G:link | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | Translink | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Gold Coast, Queensland, Australia | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Transit type | Light rail | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of lines | 1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of stations | 19 (27 after stage 3 completion) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Annual ridership | 10.74 million (2018/19) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Chief executive | Phil Mumford | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Headquarters | Southport | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Website | www.ridetheg.com.au | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operation | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Began operation | 20 July 2014 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | Keolis Downer | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of vehicles | 18 Bombardier Flexity 2 trams | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Train length | 43.5 m (143 ft) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Headway | 7-30 minutes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System length | 20 km (12 mi) (26 km (16 mi) after stage 3 completion) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | 750 V DC overhead catenary | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Average speed | 27 km/h (17 mph) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Top speed | 70 km/h (43 mph) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
G:link, also known as the Gold Coast Light Rail and the Gold Coast Tram, is a light rail system serving the Gold Coast in Queensland, Australia, and is the sole light rail system in Queensland. The system forms part of Translink's South East Queensland public transport network and consists of a single 20 km (12 mi) line of nineteen stations. The Helensvale railway station is the northern terminus of the system, while Broadbeach South is the southern terminus. The line opened on 20 July 2014 and was extended northwest from Gold Coast University Hospital to Helensvale on 17 December 2017.
Background
The Gold Coast is one of the fastest-growing regions in Australia, with an annual population growth of 2–3%.[1] The project was first proposed in the Gold Coast City Council Transport Plan 1996 after some years of consideration and review. In 2002, the Queensland and Federal Governments each contributed $650,000 to fund the Gold Coast Light Rail Feasibility Study.[2][3] In 2004, the draft summary report was released.[4]
History
Stage 1
In 2009, the Queensland Government committed $464 million to the Gold Coast Rapid Transit (GCRT) project, supplementing $365 million committed by the Federal Government and $120 million provided by Gold Coast City Council.[5]
In June 2011, the GoldLinq consortium comprising Bombardier Transportation, Downer EDI, Keolis, McConnell Dowell and Plenary Group was awarded the contract to build and operate the Gold Coast light rail line for 18 years under a Public Private Partnership.[6][7][8]
In August 2012, the cost of the initial 13 km (8.1 mi) section was estimated at $1.6 billion.[9] Construction began on the Gold Coast University Hospital station shell in July 2010.[10] In late 2010, early roadworks began in Broadbeach and Southport.[11]
By November 2013, much of the work was complete with the southern section at Broadbeach being the only section of trackwork to be completed. Testing commenced on the northern section of the line in October 2013. The line opened on 20 July 2014, with a free travel day, before normal operations began on 21 July.[12][13][14]
The system had a significant impact on property both directly and indirectly in the corridor. A total of $170 million was allocated for property resumptions. The Queens Park Tennis Club and Southport Croquet Club were both relocated.[15]
Stage 2
After the successful opening and operations of Stage 1, the Queensland Government announced in February 2016 plans to extend the light rail line from the University Hospital to the Helensvale railway station, providing a connection with the Gold Coast railway line that connects the city with Brisbane, the state capital of Queensland. Financial commitment from the state and federal governments needed to progress with the extension was finalised in late 2016. The new extension includes 7.3 km (4.5 mi) tracks and 3 new light rail stations, with Helensvale being the new northern terminus for the line. Construction commenced in 2016[16] with plans to be completed in time for the 2018 Gold Coast Commonwealth Games in April 2018. Construction finished early, ahead of schedule with passenger services commencing in December 2017.
Stage 3 extension
The Queensland Government, in conjunction with the Gold Coast City Council and the Federal Government, announced the plan to extend the light rail line 6.4 km (4.0 mi) south, from the existing Broadbeach South station to Burleigh Heads back in 2018 with the original completion date to be in 2024. Due to funding disputes among the three levels of government, the COVID-19 pandemic along with rising construction costs in recent years, the project kept getting delayed. In February 2020, three parties were short-listed to build the extension:[17]
- a CPB Contractors / Seymour Whyte joint venture
- a Fulton Hogan / UGL Rail joint venture
- John Holland
It was announced in October 2020 that John Holland had won the contract,[18] with the state government releasing a statement in 2021 saying that the agreement will see the construction consortium undertake detailed construction planning and start establishing a site presence along the 6.7-kilometre (4.2 mi) corridor.[1]
In July 2022 construction formally started with water, sewerage and gas infrastructure upgrades and relocation on the Gold Coast Highway between Broadbeach and Nobby Beach.[3] Major construction including earthworks and construction of the tracks will commence in 2023 with the project expected to be operational by 2025.[4]
Planned stations
Eight new light rail stations will be constructed with the original cost estimate of the project at $670 million,[19] which has now blown out to $1.2 billion[6] due largely to rising inflation post-pandemic.
