Rangit Dam
Rangit Dam and Reservoir
Rangit Dam is located in Sikkim
Rangit Dam
Location of Rangit Dam in Sikkim
Official nameRangit Hydropower Project, Stage III
LocationLegship, Sikkim, India
Coordinates27°17′41″N 88°17′32″E / 27.29472°N 88.29222°E / 27.29472; 88.29222
Opening dateJanuary 2000
Owner(s)NHPC
Operator(s)National Hydroelectric Power Corporation
Dam and spillways
Type of damConcrete Gravity
ImpoundsRanjit River
Height45 metres (148 ft)
Length100 metres (330 ft)
Spillway typeGated Overflow
Spillway capacity2725 m³/s
Reservoir
CreatesRangit Reservoir
Total capacity1.175 million cubic metres
Catchment area979 square kilometres (378 sq mi)
Surface area12.9 hectares (32 acres)
Power Station
Operator(s)National Hydroelectric Power Corporation
Commission dateJanuary 2000
TypeRun-of-the-river
Turbines3×20 MW
Installed capacity60 MW
Annual generation340 GWh (Firm Power 39 MW)

Rangit Dam (Hindi: रन्गीत् बाँध Bāndh), which forms the headworks of the Rangit Hydroelectric Power Project Stage III, is a run-of-the-river hydroelectric power project on the Ranjit River, a major tributary of the Teesta River in the South Sikkim district of the Northeastern Indian state of Sikkim. The project's construction was completed in 1999. The project is fully functional since 2000. The project was built at a cost of Rs 4922.6 million (Rs 492.26 crores) (at US$1 = Rs 45, this is US$109.39 million).[1] The average annual power generation from the 60 MW (3x20 MW) project is 340 GWh with firm power of 39 MW.[1][2][3][4][5]

Topography

Left: Confluence of Rangeet River and Rathong chu rivers upstream of the Rangit Dam. Right: A chorten above the confluence of the two rivers

The Ranjit River on which the Rangit Dam is located, is a major right bank tributary of the Teesta River in Sikkim. The river arises from the Talung glacier and it meets the Teesta river at Melli after a travel of 61 kilometres (38 mi) from its source. At the dam site, the catchment area drained is 979.02 square kilometres (378.00 sq mi) (rain-fed catchment is 712 square kilometres (275 sq mi) and the balance area is snow fed above snow line contour of (4,570 metres (14,990 ft)); elevation of the catchment area varies from about 600 metres (2,000 ft) to about 7,338 metres (24,075 ft) (North Kabru Peak) and is delimited between (27°16′30″N 88°00′51″E / 27.275°N 88.0141°E / 27.275; 88.0141) and (27°37′10″N 88°25′12″E / 27.6195°N 88.42°E / 27.6195; 88.42). A number of perennial streams originate in glacial fields of the river basin; important snow-fed rivers which constitute the Rangit basin above the dam site are the Rathong Chu, Rimbi Chu, Prek Chu, Ralli Chu, Rongdon Chu and Kayam Chu. The drainage pattern is sub-dendentric.[6]

The dam is located at a distance of 130 kilometres (81 mi) from Siliguri and70 kilometres (43 mi) from Gangtok. The dam is located downstream of the confluence of Rathong Chu and Rangit Rivers near the Legship town and the powerhouse of the project is located near Sagbari village.[2][3]

Hydrology

The annual inflow in the river at the location of the dam has been estimated as 696,000 cubic metres. The maximum flood discharge has been adopted as 3,395 cubic metres (119,900 cu ft)/s while the design flood discharge adopted for the spillway of the dam is 2,725 cubic metres (96,200 cu ft)/sec. The dependable discharge adopted for diversion from the reservoir for power generation is 1717.8 cubic metres (630 cu ft)/s (without considering contribution from the upstream Stage II project, which is yet to be implemented).[2][3]

Climate

The climate of the Rangit River basin is cold and humid. The climatic seasons of the basin represented in the project area are: spring season-late February, summer season-March, premonsoon showers-April and May; monsoon season May to September, sometimes extending to October. The snow season, at higher elevations of the catchment falls between December and February. Winters are very cold with mist and fog lasting from November to February.[6]

Geology

Precambrian formations of the Daling series of quartzites and phyllites dominate the area. This rock type is overlain by crystalline Darjeeling Gneiss comprising gneisses and granitoides. Recent alluvium of sandy loam, silty loam and clayey material of varying thickness overlay the rock formations. The banks of the Rangit River depict silty clay material with large rock blocks. Many land slides are observed in the catchment, which add to the siltation problems of the reservoir.[6]

