Tutow Solar Park | |
---|---|
Country | Germany |
Location | Demmin |
Coordinates | 53°55′17″N 13°13′09″E / 53.92139°N 13.21917°E |
Status | Operational |
Commission date | 2009-2011 |
Solar farm | |
Type | Flat-panel PV |
Site area | 22 ha (54.4 acres) Site plan |
Power generation | |
Nameplate capacity | 52 MW |
The Tutow Solar Park is in Demmin, Germany,[1] and is located at Tutow Airport.[2]
The first phase of the project, Tutow I was commissioned in 2009, using 91,200 First Solar thin film modules, with a total rating of 6782 kWp, and was expected to produce 6.7 GWh per year.[3] The second, Tutow II, brought the total to 25.4 MWp, about four times larger, in 2010,[4] and was expected to produce 26 GWh/year using a total of 335,400 panels, and the third section, Tutow III, making the total 52 MWp, was completed in 2011.[5]