Route
The new extension will begin from the current southern terminus, Broadbeach South travelling on the median strip of the Gold Coast Highway for the whole way south to Burleigh Heads. The 6.7 km (4.2 mi) extension will pass through Mermaid Beach, Nobby's Beach, Miami and Burleigh Heads[7] with the hopes of creating better connectivity, reducing congestion and improving travel times.[8]
Stage 4 extension
The Gold Coast City Transport Strategy 2031 supports a future expansion to Coolangatta via the Gold Coast Airport.[20] The 14 km (8.7 mi) extension of the light rail line from Burleigh Heads station would continue south along the Gold Coast Highway, passing through the southern suburbs of Palm Beach and Tugun and connecting the city's international airport with the light rail. A potential light rail corridor has also been identified from the Airport to Coolangatta and will be preserved for possible future expansion.[21] In August 2020, funding was provided to formulate a business case for the extension.[22] Since 2021 community consultation and preliminary works have begun on stage 4.[9]
Route
The single 20-kilometre (12 mi) line runs from Helensvale railway station to Broadbeach South. Beginning at Helensvale railway station, the line runs parallel to the Gold Coast railway line until it meets the Smith Street Motorway, which it then follows, stopping at Parkwood and Parkwood East. The next two stops serve the Gold Coast University Hospital and the Gold Coast campus of Griffith University. The line runs south, passing over the Smith Street Motorway and the depot before reaching Queen Street station and Nerang Street station that services the Southport medical precinct. The next two stops serve the Australia Fair Shopping Centre, and the following stop serves the Broadwater Parklands. The line passes over the Nerang River before reaching the only stop in Main Beach, which serves the Sea World theme park. The next stops are Surfers Paradise North and Cypress Avenue, the latter serving the Chevron Renaissance Shopping Centre and the Funtime amusement park. The next stop, Cavill Avenue serves the heart of Surfers Paradise including the Cavill Avenue pedestrian mall and Paradise Centre shopping centre. The following station services the Q1 residential tower as well as the SkyPoint observation deck. The next stops are Northcliffe, Florida Gardens and Broadbeach North, the latter serving the Gold Coast Convention & Exhibition Centre, The Star Gold Coast, the Oasis Shopping Centre and the Oracle Shopping Centre. The line terminates at Broadbeach South which serves Pacific Fair Shopping Centre and provides bus connections to southern suburbs as well as the Gold Coast Airport. It takes around 44 minutes to travel from one end of the line to the other.
There are nineteen stations on the line. One station is located in Helensvale, two are in Parkwood, seven are in Southport, one is in Main Beach, six are in Surfers Paradise, and two are in Broadbeach. All but one of the stations is street-level open-air structures with passenger canopies on the platforms. The Gold Coast University Hospital station is underground. Eleven stations have side platforms and eight have island platforms. Eight of the stations have kiosks on the platforms. Seven stations offer transfers to bus services and Helensvale also offers transfers to train services. Two of the stations have free park-and-ride lots with a total of 1,400 new parking spaces.[23][24] The most heavily trafficked station is Cavill Avenue, with an average of 4,729 daily passengers in February 2016.[25]
Infrastructure
The system uses standard gauge tracks with 750 V DC overhead catenary. It primarily operates in a centre-running configuration.
