This is a list of all the commercial nuclear reactors in the world, sorted by country, with operational status. The list only includes civilian nuclear power reactors used to generate electricity for a power grid. All commercial nuclear reactors use nuclear fission. As of September 2023, there are 412 operable power reactors in the world, with a combined electrical capacity of 368.6 GW. Additionally, there are 60 reactors under construction and 110 reactors planned, with a combined capacity of 67 GW and 107 GW, respectively, while 321 more reactors are proposed.[1] For non-power reactors, see List of nuclear research reactors. For fuel plants see List of Nuclear Reprocessing Plants. Where not otherwise specified, all information is sourced from the Power Reactor Information System (PRIS) of the International Atomic Energy Agency (IAEA).[2]

In the following tables, the capacity (expressed in megawatt, MW) refers to the net capacity, or the maximum electricity output under reference ambient conditions, after deducting the losses within the system including the energy transformers.[3]

Argentina

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Atucha[4]1PHWRSiemens-KWUOperational3351 Jun 196824 Jun 1974
2PHWRSiemens-KWUOperational69214 Jul 198127 Jun 2014
3PWRHualong OnePlanned[5]1200
Embalse[6]1PHWRCANDU-6Operational6001 Apr 197420 Jan 1984(2049)[7]
CAREM1PWRCAREM25Under construction258 Feb 2014

Armenia

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Metsamor1PWRVVER-440/V-270Shut down3761 Jul 19696 Oct 197725 Feb 1989
2PWRVVER-440/V-270Operational3751 Jul 19753 May 1980(2026)[8]

Austria

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Zwentendorf1BWRBWR-69 (KWU)Finished; never entered service878Apr 19725 Nov 1978

Bangladesh

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Rooppur1PWRVVER-1200/V-523Under construction108030 Nov 2017[9](2024)[10]
2PWRVVER-1200/V-523Under construction108014 Jul 2018(2025)

Belarus

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Ostrovets1PWRVVER-1200/V-491Operational11096 Nov 201310 Jun 2021[11]
2PWRVVER-1200/V-491Operational110924 Apr 20141 Nov 2023[12]
Minsk1PWRVVER-1000Unfinished96319831987
2PWRVVER-1000Unfinished96319831987

Belgium

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
SCK•CEN1PWRWestinghouse (WH) BR-3Decommissioned101 Nov 195710 Oct 196230 Jun 1987
Doel1PWRWH 2 loopsOperational4451 Jul 196915 Feb 1975(2025)
2PWRWH 2 loopsOperational4451 Sep 19711 Dec 1975(2025)
3PWRFramatome 3 loopsShut down10061 Jan 19751 Oct 198223 Sep 2022[13]
4PWRBelgian firms plus WH 3 loopsOperational10391 Dec 19781 Jul 1985(2035)[14]
Tihange1PWRFramatome 3 loopsOperational9621 Jun 19701 Oct 1975(2025)
2PWRFramatome 3 loopsShut down10081 Apr 19761 Jun 198331 Jan 2023[15]
3PWRBelgian firms plus WH 3 loopsOperational10461 Nov 19781 Sep 1985(2035)

Brazil

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Angra1PWRWH 2 loopsOperational6091 May 19711 Jan 1985
2PWRPre-KonvoiOperational12751 Jan 19761 Feb 2001
3PWRPre-KonvoiUnder construction12451 Jun 2010(2028)[16]

Bulgaria

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Kozloduy1PWRVVER-440/V-230Shut down4081 Apr 197028 Oct 197431 Dec 2002
2PWRVVER-440/V-230Shut down4081 Apr 197010 Nov 197531 Dec 2002
3PWRVVER-440/V-230Shut down4081 Oct 197320 Jan 198131 Dec 2006
4PWRVVER-440/V-230Shut down4081 Oct 197320 Jun 198231 Dec 2006
5PWRVVER-1000/V-320Operational10039 Jul 198023 Dec 1988
6PWRVVER-1000/V-320Operational10031 Apr 198230 Dec 1993
7PWRAP1000Planned[17]1150(2033)[17]
8PWRAP1000Planned[17]1150
Belene1PWRVVER-1000/V-320
VVER-1000/V-446B
Unfinished953
1011
1987
2008
2PWRVVER-1000/V-320
VVER-1000/V-446B
Unfinished953
1011
1987
2008

Canada

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Pickering1PHWRCANDU 500AOperational515Jun 196629 Jul 1971(2024)
2PHWRCANDU 500AShut down515Sep 196630 Dec 19711997[18]
3PHWRCANDU 500AShut down515Dec 19671 Jun 19721997
4PHWRCANDU 500AOperational515May 196817 Jun 1973(2024)
5PHWRCANDU 500BOperational516Nov 197410 May 1983(2026)
6PHWRCANDU 500BOperational516Oct 19751 Feb 1984(2026)
7PHWRCANDU 500BOperational516Mar 19761 Jan 1985(2026)
8PHWRCANDU 500BOperational516Sep 197628 Feb 1986(2026)[19]
Darlington1PHWRCANDU 850Operational878Apr 198214 Nov 1992(2052)
2PHWRCANDU 850Operational878Sep 19819 Oct 1990(2050)
3PHWRCANDU 850Operational878Sep 198414 Feb 1993(2053)
4PHWRCANDU 850Operational878Jul 198514 Jun 1993(2053)
5[20]BWRBWRX-300Planned300(2023)(2028)
6[20]BWRBWRX-300Planned300(2023)(2028)
7BWRBWRX-300Planned300(2023)(2029)
8BWRBWRX-300Planned300(2023)(2029)[21]
Bruce1PHWRCANDU 791Operational823Jun 19711 Sep 1977(2043)
2PHWRCANDU 791Operational823[22]Dec 19701 Sep 1977(2043)
3PHWRCANDU 750AOperational817Jul 19721 Feb 1978(2064)[23]
4PHWRCANDU 750AOperational817Sep 197218 Jan 1979(2064)
5PHWRCANDU 750BOperational817Jun 19781 Mar 1985(2064)
6PHWRCANDU 750BOperational880[24]Jan 197815 Sep 1984(2064)
7PHWRCANDU 750BOperational817May 197910 Apr 1986(2064)
8PHWRCANDU 750BOperational817Aug 197922 May 1987(2064)
NPD1PHWRCANDUShut down19Jan 19584 Jun 19621987
Douglas Point1PHWRCANDU 200Shut down200Feb 196026 Sep 19684 May 1984
Gentilly1BWRCANDU BLWR 250Shut down250Sep 19661 May 19721977
2PHWRCANDU-6Shut down635Apr 19741 Oct 198328 Dec 2012
Point Lepreau1PHWRCANDU-6Operational635May 19751 Feb 1983(2041)

China

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Bailong1PWRCAP-1000Planned1100
2PWRCAP-1000Planned1100
ChangjiangI-1PWRCNP-600Operational60125 Apr 201025 Dec 2015
I-2PWRCNP-600Operational60121 Nov 201020 Jun 2016
I-3[25]PWRHualong OneUnder construction120031 Mar 2021[26]
I-4[25]PWRHualong OneUnder construction120031 Mar 2021[26]
II-1PWRACP-100Under construction10013 Jul 2021
II-2PWRACP-100Planned100
Daya Bay1PWRM-310Operational9447 Aug 19871 Feb 1994
2PWRM-310Operational9447 Apr 19886 May 1994
Fangchenggang1PWRCPR-1000Operational100030 Jul 201025 Oct 2015
2PWRCPR-1000Operational100023 Dec 201015 Jul 2016
3PWRHualong OneOperational100024 Dec 201525 Mar 2023
4PWRHualong OneUnder construction100024 Dec 2016(2024)
5PWRHualong OnePlanned1117
6PWRHualong OnePlanned1117
Fangjiashan1PWRCPR-1000Operational101226 Dec 200815 Dec 2014
2PWRCPR-1000Operational101217 Jul 200912 Feb 2015
Fuqing1PWRCPR-1000Operational100021 Nov 200819 Nov 2014
2PWRCPR-1000Operational100017 Jun 200915 Oct 2015
3PWRCPR-1000Operational100031 Dec 20107 Sep 2016
4PWRCPR-1000Operational100017 Nov 201231 Jul 2017
5PWRHualong OneOperational100015 Apr 201530 Jan 2021[27]
6PWRHualong OneOperational100022 Dec 201525 Mar 2022[28]
Haiyang1PWRAP1000Operational117024 Sep 200923 Oct 2018[29]
2PWRAP1000Operational117020 Jun 20109 Jan 2019[30]
3PWRCAP-1000Under construction11007 Jul 2022[31]
4PWRCAP-1000Under construction110022 Apr 2023[32]
Haixing[33]1PWRCAP-1000Planned1100
2PWRCAP-1000Planned1100
Hongyanhe1PWRCPR-1000Operational106118 Aug 20076 Jun 2013
2PWRCPR-1000Operational106128 Mar 200813 May 2014
3PWRCPR-1000Operational10617 Mar 200923 Mar 2015
4PWRCPR-1000Operational106115 Aug 20091 Apr 2016
5PWRACPR-1000Operational106129 Mar 20152 Aug 2021[34]
6PWRACPR-1000Operational106124 Jul 201523 Jun 2022
Lianjiang[35]1PWRCAP-1000Under construction110027 Sep 2023
2PWRCAP-1000Planned1100
Ling Ao1PWRM-310Operational95015 May 199728 May 2002
2PWRM-310Operational95028 Nov 19978 Jan 2003
3PWRCPR-1000Operational100715 Dec 200515 Sep 2010
4PWRCPR-1000Operational100715 Jun 20067 Aug 2011
Lufeng1PWRCAP-1000Planned1100
2PWRCAP-1000Planned1100
3PWRCAP-1000Planned1100
4PWRCAP-1000Planned1100
5PWRHualong OneUnder construction10008 Sep 2022[36]
6PWRHualong OneUnder construction100026 Aug 2023[37]
Ningde1PWRCPR-1000Operational101818 Feb 200815 Apr 2013
2PWRCPR-1000Operational101812 Nov 20084 May 2014
3PWRCPR-1000Operational10188 Jan 201010 Jun 2015
4PWRCPR-1000Operational101829 Sep 201029 Mar 2016
5PWRHualong OnePlanned1080
6PWRHualong OnePlanned1080
Pengze1PWRCAP-1000Planned1100
2PWRCAP-1000Planned1100
QinshanI-1PWRCNP-300Operational30820 Mar 19851 Apr 1994
II-1PWRCNP-600Operational6102 Jun 199615 Apr 2002
II-2PWRCNP-600Operational6101 Apr 19973 May 2004
II-3PWRCNP-600Operational61928 Apr 20065 Oct 2010
II-4PWRCNP-600Operational61928 Jan 200730 Dec 2011
III-1PHWRCANDU-6Operational6778 Jun 199831 Dec 2002
III-2PHWRCANDU-6Operational67725 Sep 199824 Jul 2003
San'ao[38] 1PWRHualong OneUnder construction111731 Dec 2020
2PWRHualong OneUnder construction100030 Dec 2021[39]
Sanmen1PWRAP1000Operational115719 Apr 200921 Sep 2018[40]
2PWRAP1000Operational115715 Dec 20095 Nov 2018[41]
3PWRCAP-1000Under construction116328 Jun 2022[42]
4PWRCAP-1000Under construction110022 Mar 2023[43]
ShidaowanI-1HTGRHTR-PMOperational2009 Dec 20126 Dec 2023[44]
II-1PWRCAP-1400Under construction150019 Jun 2019(2025)
II-2PWRCAP-1400Under construction150021 Apr 2020(2025)
Taipingling1PWRHualong OneUnder construction111626 Dec 2019
2PWRHualong OneUnder construction111615 Oct 2020[45]
Taishan1PWREPROperational166018 Nov 200914 Dec 2018[46]
2PWREPROperational166015 Apr 20107 Sep 2019[47]
3PWREPRPlanned1660
4PWREPRPlanned1660
Taohuajiang1PWRCAP-1000Planned1100
2PWRCAP-1000Planned1100
3PWRCAP-1000Planned1100
4PWRCAP-1000Planned1100
Tianwan1PWRVVER-1000/V-428Operational99020 Oct 199917 May 2007
2PWRVVER-1000/V-428Operational99020 Sep 200016 Aug 2007
3PWRVVER-1000/V-428MOperational104527 Dec 201214 Feb 2018
4PWRVVER-1000/V-428MOperational104527 Sep 201322 Dec 2018[48]
5PWRACPR-1000Operational100027 Dec 20158 Sep 2020[49]
6PWRACPR-1000Operational10007 Sep 20163 Jun 2021[50]
7PWRVVER-1200/V-491Under construction115019 May 2021(2027–2028)
8PWRVVER-1200/V-491Under construction115025 Feb 2022[51](2027–2028)
Xianning1PWRCAP-1000Planned1100
2PWRCAP-1000Planned1100
Xiapu[52]I-1SFRCFR-600Under construction64229 Dec 2017(2023)[53]
I-2SFRCFR-600Under construction[53]64227 Dec 2020[53]
II-1PWRCAP-1000Planned1100
II-2PWRCAP-1000Planned1100
II-3PWRCAP-1000Planned1100
II-4PWRCAP-1000Planned1100
Xudabao1PWRCAP-1000Under construction125015 Nov 2023 [54]
2PWRCAP-1000Planned1100
3PWRVVER-1200/V-491Under construction115028 Jul 2021[55](2027)
4PWRVVER-1200/V-491Under construction115019 May 2022[56](2028)
Yangjiang1PWRCPR-1000Operational100016 Dec 200825 Mar 2014
2PWRCPR-1000Operational10004 Jun 20098 Jun 2015
3PWRCPR-1000+Operational100015 Nov 20101 Jan 2016
4PWRCPR-1000+Operational100017 Nov 201215 Mar 2017
5PWRACPR-1000Operational100018 Sep 201312 Jul 2018[57]
6PWRACPR-1000Operational100023 Dec 201324 Jul 2019
Zhangzhou1PWRHualong OneUnder construction112616 Oct 2019[58]
2PWRHualong OneUnder construction11264 Sep 2020[45]
3PWRHualong OnePlanned1000
4PWRHualong OnePlanned1000

