Xingu-Rio | |
---|---|
Location | |
Country | Brazil |
General direction | North-South |
From | Xingu substation, Anapu, Pará |
To | Terminal Rio substation, Paracambi, Rio de Janeiro |
Construction information | |
Commissioned | 22 August 2019 |
Technical information | |
Type | overhead transmission line |
Type of current | HVDC |
Total length | 2,543.4 km (1,580.4 mi) |
Power rating | 4000 MW[1] |
DC voltage | 800 kV |
The Xingu-Rio HVDC transmission line is a 2543.4 km long 800 kV high-voltage direct current transmission line in Brazil between the Xingu substation at the city of Anapu in the Pará state, 17 km from the Belo Monte Dam, and the Terminal Rio substation at the city of Paracambi in the Rio de Janeiro state. It was inaugurated 22 August 2019.[2][3]
See also
References
- ↑ "XRTE receives LO to start operations". 2019-07-01. Retrieved 2023-01-22.
- ↑ Cardoso Júnior, Ricardo Abranches Felix; Garcia Neto, Edgard Villarinho; Hongxian, Cai; Leal, Anselmo; Amorim, Anne Luise (2020). A XRTE e o Meio Ambiente (PDF) (in Brazilian Portuguese). ISBN 978-65-00-00641-4. Retrieved 2022-01-17.
- ↑ "AVISO DE LICENÇA". Diário Oficial da União (in Brazilian Portuguese). Imprensa Nacional (130): 114. 9 July 2019. ISSN 1677-7069. Retrieved 2022-01-17.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.