The wind resource potential in NSW is very good, yet this potential has remained largely untapped. The NSW Wind Atlas[1] shows that many of the sites with good potential for wind farms are situated on the western side of the Great Dividing Range. While the wind is also strong in coastal areas, wind farms are unlikely to be built there due to existing residential development and national park areas. NSW also has an extensive electricity transmission network, providing relatively good power grid access for new wind farms.
As of March 2015, there was 625 MW of wind power installed in NSW.[2] As of May 2019, there was 1493 MW of wind power installed in NSW.
To measure public attitudes to wind farms, the NSW government surveyed 2000 people and 300 businesses in rural NSW in late 2010. About 80 per cent of respondents said they would strongly support wind farms in their region.[3] Support dropped off somewhat if a wind farm was proposed closer to a person's house but 60 per cent still supported wind turbines within two kilometres of their house. About 13 per cent of people surveyed, many aged over 65, said they did not support wind power.[3]
Wind farms in New South Wales
A list of operating and planned wind farms in New South Wales is below.
Project name | Sponsoring company | Coordinates | Turbines | Capacity (MW) | Status | Completion Date | Notes |
---|---|---|---|---|---|---|---|
Bango Wind Farm | Wind Prospect CWP | 34°20′S 148°28′E / 34.34°S 148.47°E | 46 | 244 | Operating | 2023 | [4][5] First project in Australia to use General Electric 5.3 MW Turbines. |
Black Springs | Wind Corporation | 33°50′28″S 149°42′36″E / 33.841°S 149.71°E | 40 | Cancelled | |||
Blayney Wind Farm[6] | Eraring Energy | 33°37′19″S 149°11′54″E / 33.62194°S 149.19833°E | 15 | 9.9 | Operating | 2000 | |
Boco Rock Wind Farm[7] | Wind Prospect CWP | 36°34′37″S 149°07′26″E / 36.577°S 149.124°E | 67 | 113 | Operating | 2015 | [8] |
Capital Wind Farm[9] | Infigen Energy | 35°08′45″S 149°34′02″E / 35.1458°S 149.5671°E | 67 | 140.7 | Operating | 2009 | [10] |
Collector Wind Farm | RATCH-Australia | 34°51′S 149°23′E / 34.85°S 149.39°E | 55 | 228 | Operating | 2021 | [11] |
Conroys Gap Wind Farm | Epuron | 34°07′41″S 149°46′05″E / 34.128°S 149.768°E | 30 | Planning approved | |||
Cooma | Pacific Hydro | 36°14′24″S 149°07′30″E / 36.24°S 149.125°E | 100 | Feasibility | |||
Crookwell Wind Farm[12] | Tilt Renewables[13] (formerly Eraring Energy) | 34°27′25″S 149°28′19″E / 34.457°S 149.472°E | 8 | 4.8 | Operating | 1998 | |
Crookwell 2 Wind Farm[14] | Unión Fenosa Wind Australia | 34°32′28″S 149°34′12″E / 34.541°S 149.570°E | 46 | 92 | Operating | 2018 | |
Crudine Ridge Wind Farm | Wind Prospect CWP | 32°56′35″S 149°40′41″E / 32.943°S 149.678°E | 37 | 135 | Operating | 2021 | [15] |
Cullerin Range Wind Farm[16] | Epuron (owned by EDL) | 34°53′56″S 149°38′53″E / 34.899°S 149.648°E | 15 | 30 | Operating | 2009 | Developed by Epuron, Built by Origin, sold to EDL[17] |
Gullen Range Wind Farm[18] | Goldwind Australia / JNCEC | 34°36′52.04″S 149°27′34.31″E / 34.6144556°S 149.4595306°E | 73 | 165.5 | Operating | 2013 | |
Gunning Wind Farm[19] | Acciona | 34°41′49″S 149°22′59″E / 34.697°S 149.383°E | 31 | 46.5 | Operating | 2011 | |