Cuba

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Juragua1PWRVVER-440/V-318Unfinished44019835 Sep 1992
2PWRVVER-440/V-318Unfinished44019855 Sep 1992

Czech Republic

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Dukovany1PWRVVER-440/V-213Operational4681 Jan 19793 May 1985
2PWRVVER-440/V-213Operational4711 Jan 197921 Mar 1986
3PWRVVER-440/V-213Operational4681 Mar 197920 Dec 1986
4PWRVVER-440/V-213Operational4711 Mar 197919 Jul 1987
5PWRTBDPlanned1200
Temelín1PWRVVER-1000/V-320Operational10031 Feb 198710 Jun 2002
2PWRVVER-1000/V-320Operational10031 Feb 198718 Apr 2003

Egypt

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
El Dabaa1PWRVVER-1200/V-529Under construction120020 Jul 2022[59](2028)
2PWRVVER-1200/V-529Under construction120019 Nov 2022[60]
3PWRVVER-1200/V-529Under construction12003 May 2023[61]
4PWRVVER-1200/V-529Planned1200

Finland

Plant
name
Unit
No.
Type Model Status Capacity
(MW)[62]
Begin
building
Commercial
operation
Closed
Hanhikivi1PWRVVER-1200/V-491Cancelled1200(2023)(2029)2 May 2022[63][64]
Loviisa1PWRVVER-440/V-213Operational5071 May 19719 May 1977
2PWRVVER-440/V-213Operational5071 Aug 19725 Jan 1981
Olkiluoto1BWRASEA-III, BWR-2500Operational8901 Feb 197410 Oct 1979
2BWRASEA-III, BWR-2500Operational8901 Nov 197510 Jul 1982[65]
3PWREPROperational160012 Aug 200516 Apr 2023[66]

France

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Belleville1PWRP4 REP 1300Operational13101 May 19801 Jun 1988
2PWRP4 REP 1300Operational13101 Aug 19801 Jan 1989
Blayais1PWRCP1Operational9101 Jan 19771 Dec 1981
2PWRCP1Operational9101 Jan 19771 Feb 1983
3PWRCP1Operational9101 Apr 197814 Nov 1983
4PWRCP1Operational9101 Apr 19781 Oct 1983
Brennilis1HWGCRShut down/in decommissioning701 Jul 19621 Jun 196831 Jul 1985
Bugey1GCRUNGGShut down5401 Dec 19651 Jul 197227 May 1994
2PWRCP0Operational9101 Nov 19721 Mar 1979
3PWRCP0Operational9101 Sep 19731 Mar 1979
4PWRCP0Operational8801 Jun 19741 Jul 1979
5PWRCP0Operational8801 Jul 19743 Jan 1980
6PWREPR2Planned1670
7PWREPR2Planned1670
Cattenom1PWRP4 REP 1300Operational130029 Oct 19791 Apr 1987
2PWRP4 REP 1300Operational130028 Jul 19801 Feb 1988
3PWRP4 REP 1300Operational130015 Jun 19821 Feb 1991
4PWRP4 REP 1300Operational130028 Sep 19831 Jan 1992
ChinonA-1GCRUNGGShut down701 Feb 19571 Feb 196416 Apr 1973
A-2GCRUNGGShut down1801 Aug 195924 Feb 196514 Jun 1985
A-3GCRUNGGShut down3601 Mar 19614 Aug 196615 Jun 1990
B-1PWRCP2Operational9051 Mar 19771 Feb 1984
B-2PWRCP2Operational9051 Mar 19771 Aug 1984
B-3PWRCP2Operational9051 Oct 19804 Mar 1987
B-4PWRCP2Operational9051 Feb 19811 Apr 1988
ChoozA-1PWRCHOOZ-ADecommissioned3051 Jan 196215 Apr 196730 Oct 1991
B-1PWRN4 REP 1450Operational15001 Jan 198415 May 2000
B-2PWRN4 REP 1450Operational15001 Jan 198415 May 2000
Civaux1PWRN4 REP 1450Operational149515 Oct 198829 Jan 2002
2PWRN4 REP 1450Operational14951 Apr 199123 Apr 2002
Cruas1PWRCP2Operational9151 Aug 19782 Apr 1984
2PWRCP2Operational91515 Nov 19781 Apr 1985
3PWRCP2Operational91515 Apr 197910 Sep 1984
4PWRCP2Operational9151 Oct 197911 Feb 1985
Dampierre1PWRCP1Operational8901 Feb 197510 Sep 1980
2PWRCP1Operational8901 Apr 197516 Feb 1981
3PWRCP1Operational8901 Sep 197527 May 1981
4PWRCP1Operational8901 Dec 197520 Nov 1981
Fessenheim1PWRCP0Shut down8801 Sep 19711 Jan 197822 Feb 2020
2PWRCP0Shut down8801 Feb 19721 Apr 197829 Jun 2020
Flamanville1PWRP4 REP 1300Operational13301 Dec 19791 Dec 1986
2PWRP4 REP 1300Operational13301 May 19809 Mar 1987
3PWREPRUnder construction16003 Dec 2007(2024)[67]
Golfech1PWRP4 REP 1300Operational131017 Nov 19821 Feb 1991
2PWRP4 REP 1300Operational13101 Oct 19844 Mar 1994
Gravelines1PWRCP1Operational9101 Feb 197525 Nov 1980
2PWRCP1Operational9101 Mar 19751 Dec 1980
3PWRCP1Operational9101 Dec 19751 Jun 1981
4PWRCP1Operational9101 Apr 19761 Oct 1981
5PWRCP1Operational9101 Oct 197915 Jan 1985
6PWRCP1Operational9101 Oct 197925 Oct 1985
7PWREPR2Planned1670
8PWREPR2Planned1670
Nogent1PWRP4 REP 1300Operational131026 May 198124 Feb 1988
2PWRP4 REP 1300Operational13101 Jan 19821 May 1989
Paluel1PWRP4 REP 1300Operational133015 Aug 19771 Dec 1985
2PWRP4 REP 1300Operational13301 Jan 19781 Dec 1985
3PWRP4 REP 1300Operational13301 Feb 19791 Feb 1986
4PWRP4 REP 1300Operational13301 Feb 19801 Jun 1986
Penly1PWRP4 REP 1300Operational13301 Sep 19821 Dec 1990
2PWRP4 REP 1300Operational13301 Aug 19841 Nov 1992
3PWREPR2Planned1670(2024)
4PWREPR2Planned1670(2024)[68]
Phénix1FBRPH-250Shut down1301 Nov 196814 Jul 19741 Feb 2010
Saint-Alban1PWRP4 REP 1300Operational133529 Jan 19791 May 1986
2PWRP4 REP 1300Operational133531 Jul 19791 Mar 1987
Saint-LaurentA-1GCRUNGGShut down3901 Oct 19631 Jun 196918 Apr 1990
A-2GCRUNGGShut down4651 Jan 19661 Nov 197127 May 1992
B-1PWRCP2Operational9151 May 19761 Aug 1983
B-2PWRCP2Operational9151 Jul 19761 Aug 1983
Superphénix1FBRNa-1200Shut down/in decommissioning120013 Dec 19761 Dec 198631 Dec 1998
Tricastin1PWRCP1Operational9151 Nov 19741 Dec 1980
2PWRCP1Operational9151 Dec 19741 Dec 1980
3PWRCP1Operational9151 Apr 197511 May 1981
4PWRCP1Operational9151 May 19751 Nov 1981

Germany

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
AVR1HTGRPBR PrototypeShut down131 Aug 196119 May 196931 Dec 1988
Biblis1PWRSiemens-KWUShut down/in decommissioning11671 Jan 197026 Feb 19756 Aug 2011
2PWRKWUShut down/in decommissioning12401 Feb 197231 Jan 19776 Aug 2011
Brokdorf1PWRKWUShut down14101 Jan 197622 Dec 198631 Dec 2021
Brunsbüttel1BWRBWR-69Shut down77115 Apr 19709 Feb 19776 Aug 2011
Emsland1PWRKonvoi (KWU)Shut down132910 Aug 198220 Jun 198815 Apr 2023
Grafenrheinfeld1PWRKWUShut down12751 Jan 197517 Jun 198227 Jun 2015
Greifswald1PWRVVER-440/V-230Shut down/in decommissioning4081 Mar 197012 Jul 197414 Feb 1990
2PWRVVER-440/V-230Shut down/in decommissioning4081 Mar 197016 Apr 197514 Feb 1990
3PWRVVER-440/V-230Shut down/in decommissioning4081 Apr 19721 May 197828 Feb 1990
4PWRVVER-440/V-230Shut down/in decommissioning4081 Apr 19721 Nov 197922 Jul 1990
5PWRVVER-440/V-213Shut down/in decommissioning4081 Dec 19761 Nov 198924 Nov 1989
6PWRVVER-440/V-213Finished; never entered service408
Grohnde1PWRKWUShut down13601 Jun 19761 Feb 198531 Dec 2021[69]
Grosswelzheim1BWRBWRDismantled251 Jan 19652 Aug 197020 Apr 1971
GundremmingenABWRGE, BWR-1Shut down/in decommissioning23712 Dec 196212 Apr 196713 Jan 1977
BBWRBWR-72 (KWU)Shut down128420 Jul 197619 Jul 198431 Dec 2017[70]
CBWRBWR-72 (KWU)Shut down128820 Jul 197618 Jan 198531 Dec 2021[69]
Isar1BWRBWR-69Shut down/in decommissioning8781 May 197221 Mar 19796 Aug 2011
2PWRKonvoi (KWU)Shut down141015 Sep 19829 Apr 198815 Apr 2023
Kahl1BWRBWRDismantled151 Jul 19581 Feb 196225 Nov 1985
SNR-3001FBRFinished; never entered service19721985
KNK II1FBRShut down171 Sep 19743 Mar 197923 Aug 1991
Krümmel1BWRBWR-69 (KWU)Shut down13465 Apr 197428 Mar 19846 Aug 2011
Lingen1BWRBWRShut down1831 Oct 19641 Oct 19685 Jan 1977
Mülheim-Kärlich1PWRB & WShut down/in decommissioning121915 Jan 19758 Aug 19879 Sep 1988
MZFR1PHWRPHWRShut down521 Dec 196119 Dec 19663 May 1984
Neckarwestheim1PWRKWUShut down7851 Feb 19721 Dec 19766 Aug 2011
2PWRKonvoi (KWU)Shut down13109 Nov 198215 Apr 198915 Apr 2023
Niederaichbach1HWGCRPressure tube reactorShut down/decommissioned1001 Jun 19661 Jan 197331 Jul 1974
Obrigheim1PWRSiemensShut down/in decommissioning34015 Mar 196531 Mar 196911 May 2005
Philippsburg1BWRBWR-69Shut down8901 Oct 197026 Mar 19806 Aug 2011
2PWRKWUShut down14027 Jul 197718 Apr 198531 Dec 2019[71]
Rheinsberg1PWRVVER-70Shut down/in decommissioning621 Jan 196011 Oct 19661 Jun 1990
Stade1PWRSiemensShut down/in decommissioning6401 Dec 196719 May 19724 Nov 2003
Stendal1PWRVVER-1000/V-320Unfinished19831990
2PWRVVER-1000/V-320Unfinished19831990
3PWRVVER-1000/V-320Never built
4PWRVVER-1000/V-320Never built
THTR-3001HTGRPBRDecommissioned2963 May 19711 Jun 198729 Sep 1988
Unterweser1PWRKWUShut down/in decommissioning13451 Jul 19726 Sep 19796 Aug 2011
Würgassen1BWRBWR-69 (AEG)Shut down/in decommissioning64026 Jan 196811 Nov 197526 Aug 1994

