British Rail BEMU
Battery Multiple Unit at Milton of Crathes
In service1958–1966
Built atDerby Works - converted to battery at Cowlairs
Family nameDerby Lightweight
ReplacedSteam locomotives and carriages
Constructed1956 - converted 1958
Number built1 set (2 cars)
Number preserved1 set (2 cars)
FormationDMBS-DTC
Capacity12 first
105 second (initially 31 + 86)
OperatorsBritish Railways
Specifications
Car body constructionSteel
Car length57 ft 6 in (17.53 m)
Doors2 on each side
Maximum speed60 miles per hour (97 km/h)
WeightDMBS: 37 long tons 10 cwt (84,000 lb or 38.1 t)
DTC: 32 long tons 10 cwt (72,800 lb or 33 t)
Prime mover(s)2 x 100 kilowatts (130 hp) nose-suspended motors
Power supplyChloride Batteries Ltd
Electric system(s)216 lead-acid cells, 440 V, 1070 A·hr
Track gauge4 ft 8+12 in (1,435 mm)

The British Rail BEMU was an experimental two-car battery electric multiple unit (BEMU), converted from the prototype Derby Lightweight Diesel multiple units. The train was powered by many lead-acid batteries, and was used on the Deeside Railway from Aberdeen to Ballater in Scotland from April 1958 until it was finally withdrawn in December 1966. The North of Scotland Hydro-Electric Board initiated the design and was a joint sponsor. The board promised to supply power at three farthings per unit for a fixed two-year period.[1] It provided an 11kV supply to a charger at Aberdeen's platform 1 and a 6.6kV supply to a charger at Ballater.[2]

Career

The estimated cost of the fit-out was £50,000, with the two coaches accounting for almost half of that. Because each set of batteries weighed about eight tons, the underframe of the carriages needed strengthening,[2] at a budgeted cost of £2,000. Motors, conduits and cabling were costed at £5,000.[1]

The unit was equipped with a new type of battery in the early 1960s, but subsequently suffered a series of small fires in the battery areas and was withdrawn from service. It returned to use for a period before closure of the line in 1966.

Departmental use and preservation

The train then spent a short time in storage at Inverurie Works, and at Hyndland Shed in Glasgow, before being transferred to departmental use as test train "Gemini" (or "Laboratory 16") for use at the Railway Technical Centre, at Derby.[1] It lasted in this role until it was withdrawn in 1984, and was eventually bought for preservation at the proposed West Yorkshire Transport Museum, where it was returned to working order. The museum placed it on loan to the East Lancashire Railway in 1994 where, after asbestos was removed and the batteries refurbished, it was used on some services until 2000.[1] After the museum went into liquidation, the unit was purchased by the Royal Deeside Railway near Crathes, in 2001. It is now back in Scotland, where it is undergoing refurbishment.

Details are as follows:

Vehicle Nos. Location Comments Departmental Nos.
DMBS DTC DMBS DTC
79998 79999 Royal Deeside Railway Used as test train "Gemini" (Lab 16). 975003 975004

References

  1. 1 2 3 4 Mullay, Alexander (August 2004). "Batteries Included". The Railway Magazine. pp. 56–58.
  2. 1 2 "First Battery Railcars on BR". The Railway Magazine. Vol. 104, no. 686. June 1958. pp. 419–420.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.