Hampton Wind Park[20] | Wind Corporation Australia | 33°38′20″S 150°02′58″E / 33.6388°S 150.0494°E | 2 | 1.32 | Operating | 2001 | |
Kooragang, Newcastle | EnergyAustralia | 32°52′38.94″S 151°44′54.95″E / 32.8774833°S 151.7485972°E | 0.6 | Decommissioned | |||
Liverpool Range | Epuron | 31°52′59″S 149°52′16″E / 31.883°S 149.871°E | 267 | 1000 | Planning approved | Largest proposed wind farm in Australia. | |
Lord Howe Island | 31°33′S 159°05′E / 31.55°S 159.08°E | 0.3 | Feasibility | ||||
Molonglo | Acciona Energy | 35°13′55″S 149°26′46″E / 35.2319°S 149.446°E | 120 | Cancelled | |||
Mt Spring | ActewAGL | 33°23′53″S 149°09′07″E / 33.398°S 149.152°E | 10 | Cancelled | |||
Paling Yards | Unión Fenosa Wind Australia | 35°08′38″S 149°01′19″E / 35.144°S 149.022°E | 60 | 204 | Feasibility | [21] | |
Rock Flat Creek | Pacific Hydro | 36°09′29″S 149°12′36″E / 36.158°S 149.21°E | 100 | Feasibility | |||
Rye Park Wind Farm | Epuron | 34°34′S 148°58′E / 34.57°S 148.96°E | 92 | 276 | Planning approved | Sold to Tilt Renewables. Original total of turbines reduced from 126 to 109.[22] 92 turbines have been approved. | |
Sapphire Wind Farm[23] | CWP Renewables | 29°45′S 151°29′E / 29.75°S 151.49°E | 75 | 270 | Operating | 2018 | Completed as of 31 October 2018.[24] |
Silverton Wind Farm | Epuron | 31°58′S 141°28′E / 31.97°S 141.46°E | 58 | 200 | Operating | 2019 | |
Snowy Plains Wind Farm (Berridale) | Epuron | 36°09′14″S 148°33′54″E / 36.154°S 148.565°E | 26 | Cancelled 2010[25] | |||
Taralga Wind Farm | CBD Energy/Banco Santander | 34°25′37″S 149°51′28″E / 34.427076°S 149.857640°E | 51 | 107 | Operating | 2015 | |
Uungula | Wind Prospect CWP | 32°30′50″S 149°16′23″E / 32.514°S 149.273°E | 125 | 400 | Feasibility | [26] | |
White Rock Wind Farm | Goldwind Australia/ CECEP | 29°47′S 151°32′E / 29.78°S 151.54°E | 70 | 175 (Stage 1) | Operating | 2018 | Approval for up to 119 WTGs.[27] |
Woodlawn Wind Farm[28] | Infigen Energy | 35°05′02″S 149°37′12″E / 35.084°S 149.62°E | 23 | 48.3 | Operating | 2011 | |
Coppabella Wind Farm | Epuron | 34°44′10″S 148°33′18″E / 34.736°S 148.555°E | 75 | 284 | Planning approved | Sold to Goldwind.[29] | |
Bodangora Wind Farm[30] | Infigen Energy | 32°26′42″S 149°02′24″E / 32.445°S 149.04°E | 33 | 113.2 | Operating | 2019 | 33 GE 3.4-130 Turbines[31] |
Bowmans Creek Wind Farm | Epuron | 32°15′47″S 151°05′53″E / 32.263°S 151.098°E | 250+ | Feasibility | [32] | ||
Flyers Creek Wind Farm | Infigen Energy | 38 | 145 | Under construction | [33] | ||
Biala Wind Farm | BJCE Australia | 31 | 110 | Operating | 2021 | [34] | |
Granite Hills Wind Farm | Akuo Energy | 132 | Feasibility | [35] | |||
Hills of Gold Wind Farm | Wind Energy | 98 | 400 | Feasibility | [36] | ||
Jupiter Wind Farm | EPYC Pty Ltd | 350 | Cancelled | [37] | |||
Upper Hunter Energy Park | Upper Hunter Energy Park Pty Ltd | 34 | Feasibility | [38] | |||
See also
References
- ↑ "Archived copy" (PDF). Archived from the original (PDF) on 19 February 2011. Retrieved 22 May 2010.
{{cite web}}
: CS1 maint: archived copy as title (link) - ↑ AEMO Electricity Registration List
- 1 2 Ben Cubby (25 March 2011). "Turbines take their turn". Sydney Morning Herald.