Hungary

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Paks1PWRVVER-440/V-213Operational4701 Aug 197410 Aug 1983
2PWRVVER-440/V-213Operational4731 Aug 197414 Nov 1984
3PWRVVER-440/V-213Operational4731 Oct 19791 Dec 1986
4PWRVVER-440/V-213Operational4711 Oct 19791 Nov 1987
5PWRVVER-1200Planned1114(2024)
6PWRVVER-1200Planned1114(2024)

India

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Chutka[72]1PHWRIPHWR-700Planned630
2PHWRIPHWR-700Planned630
Gorakhpur1PHWRIPHWR-700Planned630
2PHWRIPHWR-700Planned630
3PHWRIPHWR-700Planned630
4PHWRIPHWR-700Planned630
Jaitapur1PWREPRPlanned1600
2PWREPRPlanned1600
3PWREPRPlanned1600
4PWREPRPlanned1600
5PWREPRPlanned1600
6PWREPRPlanned1600
Kaiga1PHWRIPHWR-220[73]Operational2021 Sep 198916 Nov 2000
2PHWRIPHWR-220[73]Operational2021 Dec 198916 Mar 2000
3PHWRIPHWR-220[73]Operational20230 Mar 20026 May 2007
4PHWRIPHWR-220[73]Operational20210 May 200220 Jan 2011
5PHWRIPHWR-700Planned630
6PHWRIPHWR-700Planned630
Kakrapar1PHWRIPHWR-220[73]Operational2021 Dec 19846 May 1993
2PHWRIPHWR-220[73]Operational2021 Apr 19851 Sep 1995
3PHWRIPHWR-700[74]Operational63022 Nov 201030 Jun 2023
4PHWRIPHWR-700[74]Under construction63022 Nov 2010
Kudankulam1PWRVVER-1000/V-412Operational93231 Mar 200231 Dec 2014
2PWRVVER-1000/V-412Operational9324 Jul 200231 Mar 2017
3PWRVVER-1000/V-412Under construction91730 Jun 2017
4PWRVVER-1000/V-412Under construction91723 Oct 2017
5PWRVVER-1000/V-412Under construction91729 Jun 2021
6PWRVVER-1000/V-412Under construction91720 Dec 2021[75]
Madras1PHWRIPHWR-220[73]Operational2051 Jan 197127 Jan 1984
2PHWRIPHWR-220[73]Operational2051 Oct 197221 Mar 1986
Mahi Banswara1PHWRIPHWR-700Planned630
2PHWRIPHWR-700Planned630
3PHWRIPHWR-700Planned630
4PHWRIPHWR-700Planned630
Narora1PHWRIPHWR-220[73]Operational2021 Dec 19761 Jan 1991
2PHWRIPHWR-220[73]Operational2021 Nov 19771 Jul 1992
PFBR1FBRPrototypeUnder construction47023 Oct 2004
Rajasthan1PHWRCANDU[73]Shut down901 Aug 196516 Dec 19739 Oct 2004[76]
2PHWRCANDU[73]Operational1871 Apr 19681 Apr 1981
3PHWRIPHWR-220[73]Operational2021 Feb 19901 Jun 2000
4PHWRIPHWR-220[73]Operational2021 Oct 199023 Dec 2000
5PHWRIPHWR-220[73]Operational20218 Sep 20024 Feb 2010
6PHWRIPHWR-220[73]Operational20220 Jan 200331 Mar 2010
7PHWRIPHWR-700[74]Under construction63018 Jul 2011
8PHWRIPHWR-700[74]Under construction63030 Sep 2011
Tarapur1BWRBWR-1, Mark 1Operational1501 Oct 196428 Oct 1969
2BWRBWR-1, Mark 1Operational1501 Oct 196428 Oct 1969
3PHWRIPHWR-540Operational49012 May 200018 Aug 2006
4PHWRIPHWR-540Operational4908 Mar 200012 Sep 2005

Iran

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Bushehr1PWRVVER-1000/V-446Operational9151 May 197523 Sep 2013
2PWRVVER-1000/V-528Under construction91527 Sep 2019
3PWRVVER-1000Planned915
Darkhovin1PWRUnfinished; restart planned360

Italy

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Caorso1BWRBWR-4 Mark2Shut down/in decommissioning8601 Jan 19701 Dec 19811 Jul 1990
Enrico Fermi1PWRWH 4-loopShut down/in decommissioning2601 Jul 19611 Jan 19651 Jul 1990
Garigliano1BWRBWR-1Shut down/in decommissioning1501 Nov 19591 Jun 19641 Mar 1982
Latina1GCRMagnoxShut down/in decommissioning1531 Nov 19581 Jan 19641 Dec 1987
Alto Lazio1BWRUnfinished9821 Jul 19821 Jan 1988
2BWRUnfinished9821 Jul 19821 Jul 1988
Trino 21PWRUnfinished95023 Dec 1987
2PWRUnfinished95023 Dec 1987

Japan

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Fugen1HWLWRATRShut down14810 May 197220 Mar 197929 Mar 2003
Fukushima Daiichi1BWRBWR-3Inoperable43925 Jul 196726 Mar 197119 May 2011
2BWRBWR-4Inoperable7609 Jun 196918 Jul 197419 May 2011
3BWRBWR-4Inoperable76028 Dec 197027 Mar 197619 May 2011
4BWRBWR-4Inoperable76012 Feb 197312 Oct 197819 May 2011
5BWRBWR-4Shut down76022 May 197218 Apr 197817 Dec 2013
6BWRBWR-5Shut down106726 Oct 197324 Oct 197917 Dec 2013
Fukushima Daini1BWRBWR-5Shut down106716 Mar 197620 Apr 198230 Sep 2019
2BWRBWR-5Shut down106725 May 19793 Feb 198430 Sep 2019
3BWRBWR-5Shut down106723 Mar 198121 Jun 198530 Sep 2019
4BWRBWR-5Shut down106728 May 198125 Aug 198730 Sep 2019
Genkai1PWRMitsubishi (2-loop)Shut down52915 Sep 197115 Oct 197527 Apr 2015
2PWRMitsubishi (2-loop)Shut down5291 Feb 197730 Mar 19819 Apr 2019
3PWRMitsubishi (4-loop)Operational11271 Jun 198818 Mar 1994
4PWRMitsubishi (4-loop)Operational[77]112715 Jul 199225 Jul 1997
Hamaoka1BWRBWR-4Shut down51510 Jun 197117 Mar 197630 Jan 2009
2BWRBWR-4Shut down80614 Jun 197429 Nov 197830 Jan 2009
3BWRBWR-5Operation suspended
(under review)[78]
105618 Apr 198328 Aug 1987
4BWRBWR-5Operation suspended
(under review)[78]
109213 Oct 19893 Sep 1993
5BWRABWROperation suspended132512 Jul 200018 Jan 2005
Higashidōri (Tōhoku)1BWRBWR-5Operation suspended
(under review)[78]
10677 Nov 20008 Dec 2005
Higashidōri (Tokyo)1BWR ABWRUnfinished; restart planned135025 Jan 2011[79]
Ikata1PWRMitsubishi (2-loop)Shut down5381 Sep 197330 Sep 197725 Mar 2016
2PWRMitsubishi (2-loop)Shut down5381 Aug 197819 Mar 198227 Mar 2018
3PWRMitsubishi (3-loop)Operational8461 Oct 199015 Dec 1994
Kashiwazaki-Kariwa1BWRBWR-5Operation suspended10675 Jun 198018 Sep 1985
2BWRBWR-5Operation suspended106718 Nov 198528 Sep 1990
3BWRBWR-5Operation suspended10677 Mar 198911 Aug 1993
4BWRBWR-5Operation suspended10675 Mar 199011 Aug 1994
5BWRBWR-5Operation suspended106720 Jun 198510 Apr 1990
6BWRABWROperation suspended
(restart approved)[80]
13153 Nov 19927 Nov 1996
7BWRABWROperation suspended
(restart approved)[80]
13151 Jul 19932 Jul 1997
Mihama1PWRMitsubishi (2-loop)Shut down3201 Feb 196728 Nov 1970Mar 2015
2PWRMitsubishi (2-loop)Shut down47029 May 196825 Jul 1972Mar 2015
3PWRMitsubishi (3-loop)Operational[81]7807 Aug 19721 Dec 1976
Monju1FBRShut down24610 May 198629 Aug 19955 Dec 2017
Ōi1PWRW (4-loop)Shut down112026 Oct 197227 Mar 1979Dec 2017
2PWRWestinghouse (4-loop)Shut down11208 Dec 19725 Dec 1979Dec 2017
3PWRMitsubishi (4-loop)Operational11273 Oct 198718 Dec 1991
4PWRMitsubishi (4-loop)Operational[82]112713 Jun 19882 Feb 1993
Ōma1BWRABWRUnder construction13257 May 2010
Onagawa1BWRBWR-4Shut down4988 Jul 19801 Jun 198421 Dec 2018
2BWRBWR-5Operation suspended
(restart approved)[83]
79612 Apr 199128 Jul 1995
3BWRBWR-5Operation suspended79623 Jan 199830 Jan 2002
Sendai1PWRMitsubishi (3-loop)Operational84615 Dec 19794 Jul 1984
2PWRMitsubishi (3-loop)Operational84612 Oct 198128 Nov 1985
Shika1BWRBWR-5Operation suspended5051 Jul 198930 Jul 1993
2BWRABWROperation suspended
(under review)[78]
110820 Aug 200115 Mar 2006
Shimane1BWRBWR-3Shut down4392 Jul 197029 Mar 1974Mar 2015
2BWRBWR-5Operation suspended
(restart approved)[84]
7892 Feb 198510 Feb 1989
3BWRABWRUnder construction132512 Oct 2007
Takahama1PWRMitsubishi (3-loop)Operational[85]78025 Apr 197014 Nov 1974
2PWRMitsubishi (3-loop)Operational[86]7809 Mar 197114 Nov 1975
3PWRMitsubishi (3-loop)Operational83012 Dec 198017 Jan 1985
4PWRMitsubishi (3-loop)Operational83019 Mar 19815 Jun 1985
Tōkai1GCRMagnoxShut down1371 Mar 196125 Jul 196631 Mar 1998
2BWRBWR-5Operation suspended
(restart approved)[87]
10603 Oct 197328 Nov 1978
Tomari1PWRMitsubishi (2-loop)Operation suspended
(under review)[78]
55018 Apr 198522 Jun 1989
2PWRMitsubishi (2-loop)Operation suspended
(under review)[78]
55013 Jun 198512 Apr 1991
3PWRMitsubishi (3-loop)Operation suspended
(under review)[78]
86618 Nov 200422 Dec 2009
Tsuruga1BWRBWR-2Shut down34024 Nov 196614 Mar 1970Mar 2015
2PWRMitsubishi (4-loop)Operation suspended
(under review)[78]
11086 Nov 198217 Feb 1987