Rolling stock
The Gold Coast Rapid Transit fleet consists of 18 Bombardier Flexity 2 trams built in Germany.[26] The trams feature low floors and have dedicated spaces for wheelchairs, prams and surfboards.[27] They have a top speed of 70 km/h (43 mph) and room for 309 passengers with seating for 80.[28] Fourteen trams were ordered to serve the original section of the line. Four additional trams were ordered in November 2015 to service the Helensvale extension.[29] These were delivered in September and October 2017.[30] As at July 2023 a further 5 vehicles are under construction or in commissioning.
Operation
Services are operated by Keolis Downer, a joint venture between Keolis and Downer. Fares are set by Translink with all stations fitted with go card readers.[31] Translink charges fares that increase as passengers travel through eight concentric zones radiating outward from the Brisbane central business district;[32] All G:link stations are located within zone 5.
Service frequencies (in minutes) from 17 December 2017:[33]
Weekdays | Weekends | |
---|---|---|
00:00 to 05:00 | Closed | 30† |
05:00 to 07:00 | 15 | 15 |
07:00 to 19:00 | 7.5 | 10 |
19:00 to 23:30 | 15 | 15 |
† No service between Helensvale station and Gold Coast University Hospital
On Monday to Friday mornings (midnight to 5 am), light rail services are replaced on most of the routes by Kinetic Group route 700.[34] These buses do not service the section between Helensvale station and Gold Coast University Hospital.[33]
Patronage
Over 1.74 million passengers used the Gold Coast Light Rail in its first 100 days after opening. More than five million paid trips were made in the first nine months of operation.[35] 6.6 million passengers were carried on the line in its first year, and total public transport users on the Gold Coast - across buses and trams - increased by 25 per cent.[36][37] In February 2016 the Queensland Government announced the ten million passenger milestone had been reached and noted that Cavill Avenue was the busiest station with 4,729 boardings a day.[38]
The following table lists patronage figures for the network during the corresponding financial year. Australia's financial years start on 1 July and end on 30 June. Major events that affected the number of journeys made or how patronage is measured are included as notes.
Year | 2014–15 | 2015–16 | 2016–17 | 2017–18 | 2018–19 | 2019–20 | 2020–21 | 2021–22 | 2022–23 | |
---|---|---|---|---|---|---|---|---|---|---|
Patronage (millions) |
6.28 [lower-alpha 1] | 7.68 | 7.97 | 9.49 [lower-alpha 2][lower-alpha 3] | 10.74 | 8.46 [lower-alpha 4] | 6.12 [lower-alpha 5] | 6.34 [lower-alpha 6] | 10.39 | |
Reference | [39] | [40] | [41] | [42] | [43] | [44] | [45] | [46] | [47] | |
| |
Bus | 14 000 000[48] |
Light rail | 10 740 000[49] |
Heavy rail | 5 800 000[50] |
- ↑ G:link system opened in July 2014.
- ↑ Helensvale extension opened in December 2017.
- ↑ Commonwealth Games held in April 2018.
- ↑ In response to the COVID-19 pandemic, travel restriction were introduced in March 2020.
- ↑ Patronage numbers heavily affected by COVID-19 pandemic travel restrictions.
- ↑ Patronage numbers heavily affected by COVID-19 pandemic travel restrictions.
Potential extensions
Besides Stages 3 and 4, the Gold Coast City Council envisions an extensive light rail network that would potentially consist of 68 km (42 mi) of track and 4 light rail lines as outlined in the City Transport Strategy 2031. Future extensions however are not expected to take place until after stage 4 is fully completed and further feasibility studies are undertaken.
Main Beach and The Spit
A branch line from Main Beach to The Spit was proposed in the Gold Coast City Council's 2031 transport plan, City Transport Strategy 2031.[51] The council announced a number of potential route options in April 2017 and invited public comment.[52] The line is expected to cost around $200 million and would be paid for by developers and would be around 2.6 km (1.6 mi) long. The time frame for construction remains undecided but is not expected to be completed until after the extension to the Gold Coast Airport.[53]
Biggera Waters
The Gold Coast's council 2031 Transport plan published outlines a possible extension to Biggera Waters.[54] The proposed line would branch off from the existing University Hospital light rail station, travelling north before terminating at Harbour Town Shopping Centre in the suburb of Biggera Waters. It is not expected for the line to be completed until after the extension to the Gold Coast Airport.