- ↑ "Project Description – Bango Wind Farm". bangowindfarm.com.au. Retrieved 30 August 2021.
- ↑ Mazengarb, Michael (12 August 2019). "Huge Bango wind farm gets underway, to provide cheap power to Snowy Hydro". RenewEconomy. Retrieved 12 August 2019.
- ↑ "Blayney - Eraring Energy". Archived from the original on 12 November 2010. Retrieved 16 August 2010.
- ↑ "Facts & figures - - Boco Rock Wind Farm". bocorockwindfarm.com.au. Archived from the original on 16 October 2009.
- ↑ "SERREE". serree.org.au. Retrieved 1 July 2019.
- ↑ "Our Business - Infigen Energy". www.infigenenergy.com. Archived from the original on 8 August 2011.
- ↑ "NSW Wind Farms". Retrieved 22 September 2018.
- ↑ "Collector Wind Farm". Collector Wind Farm. Retrieved 30 August 2021.
- ↑ "Crookwell - Eraring Energy". Archived from the original on 29 September 2009. Retrieved 5 June 2010.
- ↑ "Crookwell Wind Farm". Tilt Renewables. Retrieved 23 September 2019.
- ↑ "Union Fenosa Wind Australia". Archived from the original on 6 March 2013. Retrieved 15 January 2013.
- ↑ "Crudine Ridge Wind Farm". Crudine Ridge Wind Farm. Retrieved 30 November 2021.
- ↑ "Electricity Generation - Origin Energy". 16 June 2021.
- ↑ "Cullerin Range | Epuron". epuron.com.au. Retrieved 1 July 2019.
- ↑ "Project Update « Gullen Range Windfarm". Archived from the original on 13 April 2013. Retrieved 15 January 2013.
- ↑ "ACCIONA Australia - Gunning Wind Farm". www.acciona.com.au. Archived from the original on 21 April 2013.
- ↑ "CEC - Hampton Wind Park". Archived from the original on 6 March 2012. Retrieved 17 December 2011.
- ↑ "Paling Yards Wind Farm" (PDF). Retrieved 13 November 2018.
- ↑ "Rye Park Wind Farm" (PDF). May 2018. Retrieved 22 September 2018.
- ↑ "Welcome | Online Community Consultation | Sapphire Wind Farm". sapphirewindfarm.com.au. Retrieved 30 June 2016.
- ↑ "Construction Update – Sapphire". www.sapphirewindfarm.com.au. Retrieved 11 November 2018.
- ↑ "WindAction | Snowy Plains wind farm falls through". www.windaction.org. Retrieved 22 September 2018.
- ↑ "Planning and Approvals – Uungula Wind Farm". uungulawindfarm.com.au. Retrieved 22 September 2018.
- ↑ "White Rock Wind Farm switches on turbines" (PDF). 10 July 2017. Retrieved 22 September 2018.
- ↑ "Woodlawn Wind Farm - Infigen Energy". www.infigenenergy.com. Archived from the original on 18 May 2013.
- ↑ "MEDIA RELEASE: Sale of Yass Valley (Coppabella) to Goldwind". 1 February 2017. Retrieved 22 September 2018.
- ↑ "Bodangora Wind Farm | Iberdrola Energy".
- ↑ "Bodangora - Infigen Energy". www.infigenenergy.com. Retrieved 22 September 2018.
- ↑ "Bowmans Creek". epuron.com.au. Retrieved 13 November 2018.
- ↑ "Wind Energy Projects - Infigen Energy". www.infigenenergy.com. Retrieved 13 November 2018.
- ↑ "Biala Wind Farm". Retrieved 30 August 2021.
- ↑ "About – Granite Hills Wind Farm". Retrieved 1 July 2019.
- ↑ "About the Project". hills-of-gold-energy. Retrieved 1 July 2019.
- ↑ Vorrath, Sophie (19 March 2018). "Jupiter wind farm plans abandoned in face of community opposition". RenewEconomy. Retrieved 1 July 2019.
- ↑ "Upper Hunter Energy Park". Pamada. Retrieved 1 July 2019.