Kazakhstan

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Aktau1FBRBN-350Shut down/in decommissioning3501 Oct 196416 Jul 197322 Apr 1999

Lithuania

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Ignalina1LWGRRBMK-1500Shut down/in decommissioning11851 May 197731 Dec 198331 Dec 2004
2LWGRRBMK-1500Shut down/in decommissioning11851 Jan 1978Aug 198731 Dec 2009
3LWGRRBMK-1500Unfinished1185
4LWGRRBMK-1500Never built1185

Mexico

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Laguna Verde1BWRBWR-5Operational7771 Oct 197628 Jul 1990
2BWRBWR-5Operational7751 Jun 197710 Apr 1995

Netherlands

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Borssele1PWRKWU 2LPOperational4821 Jul 196926 Oct 1973(2033)
Dodewaard1BWRBWR-2Shut down551 May 196526 Mar 196926 Mar 1997

North Korea

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Yongbyon1GCRMagnox (Pu-production)Shut down51994
2LWR[88]Planned[88]30
Taechon1Unfinished2001994
Kumho1PWRUnfinished10002003
2PWRUnfinished10002003

Pakistan

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Chashma1PWRCNP-300Operational3001 Aug 199315 Sep 2000
2PWRCNP-300Operational30028 Dec 200518 May 2011
3PWRCNP-300Operational31528 May 20116 Dec 2016
4PWRCNP-300Operational31318 Dec 201119 Sep 2017
5PWRHualong OnePlanned1080
Karachi1PHWRCANDU-137 MWShut down901 Aug 19667 Dec 19721 Aug 2021
2PWRHualong OneOperational101423 May 201319 Mar 2021[89]
3PWRHualong OneOperational101431 May 201618 Apr 2022

Philippines

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Bataan1PWRWestinghouseUnfinished; restart planned[90]62119761986

Poland

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Żarnowiec1PWRVVER-440Unfinished44031 Mar 19824 Sep 1990
2PWRVVER-440Unfinished44031 Mar 19824 Sep 1990
Choczewo[91]1PWRAP1000Planned1250[92](2026)(2033)[91]
2PWRAP1000Planned1250(2035–2036)[91]
3PWRAP1000Planned1250(2037–2039)[91]
Pątnów[93]1PWRAPR-1400Planned1340
2PWRAPR-1400Planned1340
Włocławek1BWRBWRX-300Planned300(2030)[94]
Ostrołęka1BWRBWRX-300Planned300(2030)[94]
Warsaw1BWRBWRX-300Planned300(2030)[94]
Tarnobrzeg/Stalowa Wola1BWRBWRX-300Planned300(2030)[94]
Dąbrowa Górnicza1BWRBWRX-300Planned300(2030)[94]
Stawy Monowskie1BWRBWRX-300Planned300(2030)[94]
Kraków1BWRBWRX-300Planned300(2030)[94]

Romania

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Cernavodă1PHWRCANDU-6Operational65031 Mar 19832 Dec 1996
2PHWRCANDU-6Operational6501 Jul 19831 Nov 2007
3PHWRCANDU-6Unfinished; restart planned650
4PHWRCANDU-6Unfinished; restart planned650
5PHWRCANDU-6Unfinished650

Russia

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Akademik Lomonosov1PWRKLT-40SOperational3215 Apr 200719 Dec 2019[95]
2PWRKLT-40SOperational3215 Apr 200719 Dec 2019
Balakovo1PWRVVER-1000/V-320Operational9501 Dec 198023 May 1986
2PWRVVER-1000/V-320Operational9501 Aug 198118 Jan 1988
3PWRVVER-1000/V-320Operational9501 Nov 19828 Apr 1989
4PWRVVER-1000/V-320Operational9501 Apr 198422 Dec 1993
Beloyarsk1LWGRAMB-100Shut down1021 Jun 195826 Apr 19641 Jan 1983
2LWGRAMB-200Shut down1461 Jan 19621 Dec 19691 Jan 1990
3SFRBN-600Operational5601 Jan 19691 Nov 1981
4SFRBN-800Operational78918 Jul 200610 Dec 2015
5SFRBN-1200Planned1100
Bilibino1LWGREGP-6Shut down111 Jan 19701 Apr 197414 Jan 2019
2LWGREGP-6Operational111 Jan 19701 Feb 1975
3LWGREGP-6Operational111 Jan 19701 Feb 1976
4LWGREGP-6Operational111 Jan 19701 Jan 1977
Kalinin1PWRVVER-1000/V-338Operational9501 Feb 197712 Jun 1985
2PWRVVER-1000/V-338Operational9501 Feb 19823 Mar 1987
3PWRVVER-1000/V-320Operational9501 Oct 19858 Nov 2005
4PWRVVER-1000/V-320Operational9501 Aug 198625 Dec 2012
Kaliningrad1PWRVVER-1200/V-491Under construction
(suspended)[96]
110922 Feb 2012
2PWRVVER-1200/V-491Planned1109
Kola1PWRVVER-440/V-230Operational4411 May 197028 Dec 1973
2PWRVVER-440/V-230Operational4411 May 197021 Feb 1975
3PWRVVER-440/V-213Operational4411 Apr 19773 Dec 1982
4PWRVVER-440/V-213Operational4411 Aug 19766 Dec 1984
Kola II[96][97]1PWRVVER-S-600Planned600(2028)(2034)
2PWRVVER-S-600Planned600(2028)(2034)
Kostroma1PWRVVER-1200Unfinished; restart planned13001979
2PWRVVER-1200Unfinished; restart planned13001979
3PWRVVER-1200Unfinished; restart planned13001979
4PWRVVER-1200Unfinished; restart planned13001979
Kursk1LWGRRBMK-1000Shut down9251 Jun 197212 Oct 197719 Dec 2021
2LWGRRBMK-1000Operational9251 Jan 197317 Aug 1979
3LWGRRBMK-1000Operational9251 Apr 197830 Mar 1984
4LWGRRBMK-1000Operational9251 May 19815 Feb 1986
Kursk II1PWRVVER-TOI/V-510Under construction111529 Apr 2018
2PWRVVER-TOI/V-510Under construction111515 Apr 2019[98]
3PWRVVER-TOIPlanned1115
4PWRVVER-TOIPlanned1115
Leningrad1LWGRRBMK-1000Shut down9251 Mar 19701 Nov 197421 Dec 2018[99]
2LWGRRBMK-1000Shut down9251 Jun 197011 Feb 197610 Nov 2020
3LWGRRBMK-1000Operational9251 Dec 197329 Jun 1980
4LWGRRBMK-1000Operational9251 Feb 197529 Aug 1981
Leningrad II[100]1PWRVVER-1200/V-491Operational108525 Oct 200829 Oct 2018
2PWRVVER-1200/V-491Operational108515 Apr 201022 Mar 2021
3PWRVVER-1200Planned1085(2024)[101](2030)
4PWRVVER-1200Planned1085(2025)(2032)
MPEB No. 1[102][103][104] 1PWRRITM-200SUnder construction5330 Aug 2022[105](2027)
2PWRRITM-200SUnder construction5330 Aug 2022[105](2027)
MPEB No. 2 1PWRRITM-200SPlanned53(2022)(2027)
2PWRRITM-200SPlanned53(2022)(2027)
MPEB No. 31PWRRITM-200SPlanned53(2022)(2028)
2PWRRITM-200SPlanned53(2022)(2028)
MPEB No. 4 1PWRRITM-200SPlanned53(2022)(2031)
2PWRRITM-200SPlanned53(2022)(2031)
Nizhny Novgorod1PWRVVER-1200Planned1300
2PWRVVER-1200Planned1300
3PWRVVER-1200Planned1300
4PWRVVER-1200Planned1300
Novovoronezh1PWRVVER/V-210Shut down1971 Jul 195731 Dec 196416 Feb 1988
2PWRVVER/V-365Shut down3361 Jun 196414 Apr 197029 Aug 1990
3PWRVVER-440/V-179Shut down3851 Jul 196729 Jun 197225 Dec 2016
4PWRVVER 440/V-179Operational3851 Jul 196724 Mar 1973
5PWRVVER-1000/V-187Operational9501 Mar 197420 Feb 1981
Novovoronezh II1PWRVVER-1200/V-392MOperational111424 Jun 200827 Feb 2017
2PWRVVER-1200/V-392MOperational111412 Jul 20096 Nov 2019
3PWRVVER-1200Planned1175
4PWRVVER-1200Planned1175
Obninsk1LWGRAM-1Shut down51 Jan 19511 Dec 195429 Apr 2002
Rostov1PWRVVER-1000/V-320Operational9501 Sep 198125 Dec 2001
2PWRVVER-1000/V-320Operational9501 May 198310 Dec 2010
3PWRVVER-1000/V-320Operational95015 Sep 200927 Dec 2014
4PWRVVER-1000/V-320Operational101116 Jun 201028 Sep 2018
Sakha1PWRRITM-200NPlanned55(2024)[106](2028)
Seversk1FBRBREST-300Under construction2808 Jun 2021[107](2026)
South Urals1FBRBN-1200Unfinished; restart planned11001982
2FBRBN-1200Unfinished; restart planned11001982
3FBRBN-1200Unfinished; restart planned11001982
Smolensk1LWGRRBMK-1000Operational9251 Oct 197530 Sep 1983
2LWGRRBMK-1000Operational9251 Jun 19762 Jul 1985
3LWGRRBMK-1000Operational9251 May 198412 Oct 1990
Smolensk II[108][109]1PWRVVER-TOIPlanned1300
2PWRVVER-TOIPlanned1300
Tatar1PWRVVER-1200Unfinished; restart planned13001980
2PWRVVER-1200Unfinished; restart planned13001980

Slovakia

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
BohuniceA-1[110]HWGCRKS 150Decommissioned931 Aug 195825 Dec 197222 Feb 1977
1[111]PWRVVER-440/V-230Shut down40824 Apr 19721 Apr 198031 Dec 2006
2PWRVVER-440/V-230Shut down40824 Apr 19721 Jan 198131 Dec 2008
3PWRVVER-440/V-213Operational4721 Dec 197614 Feb 1985(2045)
4PWRVVER-440/V-213Operational4711 Dec 197618 Dec 1985(2045)
Mochovce1PWRVVER-440 V-213Operational43613 Oct 198329 Oct 1998(2058)
2PWRVVER-440/V-213Operational43613 Oct 198311 Apr 2000(2060)
3PWRVVER-440/V-213Operational44027 Jan 198717 Oct 2023[112]
4PWRVVER-440/V-213Under construction44027 Jan 1987

Slovenia

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Krško1PWRWH 2 loopsOperational68830 Mar 19751 Jan 1983(2043)[113]
2PWRTBDPlanned1100(2030)[114]

South Africa

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Koeberg1PWRCP1 (France)Operational9301 Jul 197621 Jul 1984
2PWRCP1 (France)Operational9301 Jul 19769 Nov 1985

South Korea

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Hanbit1PWRWH FOperational9604 Jun 198125 Aug 1986
2PWRWH FOperational95810 Dec 198110 Jun 1987
3PWROPR-1000Operational99723 Dec 198931 Mar 1995
4PWROPR-1000Operational99726 May 19901 Jan 1996
5PWROPR-1000Operational99729 Jun 199721 May 2002
6PWROPR-1000Operational99520 Nov 199724 Dec 2002
Hanul1PWRCP1 (France)Operational96026 Jan 198310 Sep 1988
2PWRCP1 (France)Operational9625 Jul 198330 Sep 1989
3PWROPR-1000Operational99421 Jul 199311 Aug 1998
4PWROPR-1000Operational9981 Nov 199331 Dec 1999
5PWROPR-1000Operational9961 Oct 199929 Jul 2004
6PWROPR-1000Operational99629 Sep 200022 Apr 2005
Shin-Hanul1PWRAPR-1400Operational141410 Jul 20127 Dec 2022[115]
2PWRAPR-1400Under construction140019 Jul 2012
3PWRAPR-1400Planned[116]1340
4PWRAPR-1400Planned[116]1340
Kori1PWRWH 60Shut down57627 Apr 197229 Apr 197818 Jun 2017
2PWRWH FOperational6404 Dec 197725 Jul 1983
3PWRWH FOperational10111 Oct 197930 Sep 1985
4PWRWH FOperational10121 Apr 198029 Apr 1986
Shin-Kori1PWROPR-1000Operational99616 Jun 200628 Feb 2011
2PWROPR-1000Operational9965 Jun 200720 Jul 2012
Saeul1PWRAPR-1400Operational141616 Oct 200815 Jan 2016
2PWRAPR-1400Operational141819 Aug 200929 Aug 2019[117]
3PWRAPR-1400Under construction14001 Apr 2017
4PWRAPR-1400Under construction140020 Sep 2018
Wolsong1PHWRCANDU-6Shut down65730 Oct 197722 Apr 198324 Dec 2019
2PHWRCANDU-6Operational65522 Jun 19921 Jul 1997
3PHWRCANDU-6Operational68417 Mar 19941 Jul 1998
4PHWRCANDU-6Operational68822 Jul 19941 Oct 1999
Shin-Wolsong1PWROPR-1000Operational99120 Nov 200731 Jul 2012
2PWROPR-1000Operational96023 Sep 200826 Feb 2015