Bundall
The Gold Coast's council 2031 Transport plan published outlines a possible extension to Bundall.[55] The proposed line would branch off from Cavill Avenue, travelling west for several kilometres before terminating in the suburb of Bundall. Stations may include Chevron Island, HOTA, Bundall Business District and Gold Coast Turf Club. It is not expected for the line to be completed until after the extension to the Gold Coast Airport.
Nerang
The Gold Coast's council 2031 Transport plan published outlines a possible extension to the Nerang.[56] The proposed line would spur off from Broadbeach, travelling west along Hooker Boulevard and north along Nerang–Broadbeach Road before terminating at the Nerang railway station. Stations would include Mermaid Waters, Carrara Markets and Carrara Stadium.
Robina
A 9 km (5.6 mi) Robina extension is proposed in the Gold Coast City Council's Light Rail southern Gold Coast publication.[57] The proposed extension would branch off from Nobbys Beach and terminate at Robina railway station passing through Bond University, Market Square, Robina Town Centre and Robina Stadium. It is not expected for the line to be completed until after the extension to the Gold Coast Airport.
Varsity Lakes
The Light Rail southern Gold Coast published by the Gold Coast City Council also outline a proposal extension to Varsity Lakes[58] from Burleigh Heads. The extension would branch out from Burleigh Heads and follow Burleigh Connection Road, passing by Stocklands Burleigh Heads Shopping Centre and the light industrial areas of West Burleigh before terminating at Varsity Lakes railway station, providing a heavy rail connection. It is not expected for the line to be completed until after the extension to the Gold Coast Airport
Tweed Heads
On 19 February 2019, Tweed Heads MP Geoff Provest announced $1 million of funding towards strategic planning to extend the Gold Coast light rail system from the Gold Coast Airport to over the New South Wales border into Tweed Heads.[59]References
- 1 2 Estimated Resident Population Archived 14 December 2013 at the Wayback Machine Profile.id
- ↑ "Gold Coast Rapid Transit Corridor Study". City of Gold Coast. Archived from the original on 11 December 2013. Retrieved 6 December 2013.
- 1 2 "Gold Coast Light Rail Feasibility". Department of Infrastructure & Regional Development. 14 May 2002. Archived from the original on 14 December 2013. Retrieved 14 December 2013.
- 1 2 "Gold Coast Light Rail Feasibility Study" (PDF). Parsons Brinckerhoff. Archived from the original (PDF) on 20 February 2011. Retrieved 6 December 2013.
- ↑ Chambers, Geoff (14 February 2010). "Chinese in Gold Coast's rapid transit mix". Gold Coast Bulletin. Archived from the original on 4 November 2013. Retrieved 6 December 2013.
- 1 2 "GoldLinQ Selected for Gold Coast Light Rail". Plenary Group (Press release). 5 May 2011. Archived from the original on 12 December 2013. Retrieved 30 March 2022.
- 1 2 "GoldlinQ selected to build Gold Coast light rail". Railway Gazette International. 6 May 2011. Archived from the original on 12 December 2013. Retrieved 6 December 2013.
- 1 2 "GoldLinQ wins £657M Australian rail project". New Civil Engineer. 9 May 2011. Archived from the original on 11 December 2013. Retrieved 6 December 2013.
- 1 2 Stolz, Greg; Vogler, Sarah (8 August 2012). "Court bid to halt $1.6 billion Gold Coast light rail project". Herald Sun. Retrieved 6 December 2013.
- ↑ "Light rail work starts this month". Gold Coast Bulletin. 4 July 2010. Archived from the original on 24 March 2012. Retrieved 6 December 2013.
- ↑ Gold Coast Rapid Transit. Queensland Government. June 2011.
- ↑ "First test tram run in Southport". GoldLinQ. 1 October 2013. Retrieved 6 December 2013.
- ↑ "Works updates". GoldLinQ. 4 December 2013.
- ↑ All aboard: Gold Coast light rail officially launches with full tram cars for day of free travel Archived 28 July 2014 at the Wayback Machine Gold Coast Bulletin 20 July 2014
- ↑ Chambers, Geoff (24 December 2009). "Flurry of Coast rapid transit resumptions". Gold Coast Bulletin. Archived from the original on 24 March 2012. Retrieved 6 December 2013.