Project features

Aerial View of Ranjit Dam and appurtenant works

The Rangit dam is 45 metres (148 ft) high concrete gravity structure of 100 metres (330 ft) length. The reservoir created behind the dam has a storage capacity of 1,175,000 cubic metres. The storage created is utilized for hydropower generation at a surface Powerhouse located on the left bank of the Rangit River. The diversion of flow from the reservoir to the surface Powerhouse is effected through an Intake leading to a concrete lined Head Race Tunnel (HRT) of 4.5 metres (15 ft) diameter (Horse shoe shaped and concrete lined) of 3 kilometres (1.9 mi) length, a Surge Shaft (14 metres (46 ft) diameter and of 60 metres (200 ft) depth at the end of the HRT with control arrangement followed by one main penstock pipe (of 3.5 metres (11 ft) diameter and length of 270 metres (890 ft)) trifurcating into three lines of 2 metres (6.6 ft) diameter each (with a total length of all three lines is 59 metres (194 ft)) to connect to the three Francis Turbine Generating Units of 20 MW capacity each, through the MIVs. The tailwaters from the turbines are led back into the river through a combined short tailrace channel. The firm power generation is of the order of 39 MW corresponding to annual energy generation of 340 GWh (in a 90% dependable year). The ruling levels for power generation are: in the reservoir, Full Reservoir Level (FRL) of 639 metres (2,096 ft) and Minimum Draw Down Level (MDDL) of 627 metres (2,057 ft)), the Normal Tail Water Level (NTWL) in the Tail Race Channel from the Powerhouse of 512 m and under an operating gross head of 127 m.[2][3][4] Since it is owned by coastal projects ltd, the power generated is shared and Sikkim gets a share of 13.33%.[7]

The project was funded by the Government of India and built by its parastatal organization namely, the National Hydroelectric Power Corporation (NHPC). The construction of the project was completed in December 1999 and operation started in January 2000. Operation and maintenance of the project is also with the NHPC.[2]

This power project was the third stage of the five-stage cascade development conceived on the main stem of the Rangit River, and was the first to be built in the series of Rangit Stage I to IV initially conceived by the Central Water Commission. Three other projects on the Rangit River planned and under development are the Rangit Stage II (60 MW capacity), Rangit Stage IV (3×40 MW = 120 MW capacity) and Jorethong HEP (96 MW); the last two projects are now under construction.[8][9][10]

Environmental aspects

Panoramic view of Rangit Dam and Reservoir on Rangit

In river valley reservoir projects, the gravity of the siltation problem induced due to catchment degradation is serious and needs to be suitably addressed. For this purpose, the Ministry of Environment and Forests, Government of India have made it obligatory for the project authorities to implement physical engineering and biological measures in the catchment area of the project to be taken up pari passu (concurrently) with the implementation of the Hydropower project. This activity involves several works defined under the 'Catchment Area Treatment' (CAT) plan.[11]

For evolving the CAT plan, the status of the reservoir catchment was analysed. The reservoir catchment consists of five types of forests namely, the East Himalayan Sub-Tropical wet hill forests (elevation range of 800–1,800 metres (2,600–5,900 ft)), East Himalayan wet temperate forests (elevation range of 1,800–2,700 metres (5,900–8,900 ft)), Oak and Rhododendron forests (elevated above 2,700 metres (8,900 ft)), mixed coniferous forests (in elevation range of 2,700–3,750 metres (8,860–12,300 ft)) and alpine scrubs/pastures (above 3,750 metres (12,300 ft)). There are 35 reserve forests in the catchment, out of which 29 are in West Sikkim district and six (6) are in South Sikkim district. The entire catchment area was analysed in detail to assess the degraded areas to be treated under the CAT plan to reduce siltation problems. An area of 13,075 hectares (32,310 acres)) was identified for implementing engineering and biological treatment measures. These measures were implemented, starting with 1995–96, by the Forest Department of the Government of Sikkim involving engineering treatment measures (included agricultural land, forest land and water land) and biological treatment measures. 15 nurseries were established covering an area of 18.5 hectares (46 acres)) to provide saplings/seedlings for plantation in the sub-watersheds of the catchment identified for treatment.[12]

Recreation

The reservoir created by the Rangit dam has been developed into a recreational water park named 'Rangit Water World'. It is a popular venue for picnics, fishing, boating and rafting. The recreational centre was developed due to the initiative of the local people of Legship town.[13][14]

See also

Notes

  1. 1 2 "Welcome to Rangit Power Station". NHPC Limited. Retrieved 6 June 2010.
  2. 1 2 3 4 5 Kaushish, S.P.; B. S. K. Naidu (2002). Silting Problems in Hydropower Plants. Taylor & Francis. pp. 9–19. ISBN 90-5809-238-0. Retrieved 31 May 2010.
  3. 1 2 3 4 Jain, Sharad K.; Pushpendra K. Agarwal; Vijay P. Singh (16 May 2007). Hydrology and Water Resources of India. Springer. p. 464. ISBN 9781402051807. Retrieved 31 May 2010.
  4. 1 2 "Hydroelectric Power Plants in India – Northeast". Rangit. Powerplants around the World. Retrieved 31 May 2010.
  5. "Rangit Power Station". Scribd. Retrieved 2 June 2010.
  6. 1 2 3 Kaushish, p.12
  7. "Energy & Power Department Government of Sikkim" (PDF). Government of Sikkim. p. 3. Retrieved 3 June 2010.
  8. "Jorethang Loop HE Project". Dans Energy. Retrieved 2 June 2010.
  9. "Project". Jal Power Corporation Ltd. Retrieved 2 June 2010.
  10. "Gammon initial offering to fund India's 66-MW Rangit 2". Hydroworld. Retrieved 2 June 2010.
  11. Kaushish, p.10
  12. Kaushish, pp.15–17
  13. "South Sikkim" (PDF). Digital Himalaya. Retrieved 2 June 2010.
  14. "Legship". Archived from the original on 14 June 2006. Retrieved 2 June 2010.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.