Spain

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Almaraz1PWRWH 3 loopsOperational10113 Jul 19731 Sep 1983
2PWRWH 3 loopsOperational10063 Jul 19731 Jul 1984
Ascó1PWRWH 3 loopsOperational99516 May 197410 Dec 1984
2PWRWH-3 loopsOperational9977 Mar 197531 Mar 1986
Cofrentes1BWRBWR-6Operational10649 Sep 197511 Mar 1985
José Cabrera1PWRWH 1 loopShut down/in decommissioning14124 Jun 196413 Aug 196930 Apr 2006
Lemoniz1PWRUnfinished19721984
2PWRUnfinished19721984
Santa María de Garoña1BWRBWR-3Shut down/in decommissioning44611 May 197115 Feb 19756 Jul 2013
Trillo1PWRKWU 3 loopsOperational100317 Aug 19796 Aug 1988
Valdecaballeros1BWRUnfinished19751984
2BWRUnfinished19751984
Vandellòs1GCRShut down/in decommissioning48019672 Aug 197231 Jul 1990
2PWRWH 3 loopsOperational104529 Dec 19808 Mar 1988

Sweden

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Ågesta1PHWRR3Shut down/in decommissioning101 Dec 19571 May 19642 Jun 1974[lower-alpha 1]
Barsebäck1BWRASEA-IIShut down/in decommissioning6001 Feb 19711 Jul 197530 Nov 1999[lower-alpha 2]
2BWRASEA-IIShut down/in decommissioning6001 Jan 19731 Jul 197731 May 2005[lower-alpha 3]
Forsmark1BWRASEA-III, BWR-2500Operational9861 Jun 197310 Dec 1980[lower-alpha 4]
2BWRASEA-III, BWR-2500Operational11161 Jan 19757 Jul 1981[lower-alpha 5]
3BWRASEA-IV, BWR-3000Operational11671 Jan 197918 Aug 1985[lower-alpha 6]
Oskarshamn1BWRASEA-IShut down/in decommissioning4731 Aug 19666 Feb 197219 Jun 2017[lower-alpha 7]
2BWRASEA-IIShut down/in decommissioning6381 Sep 19691 Jan 197522 Dec 2016[lower-alpha 8]
3BWRASEA-IV, BWR-3000Operational14501 May 198015 Aug 1985[lower-alpha 9]
Marviken1BHWRR4Unfinished1961 Apr 196527 May 1970[lower-alpha 10]
Ringhals1BWRASEA-IShut down/in decommissioning8811 Feb 19691 Jan 197631 Dec 2020[lower-alpha 11]
2PWRWH 3-loopsShut down/in decommissioning9041 Oct 19701 May 197530 Dec 2019[lower-alpha 12]
3PWRWH 3-loopsOperational10621 Sep 19729 Sep 1981[lower-alpha 13]
4PWRWH 3-loopsOperational11041 Nov 197321 Nov 1983[lower-alpha 14]

Switzerland

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed[123]
Beznau1PWRWH 2-loopsOperational3651 Sep 19651 Sep 1969(2029)
2PWRWH 2-loopsOperational3651 Jan 19681 Dec 1971(2031)
Gösgen1PWRKWU 3-loopsOperational10101 Dec 19731 Nov 1979
Leibstadt1BWRBWR-6Operational12201 Jan 197415 Dec 1984
Lucens1HWGCRHWGCRDecommissioned61 Apr 196229 Dec 196621 Jan 1969
Mühleberg1BWRBWR-4Shut down/in decommissioning3731 Mar 19676 Nov 197220 Dec 2019

Taiwan

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Jinshan1BWRBWR-4Shut down/in decommissioning6362 Jun 197210 Dec 19783 Oct 2018
2BWRBWR-4Shut down/in decommissioning6367 Dec 197315 Jul 19793 Oct 2018
Kuosheng1BWRBWR-6Shut down98519 Nov 197528 Dec 19811 Jul 2021[124]
2BWRBWR-6Shut down98515 Mar 197616 Mar 198315 Mar 2023
Lungmen1BWRABWRUnfinished135031 Mar 19992014
2BWRABWRUnfinished135030 Aug 19992014
Maanshan1PWRWH 312 3-loopOperational95121 Aug 197827 Jul 1984
2PWRWH 312 3-loopOperational95121 Feb 197918 May 1985

Turkey

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Akkuyu1PWRVVER-1200/V-509Under construction11143 Apr 2018(2025)[125]
2PWRVVER-1200/V-509Under construction11148 Apr 2020(2026)
3PWRVVER-1200/V-509Under construction111410 Mar 2021(2027)
4PWRVVER-1200/V-509Under construction111421 Jul 2022[126](2028)
Sinop[127][128]1PWRAtmea-1Cancelled1100
2PWRAtmea-1Cancelled1100
3PWRAtmea-1Cancelled1100
4PWRAtmea-1Cancelled1100

Ukraine

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Chernobyl1LWGRRBMK-1000Shut down/in decommissioning7401 Mar 197027 May 197830 Nov 1996
2LWGRRBMK-1000Shut down/in decommissioning9251 Feb 197328 May 197911 Oct 1991
3LWGRRBMK-1000Shut down/in decommissioning9251 Mar 19768 Jun 198215 Dec 2000
4LWGRRBMK-1000Destroyed9251 Apr 197926 Mar 198426 Apr 1986
5LWGRRBMK-1000Unfinished925
6LWGRRBMK-1000Unfinished925
Chyhyryn[129]1PWRAP1000Planned1100
2PWRAP1000Planned1100
Crimean1PWRVVER-1000Unfinished95026 Jan 19841987
2PWRVVER-1000Unfinished95026 Jan 19841987
Kharkiv1PWRVVER-1000Unfinished90019881990
2PWRVVER-1000Unfinished90019881990
Khmelnytskyi1PWRVVER-1000/V-320Operational9501 Nov 198113 Aug 1988
2PWRVVER-1000/V-320Operational9501 Feb 198515 Dec 2005
3PWRVVER-1000Under construction9501 Sep 1985(2026)[130]
4PWRVVER-1000Under construction9501 Jun 1986(2026)
5PWRAP1000Planned[131]1100
6PWRAP1000Planned[132]1100
Odesa1PWRVVER-1000Unfinished9001989
2PWRVVER-1000Unfinished9001989
Rivne1PWRVVER-440/V-213Operational3811 Aug 197322 Sep 1981
2PWRVVER-440/V-213Operational3761 Oct 197329 Jul 1982
3PWRVVER-1000/V-320Operational9501 Feb 198016 May 1987
4PWRVVER-1000/V-320Operational9501 Aug 19866 Apr 2006
5PWRAP1000Planned[132]1100
South Ukraine1PWRVVER-1000/V-302Operational9501 Aug 19762 Dec 1983
2PWRVVER-1000/V-338Operational9501 Jul 19816 Apr 1985
3PWRVVER-1000/V-320Operational9501 Nov 198429 Dec 1989
4PWRAP1000Planned[132]1100
Zaporizhzhia1PWRVVER-1000/V-320Operational9501 Apr 198025 Dec 1985
2PWRVVER-1000/V-320Operational9501 Jan 198115 Feb 1986
3PWRVVER-1000/V-320Operational9501 Apr 19825 Mar 1987
4PWRVVER-1000/V-320Operational9501 Apr 198314 Apr 1988
5PWRVVER-1000/V-320Operational9501 Nov 198527 Oct 1989
6PWRVVER-1000/V-320Operational9501 Jun 198617 Sep 1996

United Arab Emirates

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Barakah1PWRAPR-1400Operational134519 Jul 20126 Apr 2021[133]
2PWRAPR-1400Operational134516 Apr 201324 Mar 2022[134]
3PWRAPR-1400Operational134524 Sep 201424 Feb 2023[135]
4PWRAPR-1400Under construction134530 Jul 2015(2024)

United Kingdom

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Berkeley1GCRMagnoxDecommissioned1381 Jan 195712 Jun 196231 Mar 1989
2GCRMagnoxDecommissioned1381 Jan 195720 Oct 196226 Oct 1988
Bradwell1GCRMagnoxDecommissioned1231 Jan 19571 Jul 196231 Mar 2002
2GCRMagnoxDecommissioned1231 Jan 195712 Nov 196230 Mar 2002
Bradwell B1PWRHualong OnePlanned1117
2PWRHualong OnePlanned1117
Calder Hall1GCRMagnoxShut down/in decommissioning491 Aug 19531 Oct 195631 Mar 2003
2GCRMagnoxShut down/in decommissioning491 Aug 19531 Feb 195731 Mar 2003
3GCRMagnoxShut down/in decommissioning491 Aug 19551 May 195831 Mar 2003
4GCRMagnoxShut down/in decommissioning491 Aug 19551 Apr 195931 Mar 2003
Chapelcross1GCRMagnoxShut down/in decommissioning481 Oct 19551 Mar 195929 Jun 2004
2GCRMagnoxShut down/in decommissioning481 Oct 19551 Aug 195929 Jun 2004
3GCRMagnoxShut down/in decommissioning481 Oct 19551 Dec 195929 Jun 2004
4GCRMagnoxShut down/in decommissioning481 Oct 19551 Mar 196029 Jun 2004
Dounreay1SFRDFRShut down/in decommissioning111 Mar 19551 Oct 19621 Mar 1977
2SFRPFRShut down/in decommissioning2341 Jan 19661 Jul 197631 Mar 1994
Dungeness AA-1GCRMagnoxShut down/in decommissioning2251 Jul 196028 Oct 196531 Dec 2006
A-2GCRMagnoxShut down/in decommissioning2251 Jul 196030 Dec 196531 Dec 2006
Dungeness BB-1GCRAGRShut down5201 Oct 19651 Apr 19857 Jun 2021
B-2GCRAGRShut down5201 Oct 19651 Apr 19897 Jun 2021
Hartlepool1GCRAGROperational5951 Oct 19681 Apr 1989(2026)
2GCRAGROperational5851 Oct 19681 Apr 1989(2026)
HeyshamA-1GCRAGROperational5851 Dec 19701 Apr 1989(2026)
A-2GCRAGROperational5751 Dec 19701 Apr 1989(2026)
B-1GCRAGROperational6101 Aug 19801 Apr 1989(2028)[136]
B-2GCRAGROperational6101 Aug 19801 Apr 1989(2028)[136]
Hinkley Point A1GCRMagnoxShut down/in decommissioning2351 Nov 195730 Mar 196523 May 2000
2GCRMagnoxShut down/in decommissioning2351 Nov 19575 May 196523 May 2000
Hinkley Point B1GCRAGRShut down/in decommissioning4351 Sep 19672 Oct 19781 Aug 2022[137]
2GCRAGRShut down/in decommissioning4351 Sep 196727 Sep 19766 Jul 2022[138]
Hinkley Point C1PWREPRUnder construction160011 Dec 2018(2027)[16]
2PWREPRUnder construction160012 Dec 2019(2028)[16]
Hunterston A1GCRMagnoxShut down/in decommissioning1501 Oct 19575 Feb 196430 Mar 1990
2GCRMagnoxShut down/in decommissioning1501 Oct 19571 Jul 196431 Dec 1989
Hunterston B1GCRAGRShut down4601 Nov 19676 Feb 197626 Nov 2021
2GCRAGRShut down4601 Nov 196731 Mar 19777 Jan 2022[139]
Moorside1PWREPRPlanned1600
2PWREPRPlanned1600
Oldbury1GCRMagnoxShut down/in decommissioning2171 May 196231 Dec 196729 Feb 2012
2GCRMagnoxShut down/in decommissioning2171 May 196230 Sep 196830 Jun 2011
Sizewell A1GCRMagnoxShut down/in decommissioning2101 Apr 196125 Mar 196631 Dec 2006
2GCRMagnoxShut down/in decommissioning2101 Apr 196115 Sep 196631 Dec 2006
Sizewell B1PWRWH SNUPPSOperational119118 Jul 198822 Sep 1995(2035)
Sizewell C1PWREPRPlanned1600(2024)[140]
2PWREPRPlanned1600
Torness1GCRAGROperational5951 Aug 198025 May 1988(2028)[136]
2GCRAGROperational5951 Aug 19803 Feb 1989(2028)[136]
Trawsfynydd1GCRMagnoxShut down/in decommissioning1951 Jul 195924 Mar 19656 Feb 1991
2GCRMagnoxShut down/in decommissioning1951 Jul 195924 Mar 19654 Feb 1991
Winfrith[141]1SGHWRSGHWRShut down/in decommissioning921 May 19631 Jan 196811 Sep 1990
Wylfa1GCRMagnoxShut down/in decommissioning4901 Sep 19631 Nov 197130 Dec 2015
2GCRMagnoxShut down/in decommissioning4901 Sep 19633 Jan 197225 Apr 2012

