gas column, feet 1,650
Porosity, % 12-15
Nitrogen content, % 7-8
Pressure at depth 1,875 psi @ 3,750 feet
Recoverable reserves, trillion cubic feet (1985) 5. 2
Recoverable reserves South billion cubic metres (1994) 150.0 / 5.2 Tcf
Recoverable reserves North billion cubic metres (1994) 35.0 / 1.2 Tcf

Owner and operator

In 1985 the sole licensee of the field and the operator was Hydrocarbons GB Limited.[3] This had become British Gas E & P Ltd by 1994, then Centrica plc in 1997. In 2017, Centrica launched Spirit Energy a joint venture with German energy and infrastructure company Stadtwerke München (SWM). Spirit Energy assumed ownership of the Morecambe gas fields.[5]

Development

The Morecambe gas fields development was to provide peak UK demand for gas in the winter. Morecambe South was developed around a central drilling, production and accommodation complex. This comprised three bridge linked platforms plus a bridge-linked flare tower. Details of the platforms are as shown.[3]

Morecambe South central complex platforms
Platform CPP1 AP1 DP1
Type Steel jacket Steel jacket Steel jacket
Function Central processing Accommodation for 176 Wellhead drilling
Coordinates 53°50’48”N 03°34’51”W 53.846667N 3.580556W 53.846861N 3.580556W
Water depth, metres 26 26 26
Design contractors Matthew Hall Eng. Matthew Hall Eng. Worley-Atkins
Topsides fabrication Wm Press, Wallsend
Topside installation March 1984 June 1984 1985
Jacket fabrication RGC Offshore, Methil RGC Offshore, Methil McDermott, Ardesier
Jacket weight, tonnes 11,754 4,100 5,500
Jacket installation October 1983 March 1984 April 1984
Legs 8 4 4
Piles 32 12
Wells 16 (5-8 planned)
Startup January 1984 1985
Export to Barrow, 39 km 36-inch pipeline CPP1 via bridge

The central complex Flare tower (53.846667N 3.580556W) is linked by a bridge to the CPP1 platform. It is supported by a 3-leg jacket.

In addition to the central DP1 drilling and wellhead platform, four other wellhead platforms were installed in the field, each producing well fluids to the CPP1 platform.[3]

Morecambe South wellhead platforms
Platform DP3 DP4 DP6 DP8
Type Steel jacket Steel jacket Steel jacket Steel jacket
Function Wellhead drilling Wellhead drilling Wellhead drilling Wellhead drilling
Coordinates 53°49’00”N 03°33’37”W 53°52’34”N 03°39’39”W 53.867278N 3.616650W 53.891872N 3.622833W
Water depth, metres 30 30 32 32
Accommodation 6 6
Design contractors Worley-Atkins Worley-Atkins
Topsides weight, tonnes 5,200 5,200
Topside installation September 1983 July 1984
Jacket fabrication McDermott, Ardesier Howard Doris, Kishorm
Jacket weight, tonnes 5,500 5,500
Jacket installation July 1983 July 1984
Legs 4 4
Wells 16 (5-8 planned) 16 (5-8 planned)
Startup 1985 1985 1985 1985
Export to CPP1, 3.5 km 24-inch pipeline CPP1, 3.5 km 24-inch pipeline CPP1, 3.2 km 24-inch pipeline CPP1, 5.8km 24-inch pipeline

Because the gas reservoir is shallow, and to avoid a large deviation of the wells, slant drilling is used. Two jack up drilling rigs were built to undertake 30 degree slant drilling. The rigs were Morecambe Flame and Bay Driller.

Morecambe North (DPPA) offshore installation.

In 1984 a single drilling and production platform was installed in the Morecambe North field.[5] [6]

Platform Block Coordinates Water depth Operational Export
Morecambe North 110/2a 53.960578N 3.670694W 29 metres October 1994 37 km pipeline to Barrow

The Bains field was developed in 2002 by a single subsea wellhead producing well fluids to DP1 via a 8.3 km 8-inch pipeline.[5]

The Bains field was developed in 2002 by a single subsea wellhead producing well fluids to DP1 via a 8.3 km 8-inch pipeline.[5]

Field Block Coordinates Water depth Operational
Bains 110/3c 53.875833N 3.465556W 18 metres 2002

The North Morecambe platform was modified to tie in the Millom East / West and Dalton fields, and in 2013 the addition of the Rhyl field.[5]

Production

Well fluids from the wellhead platforms are piped to the CPP1 platform. Three phase separation into gas, condensate and water is undertaken. The gas is dehydrated using tri-ethylene glycol. Dry gas together with condensate is piped ashore.[3]

Initial production from Morecambe South field in the winter of 1984-5 was 120 million standard cubic feet of gas per day (MMSCFD). This increased to 450 MMSCFD in the winter of 1985-6 and ultimately to 1,200 MMSCFD.[3] The first year of peak production was 1993 when the South field produced 8.6 billion cubic metres per year.[1]

The first year of peak production for the Morecambe North field was 1995 when the field produced 3.1 billion cubic metres of gas per year.[1]

Decommissioning

The decommissioning of the DP3 and DP4 platforms is currently (2021) underway.[6] [7]

See also

References

  1. 1 2 3 Department of Trade and Industry (1994). The Energy Report. London: HMSO. pp. 73, 74, Map 3. ISBN 0115153802.
  2. 1 2 More, Charles (2009). Black Gold. London: continuum. pp. 165–6. ISBN 9781847250438.
  3. 1 2 3 4 5 6 Oilfield Publications Limited (1985). The North Sea Platform Guide. Ledbury: Oilfield Publications Limited. pp. 526–39.
  4. "The South Morecambe Gas Field, Blocks 110/2a, 110/3a, 110/7a and 110/8a, East Irish Sea". lyellcollection.org. Retrieved 6 November 2021.
  5. 1 2 3 4 5 "Spirit Energy infrastructure" (PDF). spirit-energy.com. Retrieved 6 November 2021.
  6. 1 2 "South Morecambe DP3-DP4 Decommissioning Environmental Appraisal" (PDF). spirit-energy.com. Retrieved 6 November 2021.
  7. "South Morecambe DP3-DP4 Decommissioning Programmes" (PDF). gov.uk. Retrieved 6 November 2021.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.