- ↑ "Gold Coast Light Rail Stage 2". www.tmr.qld.gov.au. corporateName=Department of Transport and Main Roads; jurisdiction=Queensland; sector=government. 13 July 2016. Archived from the original on 19 March 2018. Retrieved 5 July 2018.
{{cite web}}
: CS1 maint: others (link) - ↑ Preparation works continue for Gold Coast Light Rail Stage 3A construction Rail Express 20 April 2020
- ↑ 2020-10-06T13:49:00+01:00. "John Holland to build Stage 3 of Gold Coast light rail". Railway Gazette International. Archived from the original on 22 October 2020. Retrieved 24 October 2020.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - ↑ Gold Coast Light Rail Stage 3A. Gold Coast, Australia: City of Gold Coast. 2018.
- ↑ Services, corporateName=Planning, Environment & Transport | City Transport | Web. "Light rail". www.goldcoast.qld.gov.au. Archived from the original on 10 July 2018. Retrieved 3 July 2018.
{{cite web}}
: CS1 maint: multiple names: authors list (link) - ↑ Services, corporateName=Planning, Environment & Transport | City Transport | Web. "Gold Coast City Transport Strategy 2031". www.goldcoast.qld.gov.au. Archived from the original on 15 April 2018. Retrieved 3 July 2018.
{{cite web}}
: CS1 maint: multiple names: authors list (link) - ↑ Gold Coast light rail extension study funded Metro Report International 11 August 2020
- ↑ Moore, Tony (7 August 2015). "Gold Coast light rail stage two and Brisbane link unveiled". Brisbane Times. Fairfax Media. Archived from the original on 17 September 2016. Retrieved 10 June 2016.
- ↑ "Gold Coast light rail Stage 2 contractor selected". Railway Gazette International. 21 March 2016. Archived from the original on 26 June 2016. Retrieved 11 June 2016.
- ↑ Skene, Kathleen (5 February 2016). "Gold Coast light rail hits 10 million tram passenger mark as tender announcement nears for stage two". Gold Coast Bulletin. News Corp Australia. Archived from the original on 13 February 2017. Retrieved 10 June 2016.
- ↑ "GoldLinQ CEO Phil Mumford inspects construction of first tram in Germany". GoldLinkQ. 14 September 2012. Archived from the original on 11 December 2013. Retrieved 6 December 2013.
- ↑ "The tram". GoldLinkQ. 14 November 2013. Archived from the original on 11 December 2013. Retrieved 6 December 2013.
- ↑ Silva, Kristian (20 September 2013). "Gold Coast trams unveiled". Brisbane Times. Archived from the original on 26 December 2013. Retrieved 6 December 2013.
- ↑ "Record of Proceedings (proof) First Session of the Fifty-fifth Parliament Thursday, 12 November 2015" (PDF). Queensland Parliament. 12 November 2015. p. 2826. Archived (PDF) from the original on 13 September 2017. Retrieved 14 September 2017.
- ↑ New trams arrive for Gold Coast light rail Archived 7 May 2018 at the Wayback Machine Rail Express 26 September 2017
- ↑ "Gold Coast Light Rail Fare Cost". Gold Coast Light Rail. 16 September 2013. Archived from the original on 13 July 2014. Retrieved 16 July 2014.
- ↑ "Zones". TransLink. Queensland Government. 2016. Archived from the original on 1 June 2016. Retrieved 11 June 2016.
- 1 2 "Gold Coast Light Rail Stage 2 - Opening 17 December". Translink. Queensland Government. Archived from the original on 12 April 2018. Retrieved 17 December 2017.
- ↑ "Route 700 timetable". Translink.
- ↑ Tony Moore (6 May 2015). "Five million people jump on board Gold Coast Light Rail since July 2014". brisbane times. Fairfax Media. Archived from the original on 12 May 2015. Retrieved 7 May 2015.
- ↑ "Short list named for Gold Coast light rail Stage 2". GoldLinQ. 1 October 2015. Archived from the original on 9 February 2016. Retrieved 9 November 2015.