United States

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Arkansas Nuclear One1PWRB & W (DRY-Cont)Operational8361 Oct 196821 May 1974
2PWRCE (DRY)Operational9886 Dec 19681 Sep 1978
Beaver Valley1PWRWH 3-loop (DRY)Operational90826 Jun 19702 Jul 1976
2PWRWH 3-loop (DRY)Operational9053 May 197414 Aug 1987
Big Rock Point[142]1BWRBWR-1Dismantled671 May 196029 Mar 196329 Aug 1997
Braidwood1[143]PWRWH 4-loop (DRY)Operational11941 Aug 197529 Jul 1988
2[144]PWRWH 4-loop (DRY)Operational11601 Aug 197517 Oct 1988
Browns Ferry1BWRBWR-4 (WET)Operational12001 May 19671 Aug 1974
2BWRBWR-4 (WET)Operational12001 May 19671 Mar 1975
3BWRBWR-4 (WET)Operational12101 Jul 19681 Mar 1977
Brunswick1BWRBWR-4 (WET)Operational9387 Feb 197018 Mar 1977[145]
2BWRBWR-4 (WET)Operational9327 Feb 19703 Nov 1975[146]
Byron1PWRWH 4-loop (DRY)Operational11641 Apr 197516 Sep 1985
2PWRWH 4-loop (DRY)Operational11361 Apr 19752 Aug 1987
Callaway1PWRWH 4-loop (DRY)Operational12151 Sep 197519 Dec 1984
Calvert Cliffs1PWRCE 2-loop (DRY)Operational8771 Jun 19688 May 1977
2PWRCE 2-loop (DRY)Operational8551 Jun 19681 Apr 1977
Carbon Free Power Project[147][148]1PWRNuScaleCancelled77
2PWRNuScaleCancelled77
3PWRNuScaleCancelled77
4PWRNuScaleCancelled77
5PWRNuScaleCancelled77
6PWRNuScaleCancelled77
Catawba1PWRWH 4-loop (ICECOND)Operational11601 May 197429 Jun 1985
2PWRWH 4-loop (ICECOND)Operational11501 May 197419 Aug 1986
Clinch River1BWRBWRX-300Planned180
Clinton1BWRBWR-6 (WET)Operational10621 Oct 197524 Nov 1987
Columbia1BWRBWR-5 (WET)Operational11311 Aug 197213 Dec 1984
Comanche Peak1PWRWH 4-loop (DRY)Operational120519 Dec 197413 Aug 1990
2PWRWH 4-loop (DRY)Operational119519 Dec 19743 Aug 1993
Connecticut Yankee1PWRWH (DRY)Dismantled5821 May 19641 Jan 19685 Dec 1996
Cooper1BWRBWR-4 (WET)Operational7691 Jun 19681 Jul 1974
Crystal River 31PWRB & W (DRY)Shut down/in decommissioning86025 Sep 196813 Mar 19775 Feb 2013
Davis-Besse1PWRB & W (DRY)Operational8941 Sep 197031 Jul 1978
Diablo Canyon1PWRWH 4-Loop (DRY)Operational113823 Apr 19687 May 1985
2PWRWH 4-Loop (DRY)Operational11189 Dec 197013 Mar 1986
Donald C. Cook1PWRWH 4-Loop (ICECOND)Operational102025 Mar 196927 Aug 1975
2PWRWH 4-Loop (ICECOND)Operational109025 Mar 19691 Jul 1978
Dresden1BWRBWR-1Shut down1971 May 19564 Jul 196031 Oct 1978
2BWRBWR-3 (WET)Operational89410 Jan 19669 Jun 1970
3BWRBWR-3 (WET)Operational87914 Oct 196616 Nov 1971
Duane Arnold1BWRBWR-4 (WET)Shut down60122 May 19701 Feb 197510 Aug 2020
Edwin I. Hatch1BWRBWR-4 (WET)Operational92430 Sep 196831 Dec 1975
2BWRBWR-4 (WET)Operational9241 Feb 19725 Sep 1979
Elk River1BWRDismantled221 Jan 19591 Jul 19641 Feb 1968
Fermi1FBRPrototypeShut down618 Aug 19567 Aug 196629 Nov 1972
2BWRBWR-4 (WET)Operational111526 Sep 197223 Jan 1988
Fort Calhoun1PWRCE 2-loop (WET)Shut down4827 Jun 1968 9 Aug 197324 Oct 2016
Fort St. Vrain1HTGRGeneral AtomicsShut down3301 Sep 19681 Jul 197929 Aug 1989
Ginna1PWRWH 2-loop (DRY)Operational56025 Apr 19661 Jun 1970
Grand Gulf1BWRBWR-6 (WET)Operational14014 May 19741 Jul 1985
H. B. Robinson1PWRWH 3-loop (DRY)Operational73513 Apr 19677 Mar 1971
Hallam1SGRAtomics InternationalDismantled751 Jan 19591 Nov 19631 Sep 1969
HartsvilleA1[149]BWRBWR-6Unfinished128523 May 1975[150]29 Aug 1984[150]
A2[149]BWRBWR-6Unfinished128523 May 1975[150]29 Aug 1984[150]
B1[149]BWRBWR-6Unfinished128523 May 1975[150]22 Mar 1983[150]
B2[149]BWRBWR-6Unfinished128523 May 1975[150]22 Mar 1983[150]
Hope Creek1BWRBWR-4 (WET)Operational11721 Mar 197620 Dec 1986
Humboldt Bay1BWRBWR-1Dismantled631 Nov 19601 Aug 19632 Jul 1976
Indian Point1PWRShut down2571 May 19561 Oct 196231 Oct 1974
2PWRWH 4-loop (DRY)Shut down99814 Oct 19661 Aug 197430 Apr 2020[151]
3PWRWH 4-loop (DRY)Shut down10301 Nov 196830 Aug 197630 Apr 2021[151]
James A. FitzPatrick1BWRBWR-4 (WET)Operational8131 Sep 196828 Jul 1975
Joseph M. Farley1PWRWH 3-Loop (DRY)Operational8741 Oct 19701 Dec 1977
2PWRWH 3-Loop (DRY)Operational8831 Oct 197030 Jul 1981
Kemmerer1SFRNatriumPlanned345
Kewaunee1PWRWH 2-loop (DRY)Shut down5666 Aug 196816 Jun 19747 May 2013
La Crosse1BWRBWR-1Dismantled481 Mar 19637 Nov 196930 Apr 1987
LaSalle County1BWRBWR-5 (WET)Operational113710 Sep 19731 Jan 1984
2BWRBWR-5 (WET)Operational114010 Sep 197319 Oct 1984
Limerick1BWRBWR-5 (WET)Operational113419 Jun 19741 Feb 1986
2BWRBWR-5 (WET)Operational113419 Jun 19748 Jan 1990
Maine Yankee1PWRWH (DRY)Dismantled8601 Oct 196828 Dec 19721 Aug 1997
Marble Hill1PWRWH (DRY)Unfinished11301 Aug 197710 Jan 1984
McGuire1PWRWH 4-Loop (ICECOND)Operational11581 Apr 19711 Dec 1981
2PWRWH 4-Loop (ICECOND)Operational11581 Apr 19711 Mar 1984
Millstone1BWRBWR-3 (WET)Shut down6411 May 196628 Dec 197021 Jul 1998
2PWRCE 2-loop (DRY)Operational8691 Nov 196926 Dec 1975
3PWRWH 4-Loop (DRY)Operational12109 Aug 197423 Apr 1986
Monticello1BWRBWR-3 (WET)Operational62819 Jun 196730 Jun 1971
Nine Mile Point1BWRBWR-2 (WET)Operational61312 Apr 19651 Dec 1969
2BWRBWR-5 (WET)Operational12771 Aug 197511 Mar 1988
North Anna1PWRWH 3-Loop (DRY)Operational94819 Feb 19716 Jun 1978
2PWRWH 3-Loop (DRY)Operational94419 Feb 197114 Dec 1980
Oconee1PWRB & W (DRY)Operational8476 Nov 196715 Jul 1973
2PWRB & W (DRY)Operational8486 Nov 19679 Sep 1974
3PWRB & W (DRY)Operational8596 Nov 196716 Dec 1974
Oyster Creek1BWRBWR-2 (WET)Shut down61915 Dec 196423 Dec 196917 Sep 2018
Palisades1PWRCE 2-loop (DRY)Shut down80514 Mar 196731 Dec 197120 May 2022
Palo Verde1PWRCE80 2-loop (DRY)Operational131125 May 197628 Jan 1986
2PWRCE80 2-loop (DRY)Operational13141 Jun 197619 Sep 1986
3PWRCE80 2-loop (DRY)Operational13121 Jun 19768 Jan 1988
Parr1PHWRCVTRDismantled171 Jan 196018 Dec 196310 Jan 1967
Pathfinder1BWRBWR-1Dismantled591 Jan 19591 Aug 19661 Oct 1967
Peach Bottom1GCRPrototypeShut down401 Feb 19621 Jun 19661 Nov 1974
2BWRBWR-4 (WET)Operational130031 Jan 19685 Jul 1974
3BWRBWR-4 (WET)Operational133131 Jan 196823 Dec 1974
Perry1BWRBWR-6 (WET)Operational12401 Oct 197418 Nov 1987
Pilgrim1BWRBWR-3 (WET)Shut down67726 Aug 19689 Dec 197231 May 2019
Piqua1OCRAtomics InternationalDecommissioned121 Jan 19601 Nov 19631 Jan 1966
Point Beach1PWRWH 2-loop (DRY)Operational59119 Jul 196721 Dec 1970
2PWRWH 2-loop (DRY)Operational59125 Jul 19681 Oct 1972
Prairie Island1PWRWH 2-loop (DRY)Operational52225 Jun 196816 Dec 1973
2PWRWH 2-loop (DRY)Operational51925 Jun 196921 Dec 1974
Quad Cities1BWRBWR-4 (WET)Operational90815 Feb 196718 Feb 1973
2BWRBWR-4 (WET)Operational91115 Feb 196710 Mar 1973
Rancho Seco1PWRWH (DRY)Decommissioned8731 Apr 196917 Apr 197523 Jun 1989
River Bend1BWRBWR-6 (WET)Operational96725 Mar 197716 Jun 1986
Salem1PWRWH 4-loop (DRY)Operational116925 Sep 196830 Jun 1977
2PWRWH 4-loop (DRY)Operational115825 Sep 196831 Oct 1981
San Onofre1PWRWH (DRY)Dismantled43616 Jul 19641 Jan 196830 Nov 1992
2PWRCE (DRY)Shut down/in decommissioning10701 Mar 19748 Aug 19837 Jun 2013
3PWRCE (DRY)Shut down/in decommissioning11801 Mar 19741 Apr 19847 Jun 2013
Saxton1PWRDecommissioned31 Jan 1960Nov 1961May 1972
Seabrook Station1PWRWH 4-Loop (DRY)Operational12467 Jul 197615 Mar 1990
Sequoyah1PWRWH 4-Loop (ICECOND)Operational115227 May 19701 Jul 1981
2PWRWH 4-Loop (ICECOND)Operational113927 May 19701 Jun 1982
Shearon Harris1PWRWH 3-Loop (DRY)Operational96428 Jan 19782 May 1987
Shippingport1PWRWHDismantled606 Sep 195426 May 1958Dec 1989
Shoreham1BWRGEShut down8201 Nov 19721 Aug 19861 May 1989
SRE1FBRDecommissioned6.5195412 Jul 195715 Feb 1964
South Texas1PWRWH 4-loop (DRY)Operational128022 Dec 197525 Aug 1988
2PWRWH 4-loop (DRY)Operational128022 Dec 197519 Jun 1989
St. Lucie1PWRCE (DRY)Operational9811 Jul 19701 Mar 1976
2PWRCE (DRY)Operational9872 Jun 197710 Jun 1983
Surry1PWRWH 3-loop (DRY)Operational83825 Jun 196822 Dec 1972
2PWRWH 3-loop (DRY)Operational83825 Jun 19681 May 1973
Susquehanna1BWRBWR-5 (WET)Operational12572 Nov 197312 Nov 1982
2BWRBWR-5 (WET)Operational12572 Nov 197327 Jun 1984
Three Mile Island1PWRB & W (DRY)Shut down81918 May 19682 Sep 197420 Sep 2019
2PWRB & W (DRY)Core melt8801 Nov 196930 Dec 197828 Mar 1979
Trojan1PWRWH (DRY)Dismantled10951 Feb 197020 May 19769 Nov 1992
Turkey Point1PWRWH 3-loop (DRY)Operational83727 Apr 196714 Dec 1972
2PWRWH 3-loop (DRY)Operational82127 Apr 19677 Sep 1973
3PWRAP1000Planned1100
4PWRAP1000Planned1100
Vallecitos1BWRBWR-1Shut down251 Jan 195619 Oct 19579 Dec 1963
Vermont Yankee1BWRBWR-4 (WET)Shut down605[152]11 Dec 196730 Nov 197229 Dec 2014[153]
Virgil C. Summer1PWRWH 3-Loop (DRY)Operational100021 Mar 19731 Jan 1984
Vogtle1PWRWH 4-Loop (DRY)Operational11501 Aug 19761 Jun 1987
2PWRWH 4-Loop (DRY)Operational11521 Aug 197620 May 1989
3PWRAP1000Operational111712 Mar 201331 Jul 2023[154]
4PWRAP1000Under construction111719 Nov 2013(2024)[155]
Waterford1PWRCE 2-loop (DRY)Operational116814 Nov 197424 Sep 1985
Watts Bar1PWRWH 4-Loop (ICECOND)Operational115720 Jul 197327 May 1996
2PWRWH 4-Loop (ICECOND)Operational11641 Sep 19734 Jun 2016
Wolf Creek1PWRWH 4-Loop (DRY)Operational120031 May 19773 Sep 1985
Yankee Rowe1PWRWH (DRY)Dismantled1671 Nov 19571 Jul 19611 Oct 1991
Zion1PWRWH (DRY)Dismantled10401 Dec 196831 Dec 197313 Feb 1998
2PWRWH (DRY)Dismantled10401 Dec 196817 Sep 197413 Feb 1998

