JW3
Nanyang Gateway 南洋门 நன்யாங் கேட்வே | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Future Mass Rapid Transit (MRT) station | |||||||||||
General information | |||||||||||
Coordinates | 1°21′13″N 103°41′12″E / 1.35369°N 103.68661°E | ||||||||||
Owned by | Land Transport Authority | ||||||||||
Line(s) | |||||||||||
Platforms | 2 (1 island platform) | ||||||||||
Tracks | 2 | ||||||||||
Construction | |||||||||||
Structure type | Elevated | ||||||||||
Platform levels | 1 | ||||||||||
Parking | Yes | ||||||||||
Bicycle facilities | Yes | ||||||||||
Accessible | Yes | ||||||||||
History | |||||||||||
Opening | 2029 | ||||||||||
Electrified | Yes | ||||||||||
Services | |||||||||||
| |||||||||||
Location | |||||||||||
Nanyang Gateway Nanyang Gateway station in Singapore |
Nanyang Gateway MRT station is a future elevated Mass Rapid Transit (MRT) station on the Jurong Region line in Western Water Catchment, Singapore. The station will be located within the Nanyang Technological University (NTU).
History
On 9 May 2018, the Land Transport Authority (LTA) announced that Nanyang Gateway station would be part of the proposed JRL.[1][2] The station will be constructed as part of Phase 3, consisting of 7 stations – a 4 station extension to this station from Boon Lay and a 3 station extension to Peng Kang Hill from Tawas. It was expected to be completed in 2028.[3] However, the restrictions on construction due to the COVID-19 pandemic has led to delays, with the completion date pushed to 2029.[4]
The contract for the design and construction of the Nanyang Gateway and Nanyang Crescent stations and 1.4 km (0.87 mi) of associated viaducts – Contract J113[5] – was awarded to Hwa Seng Builder Pte Ltd at S$263 million (US$192.8 million) on 6 April 2021. Construction is scheduled to start in the second quarter of 2021, with expected completion in 2029.[6]
Station details
The station will serve the JRL and will be located between the Tawas and Nanyang Crescent stations. The official station code will be JW3.[7] The station will span over Nanyang Avenue and has four entrances, serving the NTU Hall of Residence and Staff Residence.[8]
References
- ↑ "Jurong Region Line to serve NTU, Tengah estate, Jurong Industrial Estate - CNA". CNA. 21 September 2019. Archived from the original on 21 September 2019. Retrieved 21 September 2019.
- ↑ Lim, Adrian (9 May 2018). "New Jurong Region Line to boost access for NTU students". The Straits Times. Archived from the original on 9 April 2021. Retrieved 9 April 2021.
- ↑ "News Room - News Releases - Joint News Release by the Land Transport Authority (LTA) & SLA - Jurong Region Line: Enhancing Connectivity in the West". Land Transport Authority. 9 April 2021. Archived from the original on 9 April 2021. Retrieved 9 April 2021.
- ↑ "Written Reply by Minister for Transport Ong Ye Kung to Parliamentary Question on Prioritising Early Completion of Jurong Region MRT Line". www.mot.gov.sg. 1 February 2021. Archived from the original on 9 April 2021. Retrieved 24 March 2021.
- ↑ "Contract J113" (PDF). Land Transport Authority. Archived (PDF) from the original on 9 April 2021. Retrieved 9 April 2021.
- ↑ "Two Civil Contracts to Construct Four Stations for the Jurong Region Line Awarded". Land Transport Authority. 6 April 2021. Archived from the original on 6 April 2021. Retrieved 8 April 2021.
- ↑ "Future system map" (PDF). Land Transport Authority. Archived (PDF) from the original on 5 April 2021. Retrieved 9 April 2021.
- ↑ "JW3 Nanyang Gateway". Land Transport Authority. Archived from the original on 10 April 2021. Retrieved 10 April 2021.