- ↑ "Key statistics". gclrstage2.com. Goldlinq. Archived from the original on 25 May 2016. Retrieved 5 March 2016.
- ↑ Skene, Kathleen (6 February 2016). "Gold Coast light rail hits 10 million tram passenger mark as tender announcement nears for stage two". Gold Coast Bulletin.
- ↑ "TMR Annual Report 2014-15 Appendix 2 – Performance statements 2014-15". Department of Transport and Main Roads. Archived from the original on 15 December 2016. Retrieved 12 October 2016.
- ↑ "TMR Annual Report – Appendix 2 – Performance statements 2015–16" (PDF). Department of Transport and Main Roads. p. 255. Archived (PDF) from the original on 1 December 2016. Retrieved 12 October 2016.
- ↑ "Department of Transport and Main Roads Annual Report 2016–17" (PDF). Department of Transport and Main Roads. p. 221. Archived (PDF) from the original on 2 December 2017. Retrieved 13 November 2017.
- ↑ "Department of Transport and Main Roads Annual Report 2017–18 - Appendix 2 – Performance Statements 2017–18" (PDF). Department of Transport and Main Roads. p. 242. Archived (PDF) from the original on 6 February 2023. Retrieved 3 October 2018.
- ↑ "Department of Transport and Main Roads Annual Report 2018–19 - Appendices – Annual Report 2018–19" (PDF). Department of Transport and Main Roads. p. 285. Archived (PDF) from the original on 28 March 2020. Retrieved 23 October 2019.
- ↑ "Department of Transport and Main Roads Annual Report 2019–20 - Appendices – Annual Report 2019–20" (PDF). Department of Transport and Main Roads. p. 186. Retrieved 18 December 2020.
- ↑ "Department of Transport and Main Roads Annual Report 2020–21 - Appendices – Annual Report 2020–21" (PDF). Department of Transport and Main Roads. p. 175. Retrieved 27 December 2021.
- ↑ "Department of Transport and Main Roads Annual Report 2021–22 - Appendices – Annual Report 2021–22" (PDF). Department of Transport and Main Roads. p. 206. Retrieved 22 December 2022.
- ↑ "Department of Transport and Main Roads Annual Report 2022–23 - Appendices – Annual Report 2022–23" (PDF). Department of Transport and Main Roads. p. 218. Retrieved 14 December 2023.
- ↑ "Adopted Report of the Transport and Infrastructure Committee Meeting" (PDF). City of Gold Coast Council Chambers. p. 49. Archived (PDF) from the original on 28 March 2020. Retrieved 20 March 2020.
- ↑ "Department of Transport and Main Roads Annual Report 2018–19 - Appendices – Annual Report 2018–19" (PDF). Department of Transport and Main Roads. p. 285. Archived (PDF) from the original on 28 March 2020. Retrieved 23 October 2019.
- ↑ "Cross River Rail to deliver three new stations on the booming Gold Coast line". Cross River Rail Delivery Authority - Queensland Government. Archived from the original on 27 February 2020. Retrieved 17 January 2020.
- ↑ "Draft Gold Coast City Transport Strategy 2031" (PDF). City of Gold Coast. 2012. pp. 6, 7. Archived from the original (PDF) on 11 December 2013. Retrieved 5 January 2013.
- ↑ "Light Rail - Main Beach to The Spit". Gold Coast City Council. Archived from the original on 9 April 2017. Retrieved 8 April 2017.
- ↑ Pierce, Jeremy (2 April 2017). "First look at Gold Coast's planned $200m light rail extension to The Spit". The Courier Mail.
- ↑ Gold Coast City Transport Strategy 2031. City of Gold Coast. p. 19.
- ↑ Gold Coast City Transport Strategy 2031. City of Gold Coast. p. 19.
- ↑ Gold Coast City Transport Strategy 2031. City of Gold Coast. p. 19.
- ↑ Light Rail Southern Gold Coast. Gold Coast, Australia: City of Gold Coast. p. 3.
- ↑ Light Rail Southern Gold Coast. Gold Coast, Australia: City of Gold Coast. p. 4.
- ↑ Cross border light rail from Tweed to Coolangatta
External links