Uzbekistan

Plant
name
Unit
No.
Type Model Status Capacity
(MW)
Begin
building
Commercial
operation
Closed
Plant in the Jizzakh Region1PWRVVER-1200Planned1200
2PWRVVER-1200Planned1200

See also

Notes

  1. The full reactor model name is R3/Adam[118]
  2. The full reactor model name is ASEA-ATOM Gen II[119]
  3. The full reactor model name is ASEA-ATOM Gen II[119]
  4. The full reactor model name is ASEA-ATOM Gen III,[119] BWR-2500,[119] BWR 69[120]
  5. The full reactor model name is ASEA-ATOM Gen III,[119] BWR-2500,[119] BWR 69[120]
  6. The full reactor model name is ASEA-ATOM Gen IV,[119] BWR-3000,[119] BWR 75[120]
  7. The full reactor model name is ASEA-ATOM Gen I[119]
  8. The full reactor model name is ASEA-ATOM Gen II[119]
  9. The full reactor model name is ASEA-ATOM Gen IV,[119] BWR-3000,[119] BWR 75[121]
  10. The full reactor model name is R4/Eva. Construction date is approximate. Data are from Swedish Radiation Safety Authority.[118]
  11. The full reactor model name is ASEA-ATOM Gen I.[119] Closed at midnight on New Year's Eve.[122]
  12. The full reactor model name is Westinghouse 3-loops[119]
  13. The full reactor model name is Westinghouse 3-loops[119]
  14. The full reactor model name is Westinghouse 3-loops[119]

References

  1. "World Nuclear Power Reactors & Uranium Requirements". world-nuclear.org. World Nuclear Association. Retrieved 5 May 2020.
  2. "PRIS – Home". pris.iaea.org.
  3. Reference Unit Power at IAEA
  4. "Nuclear Power in Argentina | Argentinian Nuclear Energy – World Nuclear Association". world-nuclear.org. Retrieved 4 August 2019.
  5. "China inks $8 bln nuclear power plant deal in Argentina". Reuters. 2 February 2022. Retrieved 2 February 2022.
  6. Yulia Kosarenko. "NASA fact sheet". Archived from the original on 8 July 2007. Retrieved 20 August 2015.
  7. "BNamericas – The Embalse Nuclear Power Plant returns to s..." BNamericas.com.
  8. "Metsamor 2 to operate until 2026 : Corporate – World Nuclear News".
  9. "Nuclear Power in Bangladesh – World Nuclear Association". world-nuclear.org. Retrieved 17 July 2018.
  10. "Installation begins of outer dome at Rooppur 1". Retrieved 11 November 2022.
  11. "Росатом Госкорпорация "Росатом" ядерные технологии атомная энергетика АЭС ядерная медицина". rosatom.ru.
  12. "Second Belarus unit enters commercial operation". world-nuclear-news.org.
  13. "Doel 3: Shutdown confirmed for Friday". RTBF Info. 23 September 2022. Retrieved 25 September 2022.
  14. "RTBF Info of 21 Dec 2018". RTBF Info. 21 December 2018. Retrieved 28 December 2018.
  15. "Second Belgian reactor enters retirement : Corporate - World Nuclear News".
  16. 1 2 3 "Plans for New Nuclear Reactors Worldwide - World Nuclear Association".
  17. 1 2 3 "Bulgaria to push ahead with two new units at Kozloduy". world-nuclear-news.org. World Nuclear News. 25 October 2023. Retrieved 3 November 2023.
  18. "Utility abandons Pickering reactor overhaul". The Globe and Mail. 13 August 2005.
  19. "Ontario extends Pickering operations". World Nuclear News. 30 September 2022. Retrieved 7 July 2023.
  20. 1 2 Patel, Sonal (2 December 2021). "Darlington Nuclear Plant Will Get a BWRX-300 SMR as GE Hitachi Bags Lucrative OPG Selection". POWER Magazine. Retrieved 5 December 2021.
  21. "Additional SMRs in the pipeline for Darlington". World Nuclear News. 7 July 2023. Retrieved 7 July 2023.
  22. "Unit 2 sets record run ahead of planned maintenance outage". brucepower.com. 6 May 2022. Retrieved 7 July 2023.
  23. "Life-Extension Program & MCR Project". brucepower.com. Retrieved 7 July 2023.
  24. "Bruce 6 re-enters commercial operation : Corporate - World Nuclear News".
  25. 1 2 "China / Construction Begins of Two Hualong One Reactors at Changjiang". The Independent Global Nuclear News Agency. Retrieved 28 November 2019.
  26. 1 2 "我国自主三代核电华龙一号在海南正式开工建设". CNNC. Retrieved 2 April 2021.
  27. "China's first Hualong One nuclear reactor starts Opened". Reuters. 30 January 2021. Retrieved 30 January 2021.
  28. "Second Fuqing Hualong One enters Opened: New Nuclear – World Nuclear News".
  29. "Second AP1000 enters Opened". World Nuclear News. World Nuclear Association. Retrieved 24 October 2018.
  30. "Fourth Chinese AP1000 enters Opened". World Nuclear News. World Nuclear Association. Retrieved 13 January 2019.
  31. "Begin
    buildings on third Haiyang unit"
    . World Nuclear News. World Nuclear Association. Retrieved 25 July 2022.
  32. "Construction begins of fourth Haiyang unit". World Nuclear News. World Nuclear Association. Retrieved 26 April 2023.
  33. "China Nuclear Power | Chinese Nuclear Energy – World Nuclear Association". world-nuclear.org. Retrieved 16 July 2018.
  34. "Fifth Hongyanhe unit enters Opened". World Nuclear News. World Nuclear Association. Retrieved 2 August 2021.
  35. "China Nuclear Power | Chinese Nuclear Energy – World Nuclear Association". world-nuclear.org. Retrieved 15 June 2018.
  36. "Construction of Lufeng 5 gets under way". World Nuclear News. World Nuclear Association. Retrieved 9 September 2022.
  37. "Construction of Lufeng 6 begins". World Nuclear News. World Nuclear Association. Retrieved 29 August 2023.
  38. "Construction of new Chinese power plant begins: New Nuclear – World Nuclear News". world-nuclear-news.org. Retrieved 5 January 2021.
  39. "First concrete for unit 2 of China's San'ao nuclear power project- Nuclear Engineering International". Retrieved 4 January 2022.
  40. "First AP1000 reactor enters Opened". World Nuclear News. World Nuclear Association. Retrieved 24 October 2018.
  41. "Sanmen 2 AP1000 enters Opened – World Nuclear News". world-nuclear-news.org. Retrieved 7 November 2018.
  42. "PRIS – Reactor Details". pris.iaea.org. Retrieved 8 July 2022.
  43. "Begin
    buildings on fourth Sanmen unit"
    . world-nuclear-news.org. Retrieved 23 March 2023.
  44. "China's demonstration HTR-PM enters commercial operation : New Nuclear - World Nuclear News".
  45. 1 2 "China approves first new nuclear reactors in 3-plus years". Nikkei Asian Review. Retrieved 2 August 2019.
  46. "EDF : le premier des 2 EPR de la centrale de Taishan (Chine) entre en exploitation commerciale". Capital.fr (in French). 14 December 2018. Retrieved 14 December 2018.
  47. "World's second EPR starts operations". Retrieved 10 September 2019.
  48. "Fourth Tianwan unit enters Opened". World Nuclear News. World Nuclear Association. Retrieved 27 December 2018.
  49. "Fifth Tianwan unit starts Opened". World Nuclear News. World Nuclear Association. Retrieved 9 September 2020.
  50. "Tianwan 6 enters commercial operation : New Nuclear - World Nuclear News".
  51. "Begin
    buildings on eighth Tianwan unit: New Nuclear – World Nuclear News"
    .
  52. "Fast nuclear reactor to start construction in Fujian in 2017". 16 August 2015. Archived from the original on 17 August 2015. Retrieved 16 August 2015.
  53. 1 2 3 "China starts building second CFR-600 fast reactor : New Nuclear – World Nuclear News". world-nuclear-news.org. Retrieved 30 December 2020.
  54. "Work on Xudabao unit 1 gets under way". world-nuclear-news.org. Retrieved 17 November 2023.
  55. "Дан старт сооружению новых блоков российского дизайна атомных станций "Тяньвань" и "Сюйдапу" (Китай)". ruscable.ru.
  56. "Construction of Xudapu 4 under way: New Nuclear – World Nuclear News".
  57. "Yangjiang 5 enters Opened". world-nuclear-news.org. Retrieved 16 July 2018.
  58. "Begin
    buildings on first Zhangzhou unit – World Nuclear News"
    . world-nuclear-news.org. Retrieved 18 October 2019.
  59. "Construction of Egypt's first nuclear power plant under way : New Nuclear – World Nuclear News".
  60. "PRIS – Reactor Details".
  61. "Construction begins of third unit at Egypt's el Dabaa nuclear power plant : New Nuclear - World Nuclear News".
  62. "Nuclear power plants in Finland". STUK. 6 April 2021. Retrieved 13 May 2022.
  63. "Fennovoima cancels Hanhikivi 1 contract with Russia". World Nuclear Association. 3 May 2022.
  64. "Fennovoima terminates contract for Hanhikivi 1 NPP construction". TASS. 2 May 2022.
  65. "PRIS – Reactor Details".
  66. "Faulty seals replaced in Olkiluoto EPR : Regulation & Safety - World Nuclear News".
  67. "Further delay to Flamanville EPR start up". World Nuclear News.
  68. "EDF begins permitting process for two new reactors at Penly : New Nuclear - World Nuclear News". world-nuclear-news.org. Retrieved 9 December 2023.
  69. 1 2 "Germany shuts three of its last six nuclear plants". Retrieved 1 January 2022.
  70. "German reactor permanently shut down". world-nuclear-news.org. Retrieved 10 May 2018.
  71. "Germany shuts down Philippsburg 2". energycentral.com. Retrieved 8 January 2020.
  72. "Indian Nuclear Power Program". Archived from the original on 1 July 2012.
  73. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 "Status report 74 – Indian 220 MWe PHWR (IPHWR-220)" (PDF).
  74. 1 2 3 4 "Status report 105 – Indian 700 MWe PHWR (IPHWR-700)" (PDF).
  75. "В Индии началось сооружение блока № 6 АЭС "Куданкулам"". ase-ec.ru (in Russian). Retrieved 21 December 2021.
  76. "PRIS – Reactor Details".
  77. "Genkai unit 4 supplying power again". world-nuclear-news.org. Retrieved 22 June 2018.
  78. 1 2 3 4 5 6 7 8 "Licensing status for the Japanese nuclear facilities – Japan Nuclear Safety Institute". genanshin.jp. Retrieved 3 October 2021.
  79. "東通原子力発電所1号機の着工について". Tokyo Electric Power Company Holdings, Inc. Retrieved 27 June 2023.
  80. 1 2 "Nuclear Power Plants in Japan – The Federation of Electric Power Companies of Japan(FEPC)". fepc.or.jp. Retrieved 8 May 2018.
  81. "40年超の美浜原発3号機が再稼働 原発事故後 全国初". NHK. Retrieved 23 June 2021.
  82. "Ohi No.4 reactor restarted- News – NHK WORLD – English". NHK WORLD. Archived from the original on 10 May 2018. Retrieved 10 May 2018.
  83. "Japan clears restart at nuclear reactor closest to epicenter of 2011 quake – Reuters". Reuters. Retrieved 27 November 2019.
  84. "First Japanese BWR cleared for restart : Regulation & Safety – World Nuclear News".
  85. "運転開始40年超高浜原発1号機 約12年ぶりに再稼働". Retrieved 28 July 2023.
  86. "Takahama 2 reactor restarted". Retrieved 15 September 2023.
  87. "Japan approves extension for reactor similar to Fukushima units that melted down – Reuters". Reuters. Retrieved 29 December 2019.
  88. 1 2 "North Korea's Yongbyon Nuclear Facility: Slow Progress at the Experimental Light Water Reactor". 38 North. U.S.-Korea Institute, Johns Hopkins University School of Advanced International Studies. 14 January 2016. Archived from the original on 9 April 2016. Retrieved 4 April 2016.
  89. "PRIS - Reactor Details".
  90. "Philippines relaunches nuclear energy programme : Nuclear Policies". World Nuclear News. 3 March 2022. Retrieved 29 April 2022.
  91. 1 2 3 4 "Poland's Westinghouse choice 'deepens strategic relationship' with USA". 31 October 2022.
  92. "Poland's government confirms Westinghouse for nuclear plant". 4 November 2022.
  93. "South Korea's KHNP signs letter of intent on Polish nuclear". 31 October 2022.
  94. 1 2 3 4 5 6 7 "Taki reaktor chcą zbudować Orlen i Synthos". 18 April 2023.
  95. "Rosatom State Atomic Energy Cooperation | ROSATOM's first of a kind floating power unit connects to isolated electricity grid in Pevek, Russia's Far East". rosatom.ru. Retrieved 1 January 2020.
  96. 1 2 "Nuclear Power in Russia | Russian Nuclear Energy – World Nuclear Association". world-nuclear.org. Retrieved 14 May 2018.
  97. "Кольскую АЭС-2 начнут строить в 2028 году". Retrieved 9 December 2023.
  98. "The construction of the 2nd innovative VVER-TOI power block at the Kursk NPP-2 site has started ahead of schedule". rosenergoatom.ru. Retrieved 16 April 2019.
  99. "Russia retires Leningrad unit 1". World Nuclear News. World Nuclear Association. Retrieved 27 December 2018.
  100. "Four New NPP Units Will be Built in Russia".
  101. "Росатом планирует начать строительство второй очереди ЛАЭС-2 в 2024 году". tass.ru. Retrieved 11 July 2022.
  102. "Russia commits to further floating NPPs : New Nuclear – World Nuclear News". world-nuclear-news.org. Retrieved 28 July 2021.
  103. ""Росатом" и Kaz Minerals предварительно договорились о поставках электроэнергии для Баимского ГОКа". Interfax.ru (in Russian). Retrieved 3 September 2021.
  104. "Russia plans new generation of FNPPS – Nuclear Engineering International".
  105. 1 2 "Заложен корпус первого плавучего энергоблока в арктическом исполнении на базе реакторов РИТМ-200 – Атомэнергомаш". aem-group.ru. Archived from the original on 30 August 2022. Retrieved 30 August 2022.
  106. "В Якутии собираются строить АЭС мощностью не менее 55 МВт".
  107. ""Росатом" начал строительство реактора Брест-300 в Северске". 8 June 2021.
  108. "Russia prepares to build new nuclear reactors at Leningrad and Smolensk – Nuclear Engineering International".
  109. "VVER units planned for Leningrad and Smolensk".
  110. Shut down after a 1977 refuelling incident; decommission in progress since 1979
  111. "Tlačová agentúra Slovenskej republiky – TASR.sk". tasr.sk. Archived from the original on 20 January 2009.
  112. "Power commissioning of Mochovce 3 completed".
  113. "Krško gets an overhaul : Corporate – World Nuclear News".
  114. "Drugi blok NE Krško prve megavate mogao bi dati nakon 2030" [The second block of NPP Krško could provide the first megawatts after 2030.]. Točka na I (in Croatian). 30 November 2022. Retrieved 14 April 2023.
  115. "South Korean APR-1400 starts Opened : New Nuclear - World Nuclear News".
  116. 1 2 "Korea to resume construction of Shin Hanul 3&4".
  117. "Second APR-1400 unit starts Opened". world-nuclear-news.org. Retrieved 3 September 2019.
  118. 1 2 "Marvikenreaktorn - ett industripolitiskt utvecklingsprojekt i otakt med tiden". The Swedish Radiation Safety Authority (in Swedish). 31 March 2007. Retrieved 12 January 2023.
  119. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 "IAEA Sweden reactors". IAEA. 11 January 2023. Retrieved 12 January 2023.
  120. 1 2 3 "Forsmarks reaktorer i siffror" (PDF). Vattenfall (in Swedish). April 2016. Retrieved 12 January 2023.
  121. "MILSTOLPAR I VÅR HISTORIA". Westinghouse (in Swedish). Retrieved 12 January 2023.
  122. "Ringhals 1 inne på slutspurten". SVT (in Swedish). 26 October 2020. Retrieved 29 December 2020.
  123. admin.ch, The Federal Authorities, Federal Council decides to gradually phase out nuclear energy as part of its new energy strategy Archived 20 June 2013 at the Wayback Machine, 25 May 2011
  124. "Early shutdown for Taiwanese reactor : Corporate". World Nuclear News. 1 July 2021. Retrieved 29 April 2022.
  125. "Major components in place at Akkuyu 1 : New Nuclear". World Nuclear News. 4 March 2022. Retrieved 29 April 2022.
  126. "Construction begins of fourth Turkish reactor : New Nuclear – World Nuclear News".
  127. "Japan looks to cancel Turkish project – Nuclear Engineering International".
  128. "Turkey, Japan scrap partnership in Sinop nuclear plant in Turkey's north – Turkey News". 20 January 2020.
  129. "В Україні збудують нову атомну станцію: названо місто будівництва". GSMinfo. 22 September 2022. Retrieved 9 December 2023.
  130. "На Хмельницькій АЕС відбулася нарада з питань будівництва 3 та 4 енергоблоків". xaec.org.ua. 12 February 2021. Archived from the original on 24 February 2021. Retrieved 7 November 2022.
  131. "Ukraine planning for post-war nuclear power plants : New Nuclear – World Nuclear News".
  132. 1 2 3 "Is it sensible to invest in the construction of new nuclear reactors during post-war reconstruction? – Ecoclub Rivne is an environmental NGO".
  133. "UAE's first nuclear power plant begins Openeds". Reuters. 6 April 2021. Retrieved 6 April 2021.
  134. "Barakah / Unit 2 Begins Opened at Arab World's First Nuclear Station :: NucNet | the Independent Nuclear News Agency". 23 February 2022.
  135. "Third Barakah unit begins Opened : New Nuclear - World Nuclear News".
  136. 1 2 3 4 "Heysham 2 and Torness end dates brought forward by EDF : Corporate – World Nuclear News". world-nuclear-news.org. Retrieved 19 January 2022.
  137. "Hinkley Point B enters retirement : Corporate – World Nuclear News". world-nuclear-news.org. Retrieved 2 August 2022.
  138. "PRIS – Reactor Details". pris.iaea.org. Retrieved 25 July 2022.
  139. "Hunterston B nuclear power station retires after 46 years in service". The Guardian. 7 January 2022.
  140. "The Sizewell C project – National Infrastructure Planning". infrastructure.planninginspectorate.gov.uk. Retrieved 12 April 2022.
  141. "PRIS – Reactor Details". pris.iaea.org. Retrieved 24 January 2019.
  142. "PRIS – Reactor Details". iaea.org. Retrieved 11 May 2018.
  143. "PRIS – Reactor Details". iaea.org. Retrieved 11 May 2018.
  144. "PRIS – Reactor Details". iaea.org. Retrieved 11 May 2018.
  145. "Brunswick-1". IAEA. Retrieved 14 April 2013.
  146. "Brunswick-2". IAEA. Retrieved 14 April 2013.
  147. "Scaled down SMR pilot project remains on course : New Nuclear". World Nuclear News. 23 July 2021. Retrieved 29 April 2022.
  148. "Idaho SMR project terminated". World Nuclear News. 9 November 2023. Retrieved 9 November 2023.
  149. 1 2 3 4 "TVA Prepares to Write Final Nuclear Chapters". American Nuclear Society. 17 April 2015. Archived from the original on 29 July 2023. Retrieved 5 October 2023.
  150. 1 2 3 4 5 6 7 8 Tennessee Valley Authority. "Hartsville Nuclear Plant Site, Transfer of TVA Property For Industrial Park" (PDF). Archived from the original (PDF) on 5 January 2009. Retrieved 5 October 2023.
  151. 1 2 "Entergy's Indian Point Unit 2 to Shut Down Permanently". Indian Point Energy Center. 29 April 2020. Archived from the original on 3 August 2020. Retrieved 30 April 2020.
  152. "PRIS – Reactor Details".
  153. StarTribune.com, WILSON RING Vermont Yankee nuclear power plant ends operations after 42 years of producing electricity Archived 29 December 2014 at the Wayback Machine, 29 Dec 2014
  154. "Vogtle Unit 3 goes into operation". Cision. 31 July 2023. Retrieved 31 July 2023.
  155. "Further delay in startup of Vogtle AP1000s : New Nuclear". World Nuclear News. 18 February 2022. Retrieved 29 April 2022.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.